Fountain City Service Base Sustainment & Modernization
Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912ES21R0005
- Agency
-
ENDIST St Paul
US Army Corps of Engineers, Department of Defense
- Responses due
- Not on record
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
Notice details come from SAM.gov. Updated .
About this opportunity
The St. Paul District of the Army Corps of Engineers is planning a two-step design-build solicitation for the design and construction of a 1,400 linear foot straight-line mooring solution at the Corps' Fountain City Service Base in Fountain City, Wisconsin. The Corps will first issue a Request for Qualifications on April 16th to evaluate firms, then issue a Request for Proposal to qualified firms. The solution must include two additional crane cells, raise the southern grade to match existing, and provide shore power, water, and lighting.
There is no set-aside designated for this opportunity. The NAICS code is 237990 for heavy and civil engineering construction with a $39.5 million small business size standard. Key details include dredging and earthwork, constructing and anchoring the quayside to support 200-ton crane loads, and running utility lines to the new infrastructure.
Notice text
The St. Paul District is planning to solicit for the design and construction of a straight-line mooring solution for the Corps’ Fountain City Service Base on the Mississippi river at Fountain City, Wisconsin. This acquisition will be conducted via a two-step design build process where the Corps will first post a Request For Qualifications (RFQ), evaluate responsive firm’s qualification, and then issue a Request for Proposal (RFP) to firms that meet the required qualifications to compete for the final contract award.
The current scope of the project includes but is not limited to:
- Reviewing the Corps’ documentation on the condition of the current river front as well as any unique site conditions which may impact the design requirements. Design.
- Designing a straight-line mooring system roughly 1,400 linear feet in length, to include two (2) additional crane cells for the Corps’ 200-ton heavy lift crane, raising the grade on the southern portion of the site to bring it level with the current crane cell, improved shore lighting, providing the Corps the ability to dock their fleet directly against the vertical face, and provide shore power and water to the vessels.
- Fabrication and installation of the system. Work will include dredging and earthwork to allow for installation of the quayside, constructing the mooring solution (ex: forming and pouring concrete or driving pile), anchoring the vertical face into the current riverbed to support crane loads, and running power and water lines to the new quayside.
The anticipated posting date for the RFQ is approximately April 16, 2021. It is the District's intent to issue the solicitation as full and open. The NAICS code for the proposed project is 237990 with a small business size standard of $39.5 million.
Notice history
| Notice | Type | Posted |
|---|---|---|
| Fountain City Service Base Sustainment & Modernization | Award Notice | |
| Fountain City Service Base Sustainment & Modernization | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity