DBB P4041 medical/dental clinic replacement hadnot point MCB camp lejeune
Award Notice Posted
- Solicitation number
- N4008518R0612
- Agency
-
Naval Facilities Engineering Command
Department of the Navy, Department of Defense
- Awarded
- to The Whiting-Turner Contracting Company
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- N4008519C9265 Federal contract award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
CONTRACT N4008519C9265/REQUEST FOR PROPOSAL (RFP) N40085-18-R-0612, DESIGN-BID-BUILD CONSTRUCTION OF P4041 MEDICAL/DENTAL CLINIC REPLACEMENT, MARINE CORPS BASE, CAMP LEJEUNE, NORTH CAROLINA
This project is a construction contract for the P4041, Medical/Dental Replacement located at the Marine Corps Base, Camp Lejeune, North Carolina. The project will construct a new two story free-standing medical/dental facility of approximately 40,000 SF.
All Engineering systems will be furnished including Structural, Fire Suppression, Plumbing, HVAC, Electrical, and Communications. The basic structural frame will be comprised of steel beams supporting a steel bar joist and steel deck roof system. The exterior will be CMU and brick cavity walls.
Portions of the exterior walls will be hardened for Anti-Terrorism/Force Protection (AT/FP) and windows within the hardened portion will AT/FP requirements. The facility will be fully sprinklered in accordance with DOD criteria. The facility will be provided with a complete and usable domestic cold/hot water distribution with hot water recirculation and sanitary drainage with all associated fixtures, equipment, and appurtenances. In addition, a complete and usable cooling and heating system will be provided with all associated ductwork and equipment. Mechanical equipment will include a direct expansion dedicated outside air unit with heat recovery wheel and a variable refrigerant flow system.
A central dental evacuation system will be included in the plumbing. The mechanical equipment will be controlled by a Direct Digital Control system (DDC). The clinic will be served by 200 pair copper cable for voice service and 24 strand single mode optical fiber. The telecommunications infrastructure system will include 4-pair, category 6 cables. The voice and data system will include equipment racks, cabling, combination voice and data outlets, and termination equipment. The telecommunications systems will include: nurse call, public address, fire alarm, cable television, access control, an intrusion detection system infrastructure only, and a duress alarm system infrastructure only. A lightning protection system will be provided.
Construction of supporting facilities will include all site utilities, site preparation, site improvements, paving (parking and roadways), and access roads.
. Awarded Vendors: Whiting-Turner Contracting Company
6305 Ivy Lane, Suite 800, Greenbelt, Maryland 20770. Contract Award Dollar Amount: 22,911,402. Contract Award Date: 2019-09-27.
Notice history
| Notice | Type | Posted |
|---|---|---|
| This notice | Award Notice | |
| P4041 Medical/Dental Replacement, Marine Corps Base Camp Lejeune, North Carolina | Solicitation | |
| P4041 - design-bid-build, medical/dental clinic replacement, MCB camp lejeune | Pre-Solicitation |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity