East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912P822B0003
- Agency
-
ENDIST New Orleans
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Service-Disabled Veteran-Owned Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Louisiana 70791, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks clearing and snagging services along Bayou Fountain and Dawson Creek in East Baton Rouge Parish, Louisiana. The U.S. Army Corps of Engineers Engineering District New Orleans requires the removal of all trees and debris within the defined project limits. The estimated value of the work is between $5-10 million. Interested parties must submit bids by March 17, 2022. Evaluation will consider price, technical approach, and past performance.
This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. The NAICS code is 237990 and PSC code R499 covers other maintenance, repair, and alteration services of nonresidential structures. Four bids were received ranging from $2.3-7.1 million. The selected contractor will dispose of all waste at the East Baton Rouge Landfill and perform work within the waterways and from staging areas atop the banks as specified. Place of performance will be Zachary, Louisiana.
Notice text
7 versions
Update #7 · Latest ·
The revised bid abstract has been added to this record.
***************************************************
The bid abstract has been added to this record.
***************************************************
Amendment 02 has been added to this record.
***************************************************
The bid submission date/time has been changed to Thursday, 17 March 2022 at 10:00am. The bid opening date/time has been changed to Thursday, 17 March 2022 at 11:00am.
Bid Opening Teleconference information will be included in an Amendment 02 published later this morning.
***************************************************
Amendment 01 has been added to this record.
***************************************************
Plans were added to the solicitation.
***************************************************
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Update #6 ·
The bid abstract has been added to this record.
***************************************************
Amendment 02 has been added to this record.
***************************************************
The bid submission date/time has been changed to Thursday, 17 March 2022 at 10:00am. The bid opening date/time has been changed to Thursday, 17 March 2022 at 11:00am.
Bid Opening Teleconference information will be included in an Amendment 02 published later this morning.
***************************************************
Amendment 01 has been added to this record.
***************************************************
Plans were added to the solicitation.
***************************************************
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Update #5 ·
Amendment 02 has been added to this record.
***************************************************
The bid submission date/time has been changed to Thursday, 17 March 2022 at 10:00am. The bid opening date/time has been changed to Thursday, 17 March 2022 at 11:00am.
Bid Opening Teleconference information will be included in an Amendment 02 published later this morning.
***************************************************
Amendment 01 has been added to this record.
***************************************************
Plans were added to the solicitation.
***************************************************
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Update #4 ·
The bid submission date/time has been changed to Thursday, 17 March 2022 at 10:00am. The bid opening date/time has been changed to Thursday, 17 March 2022 at 11:00am.
Bid Opening Teleconference information will be included in an Amendment 02 published later this morning.
***************************************************
Amendment 01 has been added to this record.
***************************************************
Plans were added to the solicitation.
***************************************************
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Update #3 ·
Amendment 01 has been added to this record.
***************************************************
Plans were added to the solicitation.
***************************************************
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Update #2 ·
Plans were added to the solicitation.
***************************************************
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Update #1 ·
East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084 .
This procurement is a set aside for 100% SERVICE DISABLED VETERAN OWNED SMALL BUSINESS (SDVOSB) only.
DESCRIPTION AND MAGNITUDE OF WORK: The work consists of clearing and snagging Bayou Fountain and its tributary Dawson Creek from top-of-bank and all incidental work thereto.
Magnitude of Construction: Between $5,000,000 and $10,000,000.
Files
| File | Type | Posted |
|---|---|---|
| Revised Bid Abstract W912P822B0003v2.pdf | ||
| W912P822B0003 Bid Abstract_signed.pdf | ||
| W912P822B0003 Am 02.pdf | ||
| W912P822B0003 AM01.pdf | ||
| W912P822B0003.pdf | ||
| W912P822B0003.pdf | ||
| W912P822B0003.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging | Award Notice | |
| This notice | Solicitation | |
| East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging | Pre-Solicitation |
Similar open opportunities
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity