Data Center Bridge VI Order for Continuity of Operations
Awarded Limited / Sole Source Justification Posted
- Solicitation number
- ODT-2025-129225
- Agency
-
FDA Office of Acquisition and Grant Services
Food and Drug Administration, Department of Health and Human Services
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- HHSN316201200026W-75F40125F80258 Federal contract award
- Awardee
- Peraton Enterprise Solutions LLC
- NAICS code
- 541513 Computer Facilities Management Services
- Place of performance
- Silver Spring, Maryland 20993, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Health and Human Services Food and Drug Administration Office of Acquisition and Grant Services has issued a sole source justification for a bridge task order valued at $67.9 million to maintain continuity of critical data center and IT infrastructure support services. The contract will be awarded to Peraton Enterprise Solutions LLC under the NIH Information Technology Acquisition and Assessment Center (NITAAC) Government-Wide Acquisition Contract for a base period of nine months with potential extension options. The services encompass the management and operation of FDA's four data centers located in Silver Spring, MD (9,300 SF), Jefferson, AR, College Park, MD (2,570 SF), and Ashburn, VA (5,300 SF), along with enterprise services, database operations, application operations, and System Management Center activities. The sole source justification is predicated on the mission-critical nature of these services and the incumbent contractor's specialized knowledge and existing staff expertise necessary to prevent disruption to FDA operations during the transition to a competitive procurement expected in FY2026. Without these services, the FDA would lose network connectivity and essential data center capabilities, severely impacting the agency's ability to serve the public and fulfill its regulatory mission.
Notice text
The purpose of the bridge order is to maintain continuity of operations of all the tasks in the FDA Data Center and Infrastructure Support Task Order until such a time when a new contract is awarded and transition activities are completed. Tasks include the management of FDA’s four data centers, providing enterprise services, data center lease and operations, application operations, database operations, running the System Management Center (SMC), and related project management activities.
The services to be provided under the bridge order are mission critical to the FDA; without the services, the FDA would not be able to serve the public as the FDA would not have any network connectivity, or data center and enterprise services. The incumbent contractor has all the necessary the staff in place with expert knowledge for operating and maintaining the data center and networks. A rushed and improper transition from one contractor to the next could severely impact the continuity of operations for the FDA and creates a great potential for an overarching agency failure.
The FDA is seeking the same level of support services with the incumbent until a new competitive procurement is awarded in FY2026. The bridge order serves an important role in bridging service gaps and risks to the Agency’s public health mission.
The FDA’s four (4) data centers are located in Silver Spring, MD (9,300 SF), Jefferson, AR, College Park, MD (2,570 SF), and Ashburn, VA (5,300 SF). All of the data centers are Government-owned facilities except for the 5,300 SF data center in Ashburn, VA, which is leased from Digital Realty by the incumbent contractor. This commercially leased data center in Ashburn, VA is considered a Tier three (3) Data Center (as described by uptimeinstitute.org) facility. The lease includes the Data Center Pod and a separate storage room for the storage of equipment and deliveries.
The task areas defined below will support lights-on activities as the FDA works toward realigning its next generation data center requirements. Some tasks from previous bridge orders have been removed as the tasks have been completed. The task areas defined in the scope of work include managing the FDA’s four data centers (subtask areas include providing Enterprise services, Data Center Operations, Application Operations, Database Operations, and running the System Management Center (SMC) (includes the FDA’s SOC and NOC)); managing the FDA’s IT infrastructure (Infrastructure Operations); conducting an inventory of the hardware and software which comprise the FDA’s data centers and IT infrastructure; providing program management support; and transition in and out support.
Awarded contract HHSN316201200026W to unknown vendor for unknown amount on 2025-09-30.
Files
| File | Type | Posted |
|---|---|---|
| JA JEFO ODT_OIM Data Center Support_ Bridge 6 Order_redact.pdf |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Contractor-Hosted Fully Integrated Records Facility (FIRF) IDIQ | FDA Office of Acquisition and Grant Services | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity