Grand Coulee Dam Left and Right Powerplants G1-G18 Penstock Lining Rehabilitati
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 140R1020R0013
- Agency
-
Bureau of Reclamation
Department of the Interior
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- More information
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice seeks penstock lining rehabilitation services at the Grand Coulee Dam located in Washington state. The Department of Interior Bureau of Reclamation requires spot repairs, zone repairs, full lining removal and replacement, and removal/reinstallation of flowmeters on eleven penstocks. Bidders must be registered in the System for Acquisition Management. The period of performance is 78 months. The solicitation will be issued on or around May 20, 2020 and available on beta.sam.gov and fedconnect.net.
The procurement is set aside for total small business and has a NAICS code of 237990 for specialty trade contractors with a size standard of $39.5 million in average annual receipts. The order of magnitude for this project is estimated between $10-25 million. Rehabilitation is required on penstocks G1 through G18, including complete relining of seven penstocks and flowmeter removal/replacement on four penstocks. Prospective contractors must be registered in SAM and the solicitation will be issued on or around May 20, 2020.
Notice text
Synopsis for Solicitation 140R1020R0003:
The Department of Interior, Bureau of Reclamation, Columbia Pacific-Northwest Region requires Penstock Lining Rehabilitation at the Grand Coulee Dam, adjacent to the cities of Grand Coulee and Coulee Dam in Grant and Okanogan Counties. Location is approximately 90 miles west of Spokane, WA. Principle components of work include Penstock Lining Repairs and Replacement of eleven (11) penstocks, Complete lining removal and re-lining of the penstock interiors for seven (7) penstocks, and the Removal/re-installation of the surface-mounted flowmeters and associated conduits to facilitate access to the penstock surface units on four (4) penstocks.
Penstock Lining Repairs and Replacement:
Minimum of Spot and Zone lining repairs of the following Units¿ penstock interiors. The Government will inspect the following penstock interiors within 7 calendar days after the start of the respective penstock¿s outage. The Government reserves the right to exercise the option CLIN pertaining to the respective penstock within 14 calendar days after the start of the respective penstock¿s outage.
1) G1.
2) G2.
3) G3.
4) G5.
5) G6.
6) G7.
7) G8.
8) G9.
9) G11.
10) G12.
11) G16.
b. Complete lining removal and re-lining of the penstock interiors for Units:
1) G4.
2) G10.
3) G13.
4) G14.
5) G15.
6) G17.
7) G18.
c. Removal and re-installation of the surface-mounted flowmeters and associated conduits to facilitate access to the penstock surface in Units:
1) G2.
2) G8 (if full relining is implemented)
3) G9.
4) G12.
It is expected the period of performance (POP) will be 78 months. The North American Industry Classification System (NAICS) code associated with this project is 237990. The small business size standard applicable to this project is $39.5 million in gross annual receipts averaged over the previous three 1-year accounting periods. The order of magnitude for this project is between $10,000,000 and $25,000,000. Prospective contractors shall be registered in the System for Acquisition Management (SAM). For more information regarding registering in SAM, please visit https://www.sam.gov/portal/public/SAM/. Contractors shall note that this procurement will be issued approximately on or around May 20, 2020. When the solicitation is issued it will be available electronically at beta.sam.gov AND www.fedconnect.net.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Grand Coulee Dam Left and Right Powerplants G1-G18 | Award Notice | |
| Grand Coulee Dam Left and Right Powerplants G1-G18 | Solicitation | |
| This notice | Pre-Solicitation | |
| Grand Coulee Dam Left and Right Powerplants G1-G18 Penstock Lining Rehabilitati | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Bonneville Powerhouse II Unwatering Pump Replacement | ENDIST Portland | Total Small Business | |
| LLA Navigation Lock Switchgear | ENDIST Walla Walla | Total Small Business | |
| East Bear Creek Pumping Plant and Pipeline Moderni | — | No set-aside | |
| John day DAM unit 10 packing box replacement | ENDIST Portland | No set-aside | |
| White Horse Hill National Game Preserve Water Main Extension | — | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity