This document contains questions and responses regarding a solicitation for clearing and snagging work along Bayou Fountain and Dawson Creek in East Baton Rouge Parish, Louisiana. The solicitation seeks removal of all trees and debris within the defined project limits. The estimated value of the work is between $5-10 million. The opportunity is open only to Service-Disabled Veteran-Owned Small Businesses. The selected contractor will be responsible for disposal costs at the East Baton Rouge Landfill. Machinery may access the project area from staging areas atop the banks but working from the bank is otherwise restricted to those locations. All trees within the defined project boundaries must be cut and removed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Revised Bid Abstract W912P822B0003v2.pdf | ||
| W912P822B0003 Bid Abstract_signed.pdf | ||
| W912P822B0003 Am 02.pdf | ||
| W912P822B0003.pdf | ||
| W912P822B0003.pdf | ||
| W912P822B0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ED 18-084
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Subject Solicitation: W912P822B0003. East Baton Rouge Flood Risk Reduction Project, Bayou Fountain Clearing and Snagging, East Baton Rouge Parish, LA_Ed 18-084.
Contract questions addressed.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 07-Mar-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P822B0003
X 9B. DATED (SEE ITEM 11)
14-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
07-Mar-2022
CODE
USACE, CONTRACTING DIVISION
ATTN: CEMVN-CT, ROOM 172
7400 LEAKE AVE.
NEW ORLEANS LA 70118-3651
W912P8 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P822B0003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
CONTRACT QUESTIONS/RESPONSES
Bayou Fountain Clearing and Snagging Solicitation W912P822B0003
Contractor Questions & USACE Responses
Q1. Request for a site visit date, time and location for Clearing & Snagging of Bayou Fountain, East Baton Rouge, LA.
R1. For information to schedule a site visit, please contact Mr. Richard Broussard at 504-862-2523.
Q2. I wanted to see if you knew how the testing lab would be selected for the Charenton Floodgate Replacement project. Terracon Consultants Inc is a validated lab and I would like to understand how we can receive more work with the USACE.
R2. That information has not been determined.
Q3. Request for copies of the government quantity estimates for this project as outlined in 52.236-4 PHYSICAL DATA:
Estimates of quantities involved in certain items of work for which bids are being solicited on a job basis have been made for the use of the Government. Copies of these quantity estimates may be viewed or obtained, if available, by contacting the Contract Specialist for this contract, same address as stated in subparagraph
(a) above. It is expressly understood that the accuracy of these estimates is in no way warranted and that the furnishing of this information to a bidder will not relieve him of his responsibility to estimate the quantities involved.
R3. For item 0008 Clearing and Snagging, the IGE is using 62 acres. For item 0009 Access Clearing, the IGE is using 2 acres for light clearing and mowing.
Q4. Was an assessment performed after hurricane Ida because there are many more trees down in the creek than what the pictures show?
R4. An assessment was not performed after hurricane Ida.
Q5. In the spec section below, it details what need to be disposed of. There is a large section of sheet pile retaining wall that is leaning into the channel. Is this expected to be hauled off?
R5. Sheet pile is to remain in place. The intent is to do not disrupt bank stability.
Q6. What determines top of bank?
R6. In general, the limits of clearing and snagging are from top-of-bank top top-of-bank. The actual limits of clearing and snagging is an offset distance from the centerline as shown on sheet G-04.
Q7. Are the large cypress trees that are still standing in the water expected to be cut and hauled?
R7. All trees that are within the limits of clearing and snagging shall be cut and removed from the bayou.
Q8. Is there a diameter of tree that would be considered to remain?
R8. No, all trees that are within the limits of clearing and snagging shall be cut and removed from the bayou.
Q9. If a tree is on top of the bank and doesn’t need to be cut but there are limbs hanging over the canal. What is the requirement such as height of the limb hanging over the canal?
R9. All trees located outside of the limits of clearing and snagging, access corridors, and staging areas shall not be disturbed. If a tree is growing outside of the areas previously stated and its limbs are growing down into the channel (interfering with work or impeding flow) those limbs will be removed (not the whole tree).
Q10. Can equipment be used on top of bank to assist?
R10. The intent is to work from within the channel banks. Working from top-of-bank is allowed at staging areas only.
Q11. Can the bayou banks be utilized to skid clearing and snagging debris to the staging areas? If so, what precautions would need to be taken?
R11. Clearing and snagging shall occur within the limits shown on sheet G-04.
As stated in SECTION 31 11 13.00 12, Para. 3.3.1. “Clearing and snagging shall not impair bank stability as stated in Handheld equipment (chain saws, brush cutters, etc.) shall be used as much as possible to minimize damage to instream and riparian habitat.
Q12. Who is responsible for the dump charges at the East Baton Rouge North Landfill?
R12. Contractor shall be responsible for dump charges at the East Baton Rouge Landfill.
(End of Summary of Changes)