Rebuild of the detroit DAM & reservoir minto fish facility project no.: 1515

Ended Definitive Contract Awarded Last action

Contract number
W9127N11C0013
Awardee
Awarding agency
Obligated
$28,543,238

Award facts

Opportunity
Contract value 100% obligated
$28,543,237.64 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Y219 Construct/Other Conservation
Set-aside
No set-aside
Competition
Full and Open Competition · 10 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
McKenzie Bridge, OR 97413, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out A00025 · Minto fish facility, marion county, oregon - case no. 008 post sort pool piping & case no. 013 post sort pool north end dewatering -$67,052
Change Order A00024 · Minto construction --- project no.: 1515 - final clin adjustment & IPS air compressor OWS -$242,503
Change Order A00023 · Minto construction --- project no.: 1515 - air burst system $47,500
Supplemental Agreement for work within scope P00013 · Minto construction --- project no.: 1515 - follow on modification work #2 $692,500
Change Order A00022 · Minto construction --- project no.: 1515 - compressor pressure switch relocation $25,884
Change Order A00021 · Minto construction --- project no.: 1515 - interim adjustment to clins 0048 and 0049 $35,035
Change Order A00020 · Minto construction --- project no.: 1515 - fish hopper $13,249
Change Order A00019 · Minto construction --- project no.: 1515 - miscellaneous changes $77,610
Supplemental Agreement for work within scope P00012 · Minto construction --- project no.: 1515 - minto follow-on modification work #1 $565,500
Change Order A00018 · Minto construction --- project no.: 1515 - washdown rated motors $16,894
Exercise an Option P00011 · Minto construction --- project no.: 1515; exercise optional clins 0048 & 0049 $58,500
Change Order A00017 · Minto construction --- project no.: 1515; 8" barrier DAM pipes $139,000
Change Order A00016 · Minto construction --- project no.: 1515; fish handling equipment, anesthetic tank $40,500
Change Order A00015 · Minto construction --- project no.: 1515; barrier DAM flashboards $197,622
Change Order A00014 · Minto construction --- project no.: 1515; additional concrete $52,800
Change Order A00013 · Minto construction --- project no.: 1515 - miscellaneous IPS and PSP changes $37,400
Change Order P00010 · Minto construction --- project no.: 1515 - time impact REA $900,000
Change Order A00012 · Minto construction --- project no.: 1515 - clin 0037 interim quantity adjustment $100,000
Change Order A00011 · Minto construction --- project no.: 1515 - clin 0010 interim quantity adjustment $150,000
Change Order A00010 · Minto construction --- project no.: 1515 - fish ladder leveling slab $165,902
Change Order A00009 · Minto construction --- project no.: 1515 - rock fall protection $251,145
Funding Only Action P00009 · Minto construction --- project no.: 1515 - allocation of funds; $2,155,000.00 $2,155,000
Change Order A00008 · Minto construction --- project no.: 1515 $151,129
Other Administrative Action P00008 · Minto construction --- project no.: 1515 - correction of an administrative error. -$2,258,160
Change Order A00007 · Minto construction --- project no.: 1515 - structural drawings revisions $29,887
Change Order A00006 · Minto construction --- project no.: 1515 - AWS gate modifications $2,284,976
Change Order P00007 · Minto construction --- project no.: 1515 - exercise optional clin 0045 -$2,053,660
Change Order A00005 · Minto construction --- project no.: 1515; interim quantity adjustment to clin 0047 $324,000
Change Order P00006 · Minto construction --- project no.: 1515 - definitization NTP MOD R00005 $2,716,260
Other Administrative Action P00005 · Minto construction --- this modification reverses a duplicate modification -$2,132,639
Change Order A00004 · Minto construction --- project no.: 1515 $130,000
Supplemental Agreement for work within scope P00004 · Minto construction --- project no.: 1515 in scope modification to install drain pipe to divert water around the west protion of the construction site. $28,979
Change Order A00003 · Minto construction --- project no.: 1515 - revisions to culvert outfall diversion $2,132,639
Change Order P00003 · Minto construction --- project no.: 1515 additional funding $6,680,000
Change Order A00002 · Minto construction --- project no.: 1515 $47,659
Exercise an Option P00002 · Minto construction --- project no.: 1515; exercise optional clins - 0046 design rock cut reinforcement & 0047 rock cut reinforcement $46,000
Change Order A00001 · Minto construction --- project no.: 1515 $3,681
Other Administrative Action P00001 · Minto construction correct clerical error --- project no.: 1515 $0
Original award $15,000,000
Show all 39

Quick answers

Who was awarded contract W9127N11C0013?

W9127N11C0013 was awarded to Slayden Construction Group, Inc. by ENDIST Portland (US Army Corps of Engineers) on March 22, 2011.

How much is contract W9127N11C0013 worth?

The government has obligated $28,543,238 on W9127N11C0013.

Was contract W9127N11C0013 competed?

The extent of competition for W9127N11C0013 was full and open competition. The government received 10 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award