FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912DR23B0018
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Maryland 21201, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The contract involves maintenance dredging of approximately 1,400,000 cubic yards from the federal navigation channels serving the Port of Baltimore, with work to be performed between November 2023 and March 2024. The dredged material will be placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island and the Cox Creek Dredged Material Containment Facility. The estimated cost of the project is between $10,000,000.00 and $25,000,000.00, with a performance period of approximately 120 days from receipt of Notice-to-Proceed.

List of Products and Services:

  1. Maintenance dredging of approximately 1,400,000 cubic yards from the federal navigation channels.
  2. Placement of dredged material at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island and the Cox Creek Dredged Material Containment Facility.
  3. Use of two 30 plus cubic yard clamshell dredges, one 24-30 inch hydraulic unloader, six to eight large tugs, six to eight 2,500-6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline.
  4. Completion of work within a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed.

Notice text

3 versions

Update #3 · Latest ·

*** ABSTRACT OF BIDS

*****************************************************

*** AMD 0001 10-6-23 *** FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD. The project consists of maintenance dredging approximately 1,400,000 cubic yards (cy) from the deep-draft federal navigation channels serving the Port of Baltimore. The work is to be performed between November 2023 through March 2024.The dredging depth varies by channel segment and ranges from 35 feet mean lower low water (ft MLLW) to 50 ft MLLW with an additional 1 foot of allowable overdepth. Approximately 1,000,000 cy will be dredged from the Maryland approach channels (Brewerton Channel Eastern Extension) and placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island. Approximately 400,000 cy will be dredged from Baltimore Harbor channels (Curtis Bay Channel) and placed at the Cox Creek Dredged Material Containment Facility. The estimated magnitude of construction is between $10,000,000.00 and $25,000,000.00. The work areas are within heavy commercial waterways supporting the Port of Baltimore. The equipment required for this work commonly consists of two 30 plus cubic yard clamshell dredges, one 24 ? 30-inch hydraulic unloader, six to eight large tugs, six to eight 2,500 ? 6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline. The material will be dredged by clamshell/bucket and scow and placed within a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed.

Update #2 ·

*** AMD 0001 10-6-23 *** FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD. The project consists of maintenance dredging approximately 1,400,000 cubic yards (cy) from the deep-draft federal navigation channels serving the Port of Baltimore. The work is to be performed between November 2023 through March 2024.The dredging depth varies by channel segment and ranges from 35 feet mean lower low water (ft MLLW) to 50 ft MLLW with an additional 1 foot of allowable overdepth. Approximately 1,000,000 cy will be dredged from the Maryland approach channels (Brewerton Channel Eastern Extension) and placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island. Approximately 400,000 cy will be dredged from Baltimore Harbor channels (Curtis Bay Channel) and placed at the Cox Creek Dredged Material Containment Facility. The estimated magnitude of construction is between $10,000,000.00 and $25,000,000.00. The work areas are within heavy commercial waterways supporting the Port of Baltimore. The equipment required for this work commonly consists of two 30 plus cubic yard clamshell dredges, one 24 ? 30-inch hydraulic unloader, six to eight large tugs, six to eight 2,500 ? 6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline. The material will be dredged by clamshell/bucket and scow and placed within a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed.

Update #1 ·

FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD. The project consists of maintenance dredging approximately 1,400,000 cubic yards (cy) from the deep-draft federal navigation channels serving the Port of Baltimore. The work is to be performed between November 2023 through March 2024.The dredging depth varies by channel segment and ranges from 35 feet mean lower low water (ft MLLW) to 50 ft MLLW with an additional 1 foot of allowable overdepth. Approximately 1,000,000 cy will be dredged from the Maryland approach channels (Brewerton Channel Eastern Extension) and placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island. Approximately 400,000 cy will be dredged from Baltimore Harbor channels (Curtis Bay Channel) and placed at the Cox Creek Dredged Material Containment Facility. The estimated magnitude of construction is between $10,000,000.00 and $25,000,000.00. The work areas are within heavy commercial waterways supporting the Port of Baltimore. The equipment required for this work commonly consists of two 30 plus cubic yard clamshell dredges, one 24 ? 30-inch hydraulic unloader, six to eight large tugs, six to eight 2,500 ? 6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline. The material will be dredged by clamshell/bucket and scow and placed within a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed.

Files

Notice history

Similar open opportunities

Opportunity Agency Set-aside Responses due
Calcasieu Bar River Channel, Pascagoula Harbor, and Panama City Harbor Maintenance Dredging 70601 · NAICS 237990 ENDIST Wilmington No set-aside
Jacksonville Harbor Maintenance Dredging 32202 · NAICS 237990 ENDIST Wilmington No set-aside
Mid-Bay James Island Restoration Phase 2 Dorchester County, Maryland 21634 · NAICS 237990 ENDIST Baltimore No set-aside
Mississippi River Southwest Pass and Calcasieu River Bar Channel Hopper Dredge Contract (OM25011) Plaquemine, Louisiana, United States · NAICS 237990 ENDIST New Orleans No set-aside
Reserve basin maintenance dredging contract for sites at the phildelphia navy yard in the public works department pennsylvania area of responsibiliy Philadelphia, Pennsylvania 19112, United States · NAICS 237990 Naval Facilities Engineering Command No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors