Gate Stem Repairs, West Thompson Lake, North Grosvenordale, CT

Closed Pre-Solicitation Posted

Not the latest version. See the latest solicitation from .

Solicitation number
W912WJ23B0005
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
North Grosvenordale, Connecticut, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice seeks certified small business contractors to perform repairs to three hydraulic gate assemblies at West Thompson Lake in North Grosvenordale, Connecticut. The U.S. Army Corps of Engineers, New England District will procure these services with an estimated value between $1 million to $5 million and a period of performance of approximately 365 days. The repairs include refurbishing hydraulic cylinders, replacing various gate stem components, and upgrading the digital gate height indicator system. Contractors must submit a dewatering plan and verify the condition of stop log channels to ensure safe working conditions during the project. Questions are due by May 17, 2023, with the full solicitation to be issued in May and responses due in 2023.

The procurement is set aside only for small businesses meeting a size standard of $45 million defined under NAICS code 237990. Stop logs and a lifting beam must be fabricated and installed. Work will be completed one gate at a time to ensure at least one conduit remains operational. The current incumbent is unavailable as this pre-solicitation notice is the first stage to identify potential contractors for this requirement.

Notice text

The U.S. Army Corps of Engineers, New England District is issuing a set aside for certified small business contractors for Repairs to Hydraulic Gate Assemblies at West Thompson Lake in North Grosvenordale, Connecticut. The NAICS code for the work described below is 237990 with a size standard of $45M. The project is planned to be issued in May 2023 and will be set aside for Small Businesses.  The period of performance will be approximately 365 days.   The estimated magnitude of this project is between $1,000,000 and $5,000,000.

There are three hydraulically operated gates located in the Intake Tower at West Thompson Dam located in North Grosvenordale, CT. The dam and its operating equipment are approximately 58 years old and therefore the gate cylinder and gate assembly components are beginning to show signs of wear.  The work for this project will likely include, but not be limited to, the following:

  • Refurbish all three hydraulic cylinders located in the gate chamber
  • Replace gate leaf stems
  • Polish gate stem extension rods
  • Hone inside of hydraulic cylinder barrel
  • Replace lower/upper gate stem oil packings and gate stem water packings
  • Replace middle piston ring with rubber seal
  • Replace cylinder gaskets and gate stem O-rings
  • Replace digital gate height indicator system, including transducers, digital displays, and wiring/conduit
  • Remove the middle piston ring on both pistons and replace with a new hydrolysis resistant polyurethane (HPU) piston seal manufactured to operate within specified hydraulic fluid type, pressures, and temperatures. 
  • New composite stop logs and lifting beam shall be fabricated and new stop logs shall be installed prior to the start of construction. Stop logs shall be of equivalent dimensional size, quantity, and strength and shall be designed by a Registered professional Engineering in the State of Connecticut. Upon completion of the work, the stop logs and lifting beam shall be turned over to the Government.

The Contractor will be required to coordinate operational restrictions with the Contracting Officer’s Representative and onsite personnel. Proper work sequencing will be critical for project success. Full dewatering of the conduits may be required to perform work. Contractor shall field verify extent of dewatering requirements to obtain safe working conditions and to ensure that the space below the bonnet cover is not pressurized prior to any work beginning.  Contractor shall then coordinate sufficient time ahead of required dewatering to allow for local personnel to draw down the existing pool elevation.

A 5-ton capacity crane rail is located on the operating floor; however, the electric operated hoist system shown on the record drawings has since been removed. The Contractor may use the existing crane rail to develop a hoist system to assist in the disassembly and assembly of the hydraulic cylinders.  Prior to use, a competent person, employed by the Contractor, shall verify the rail capacity and confirm the proposed hoisting system will be compatible with the crane rail. The Contractor shall refer to EM-385-1-1, Section 16, Load Handling Equipment and Section 15, Rigging, for additional requirements.

Work shall be done on only one gate at a time and at no time shall more than one conduit be out of service. One conduit at a time can be isolated at the upstream end by use of a stop log system.    The Contractor shall be responsible for verifying the condition of the stop log channels and providing stop logs to be used for this project.  The Contractor shall submit a plan for utilizing stop log systems to ensure safe and reliable operation for dewatering the conduit for approval to the Contracting Officer prior to proceeding with work.

Please note that this solicitation is set aside for certified small businesses. This is not a request for proposals at this time; the solicitation requirements and contract documents which will include instructions for submission and the response date will be available on or about May 2023. Neither telephonic, mailed, nor faxed requests for hard copies of this solicitation will be accepted. The solicitation will only be available online; in order to view the solicitation offerors must access the System for Award Management website (www.sam.gov). In order to download the solicitation, offerors must access the Procurement Integrated Enterprise Environment (https://piee.eb.mil/). All responsible sources may submit a bid which shall be considered by the USACE New England District. Additional questions may be emailed to the Contract Specialist tyler.s.maryak@usace.army.mil.

Notice history

Notice Type Posted
Gate Stem Repairs, West Thompson Lake, North Grosvenordale, CT Latest solicitation Solicitation
This notice Pre-Solicitation
Gate Stem Repairs, West Thompson Lake, North Grosvenordale, CT Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Dike B Generator Installation, Mansfield Hollow Dam, Mansfield Center, CT Mansfield Center, Connecticut, United States · NAICS 238290 ENDIST New England Total Small Business
W9127N27BA005 Foster Spillway Gate Nut Replacements and Re-Tensioning Foster Dam, Linn County, Oregon 93745 · NAICS 237990 ENDIST Portland Total Small Business
Float Well Pipe Repairs, Surry Mountain Dam, Surry, NH Surry, New Hampshire, United States · NAICS 237990 ENDIST New England No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors