Emsworth Locks and Dams Miter Gate Hydraulic System Upgrade

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W911WN22B8002
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers, Pittsburgh District, is seeking proposals to upgrade the miter gate hydraulic systems at Emsworth Locks and Dams on the Ohio River in Pennsylvania. The contract scope includes installing four dedicated hydraulic power units on the main chamber with new variable frequency drive motor control centers, a new central hydraulic power unit for the auxiliary chamber, and demolishing existing hydraulic infrastructure. Proposals are due by June 29, 2022 and the contract will be awarded on a firm-fixed price basis to the responsible bidder offering the best value, considering technical approach and price. The contract must be completed within 450 calendar days of the notice to proceed.

There is no set-aside designation for this procurement. The NAICS code is 237990 and PSC code is F999. Wayne Crouse, Inc. provided the lowest bid of $3,127,645. The government estimate was $6,417,900 for upgrades at the Emsworth, Pennsylvania site. Work must be performed with minimal lock closures approved by the agency and is to be completed within 450 days of notice to proceed. Demolition and installation services will take place in close proximity to operating locks and dams on the Ohio River.

Notice text

3 versions

Update #3 · Latest ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the upgrade of the miter gate hydraulics systems at Emsworth Locks and Dams, Ohio River, PA. The contract generally includes the installation of four (4) dedicated hydraulic power units (HPU) on the main chamber with new variable frequency drive (VFD) motor control centers (MCC), installation of a new central HPU for the auxiliary chamber, demolition of the existing central HPU, and demolition of existing hydraulic pipes and valves associated with the main chamber. The major features of the requirements are identified below: The contract specifically includes: a. Installation of additional shutoff valves on the middle wall oil piping to enable removal of the main chamber miter gate operating machinery from the existing central hydraulic network.b. Testing of existing fiber optic network and production of network map.c. Furnishings and installation of four dedicated HPU, including raised concrete pads, protection, associated electronics and hardware, and hydraulic oil, by each of the miter gate locations on the main chamber.d. Furnishing and delivery of spare dedicated HPU.e. Furnishing and installation of VFD control MCCs on the land and middle walls.f. Furnishing and installation of new auxiliary chamber HPU on middle wall, including all associated electronics and hardware.g. Furnishing and delivery of spare motor and pump for auxiliary HPU.h. Furnish and install new miter gate position feedback sensors.i. Modification of existing control software to allow for automated miter gate operation and HPU monitoringj. Demolition and disposal of existing HPU located in the middle wall operation building. This includes all motors, pumps, reservoir, raised skid, associated piping, and proper disposal of hydraulic oil.k. Demolition and removal of all existing hydraulic oil lines on the land wall, including all lines for pressure, return, drain, and filling, valving, and proper disposal of hydraulic oil.l. Integration of new system with existing fiber optic communication cabling.Removal and proper disposal of hydraulic oil will be required. Removal and proper disposal of electrical equipment will be required. Ferrous and all other construction waste material will be disposed of at commercially permitted facilities licensed to accept waste or recyclable materials as applicable. Construction work will occur in close proximity to waterway traffic and operating lock and dam gates. The existing lock chambers and dams are currently operated and staffed by Government personnel 24 hours a day 365 days of the year. Lock closures for installation and testing of new equipment will be required to be minimal and at the approval of Government. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W911WN22B8002' to obtain more details.*

29 June 2022:  Bid opening held virtually at 1100 ET, attendance register and bid results attached.

30 June 2022:  An updated Bid Results list has been posted due to a typo error on the “.” on the Total Bid Amount for Marine Diving Solutions, LLC.

Update #2 ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the upgrade of the miter gate hydraulics systems at Emsworth Locks and Dams, Ohio River, PA. The contract generally includes the installation of four (4) dedicated hydraulic power units (HPU) on the main chamber with new variable frequency drive (VFD) motor control centers (MCC), installation of a new central HPU for the auxiliary chamber, demolition of the existing central HPU, and demolition of existing hydraulic pipes and valves associated with the main chamber. The major features of the requirements are identified below: The contract specifically includes: a. Installation of additional shutoff valves on the middle wall oil piping to enable removal of the main chamber miter gate operating machinery from the existing central hydraulic network.b. Testing of existing fiber optic network and production of network map.c. Furnishings and installation of four dedicated HPU, including raised concrete pads, protection, associated electronics and hardware, and hydraulic oil, by each of the miter gate locations on the main chamber.d. Furnishing and delivery of spare dedicated HPU.e. Furnishing and installation of VFD control MCCs on the land and middle walls.f. Furnishing and installation of new auxiliary chamber HPU on middle wall, including all associated electronics and hardware.g. Furnishing and delivery of spare motor and pump for auxiliary HPU.h. Furnish and install new miter gate position feedback sensors.i. Modification of existing control software to allow for automated miter gate operation and HPU monitoringj. Demolition and disposal of existing HPU located in the middle wall operation building. This includes all motors, pumps, reservoir, raised skid, associated piping, and proper disposal of hydraulic oil.k. Demolition and removal of all existing hydraulic oil lines on the land wall, including all lines for pressure, return, drain, and filling, valving, and proper disposal of hydraulic oil.l. Integration of new system with existing fiber optic communication cabling.Removal and proper disposal of hydraulic oil will be required. Removal and proper disposal of electrical equipment will be required. Ferrous and all other construction waste material will be disposed of at commercially permitted facilities licensed to accept waste or recyclable materials as applicable. Construction work will occur in close proximity to waterway traffic and operating lock and dam gates. The existing lock chambers and dams are currently operated and staffed by Government personnel 24 hours a day 365 days of the year. Lock closures for installation and testing of new equipment will be required to be minimal and at the approval of Government. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W911WN22B8002' to obtain more details.*

29 June 2022:  Bid opening held virtually at 1100 ET, attendance register and bid results attached.

Update #1 ·

The U.S. Army Corps of Engineers, Pittsburgh District, has a project that involves the upgrade of the miter gate hydraulics systems at Emsworth Locks and Dams, Ohio River, PA. The contract generally includes the installation of four (4) dedicated hydraulic power units (HPU) on the main chamber with new variable frequency drive (VFD) motor control centers (MCC), installation of a new central HPU for the auxiliary chamber, demolition of the existing central HPU, and demolition of existing hydraulic pipes and valves associated with the main chamber. The major features of the requirements are identified below: The contract specifically includes: a. Installation of additional shutoff valves on the middle wall oil piping to enable removal of the main chamber miter gate operating machinery from the existing central hydraulic network.b. Testing of existing fiber optic network and production of network map.c. Furnishings and installation of four dedicated HPU, including raised concrete pads, protection, associated electronics and hardware, and hydraulic oil, by each of the miter gate locations on the main chamber.d. Furnishing and delivery of spare dedicated HPU.e. Furnishing and installation of VFD control MCCs on the land and middle walls.f. Furnishing and installation of new auxiliary chamber HPU on middle wall, including all associated electronics and hardware.g. Furnishing and delivery of spare motor and pump for auxiliary HPU.h. Furnish and install new miter gate position feedback sensors.i. Modification of existing control software to allow for automated miter gate operation and HPU monitoringj. Demolition and disposal of existing HPU located in the middle wall operation building. This includes all motors, pumps, reservoir, raised skid, associated piping, and proper disposal of hydraulic oil.k. Demolition and removal of all existing hydraulic oil lines on the land wall, including all lines for pressure, return, drain, and filling, valving, and proper disposal of hydraulic oil.l. Integration of new system with existing fiber optic communication cabling.Removal and proper disposal of hydraulic oil will be required. Removal and proper disposal of electrical equipment will be required. Ferrous and all other construction waste material will be disposed of at commercially permitted facilities licensed to accept waste or recyclable materials as applicable. Construction work will occur in close proximity to waterway traffic and operating lock and dam gates. The existing lock chambers and dams are currently operated and staffed by Government personnel 24 hours a day 365 days of the year. Lock closures for installation and testing of new equipment will be required to be minimal and at the approval of Government. *Visit 'https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?solNo=W911WN22B8002' to obtain more details.*

Files

Notice history

Notice Type Posted
Emsworth Locks and Dams Miter Gate Hydraulic System Upgrade Award Award Notice
This notice Latest solicitation Solicitation
Miter Gate Hydraulics Upgrades, Emsworth Locks and Dams, Ohio River, Pennsylvania Pre-Solicitation
Miter Gate Hydraulics Upgrades, Emsworth Locks and Dams, Ohio River, Pennsylvania Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Allegheny River Lock and Dam 2 Interlock and Traffic Control System Replacement Pittsburgh, Pennsylvania 15206, United States · NAICS 237990 ENDIST Pittsburgh Total Small Business
Borough of Millvale, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation Borough of Millvale, City of Pittsburgh, Allegheny County, Pennsylvania 15223 · NAICS 237990 ENDIST Pittsburgh Total Small Business
Bonneville Powerhouse II Unwatering Pump Replacement United States · NAICS 237990 ENDIST Portland Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors