The Department of Energy Western Area Power Administration seeks construction of the Glendo-Lusk Rural Tap 115kV Transmission Line Upgrade and new Quinn Creek Substation, with proposals due August 21. The procurement carries no set-aside.

The projects enhance WAPA's ability to provide reliable and cost-efficient electric power and address deteriorating conditions on the existing Glendo-Lusk Rural Tap 69kV line. The NAICS code is 237130, Power and Communication Line and Related Structures Construction; the PSC is Y1PZ, Construction Of Other Non-Building Facilities.

Three amendments have been issued. Amendment 0001 added KMZ files and industry Q&A. Amendment 0002 extended the solicitation close date, updated the bid schedule, specifications with redline changes, drawings, KMZ files, and geotechnical report, and added Q&A. Amendment 0003 updated Q&A, added specifications, and extended both the solicitation close date and the bid opening date.

Notice text

4 versions

Update #4 · Latest ·

Amendment (0003) Update Q/A, add Specifications 1 of 1, Specifications 5 of 10, Extend Solicitation Close Date, Bid Opening date as part of the Glendo-Lusk Rural Tap 115kV Transmission Line Upgrade and Quinn Creek Substation project.

Update #3 ·

Amendment (0002) Extend Solicitation Close Date, Update Bid Schedule, Specifications W/redline changes, Drawings, KMZ files, Geotechnical Report, and Q/A from industry.

Update #2 ·

Amendment (0001) to add KMZ files and post Q/A from industry for the Glendo-Lusk Rural Tap 115kV Transmission Line Upgrade and Quinn Creek Substation project.

Update #1 ·

The Glendo-Lusk Rural Tap 115kV Transmission Line Upgrade and new Quinn Creek Substation projects aim to enhance WAPA’s ability to provide reliable and cost-efficient electric power, aligning with WAPA’s mission. WAPA benefits from the transmission line upgrades by resolving deteriorating conditions on the existing Glendo – Lusk Rural Tap 69kV line.

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Glendo-Lusk Rural Tap 115kV Transmission Line Upgrade and Quinn Creek Substation Original Pre-Solicitation