Detroit Dam and Reservoir Minto Fish Facility Rebuild

Award Notice Posted

Solicitation number
W9127N-10-R-0052
Agency
Awarded
to Slayden Construction Group, Inc.
Set-aside
No set-aside

Opportunity facts

Contract number
W9127N-11-C-0013 Federal contract award
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Not on record

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

The Minto Fish Collection Facility Rebuild will provide a new fish collection facility that meets NMFS (National Marine Fisheries Service)criteria for upstream passage and collection facilities for ESA (Endangered Species Act) listed fish and provides a safe working environment for the operators. When completed, it will serve as an upstream fish passage facility for ESA-listed fish.

Update #3 ·

The Minto Fish Collection Facility Rebuild will provide a new fish collection facility that meets NMFS (National Marine Fisheries Service)criteria for upstream passage and collection facilities for ESA (Endangered Species Act) listed fish and provides a safe working environment for the operators. When completed, it will serve as an upstream fish passage facility for ESA-listed fish.

Magnitude of construction is between $25,000,000. and $100,000,000. Place of
performance is Marion County, Oregon. The procurement is unrestricted and open to small and large business concerns. Large business are required to provide a Small Business Subcontracting Plan. The small business size standard is $33,500,000. The solicitation willbe available on or about November 17, 2010, with proposals due on or about 45 days after advertise.

Update #2 ·

The Minto Fish Collection Facility Rebuild will provide a new fish collection facility that meets NMFS (National Marine Fisheries Service)criteria for upstream passage and collection facilities for ESA (Endangered Species Act) listed fish and provides a safe working environment for the operators. When completed, it will serve as an upstream fish passage facility for ESA-listed fish.

Magnitude of construction is between $25,000,000. and $100,000,000. Place of performance is Marion County, Oregon. The procurement is unrestricted and open to small and large business concerns. Large business are required to provide a Small Business Subcontracting Plan. The small business size standard is $33,500,000. The solicitation will be available on or about November 17, 2010, with bid opening on or about 45 days after advertise.

Update #1 ·

The United States Army Corps of Engineers, Portland District will conduct a Pre-Solicitation Conference for the Detroit Dam and Reservoir Minto Fish Collection Facility Rebuild project on 21 October 2010 at Oregon Fish and Wildlife Building in Salem, Oregon. The address is:

Oregon Department of Fish and Wildlife
Commission Room
3406 Cherry Ave. NE
Salem, OR 97303

Driving directions can be found at the following link:
http://www.dfw.state.or.us/directions/


The Commission Room is located on the 1st Floor of the ODFW Main Building
The conference will begin at 10:00 AM. This Pre-Solicitation conference is for informational purposes only and is intended to give interested contractors an overview of the size,scope, and timeline of the project. The official solicitation is scheduled to be issued in early November 2010.

Attendees are required to pre register for the conference by emailing Robert Fuchs, Contracting Specialist at robert.k.fuchs@usace.army.mil . Include name of attendee and name of company.

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity