FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912DR23B0018
- Agency
-
ENDIST Baltimore
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Z1KF Maintenance Of Dredging Facilities
- Place of performance
- Baltimore, Maryland 21201, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The project involves maintenance dredging of approximately 1,400,000 cubic yards from the federal navigation channels serving the Port of Baltimore, to be performed between November 2023 and March 2024. The dredged material will be placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island and the Cox Creek Dredged Material Containment Facility. The estimated cost of the project is between $10,000,000.00 and $25,000,000.00, with a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed.
- Maintenance dredging of navigation channels.
- Placement of dredged material at designated locations.
- Use of specific equipment including clamshell dredges, a hydraulic unloader, tugs, material scows, a drag bar and barge, and attendant plant and pipeline.
- Work to be performed within a specific timeframe (November 2023 - March 2024).
- Compliance with heavy commercial waterways regulations.
Notice text
Project Name: FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay,
MD
The project consists of maintenance dredging approximately 1,400,000 cubic yards (cy) from the deep-draft federal navigation channels serving the Port of Baltimore. The work is to be performed between November 2023 through March 2024.
The dredging depth varies by channel segment and ranges from 35 feet mean lower low water (ft MLLW) to 50 ft MLLW with an additional 1 foot of allowable overdepth. Approximately 1,000,000 cy will be dredged from the Maryland approach channels (Brewerton Channel Eastern Extension) and placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island. Approximately 400,000 cy will be dredged from Baltimore Harbor channels (Curtis Bay Channel) and placed at the Cox Creek Dredged Material Containment Facility.
The estimated magnitude of construction is between $10,000,000.00 and $25,000,000.00. The work areas are within heavy commercial waterways supporting the Port of Baltimore. The equipment required for this work commonly consists of two 30 plus cubic yard clamshell dredges, one 24 – 30-inch hydraulic unloader, six to eight large tugs, six to eight 2,500 – 6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline. The material will be dredged by clamshell/bucket and scow and placed within a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed.
Notice history
| Notice | Type | Posted |
|---|---|---|
| FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD | Award Notice | |
| FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD | Solicitation | |
| This notice | Pre-Solicitation | |
| FY24 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Calcasieu Bar River Channel, Pascagoula Harbor, and Panama City Harbor Maintenance Dredging | ENDIST Wilmington | No set-aside | |
| Jacksonville Harbor Maintenance Dredging | ENDIST Wilmington | No set-aside | |
| Mid-Bay James Island Restoration Phase 2 | ENDIST Baltimore | No set-aside | |
| Mississippi River Southwest Pass and Calcasieu River Bar Channel Hopper Dredge Contract (OM25011) | ENDIST New Orleans | No set-aside | |
| Annual Maintenance Dredging of Morehead City Inner Harbor | ENDIST Wilmington | No set-aside |
On GovTribe