CXT Structure Elk Creek Campground and Recreation Area Tenkiller Lake, Oklahoma

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912BV21Q0033
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Cookson OK 74427 USA

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

The SOW in this solicitation requires the contractor to remove the entire existing single story shower/restroom and the foundation, detaching existing utilities and re-install utilities to the new CXT facility, preparing the site and installing the new concrete pre-fabricated CXT in the same location as the demoed facility and provide and place a reinforced concrete driveway.

Amendment 0001 -

(1) Change the proposal due date from 05 February 2021 to 12 February 2021.

(2) Update the Period of Performance on CLIN 0002 from 90 days to 120 days.

(3) Change the liquidated damages clause 52.211.12 from $4,750.00 to $750.00.

(4) Incorporate the latest w age determination OK20210067, dated 01/01/2021.

Amendment 0002 -

(1) Incorporate the latest w age determination OK20210019, dated 01/01/2021.

(2) Updated Paragraph 3.0 in the Statement of Work.

Amendment 0003-

(1) Change the proposal due date from 12 February 2021 to 19 February 2021

(2) Updated Section 3.1.2 in the Scope of Work

Update #2 ·

The SOW in this solicitation requires the contractor to remove the entire existing single story shower/restroom and the foundation, detaching existing utilities and re-install utilities to the new CXT facility, preparing the site and installing the new concrete pre-fabricated CXT in the same location as the demoed facility and provide and place a reinforced concrete driveway.

Amendment 0001 -

(1) Change the proposal due date from 05 February 2021 to 12 February 2021.

(2) Update the Period of Performance on CLIN 0002 from 90 days to 120 days.

(3) Change the liquidated damages clause 52.211.12 from $4,750.00 to $750.00.

(4) Incorporate the latest w age determination OK20210067, dated 01/01/2021.

Amendment 0002 -

(1) Incorporate the latest w age determination OK20210019, dated 01/01/2021.

(2) Updated Paragraph 3.0 in the Statement of Work.

Update #1 ·

The SOW in this solicitation requires the contractor to remove the entire existing single story shower/restroom and the foundation, detaching existing utilities and re-install utilities to the new CXT facility, preparing the site and installing the new concrete pre-fabricated CXT in the same location as the demoed facility and provide and place a reinforced concrete driveway.

Files

File Type Posted
W912BV21Q0033-0003.pdf PDF
W912BV21Q0033-0002.pdf PDF
W912BV21Q0033-0001.pdf PDF
Rainier CXT Photo.PNG PNG image
Rainier_dwgs.pdf PDF
W912BV21Q0033.pdf PDF
Elk Creek Bathroom Road Installation.jpg JPG image
Rainier_FlushShower_Specs.pdf PDF

Notice history

Notice Type Posted
CXT Structure Elk Creek Campground and Recreation Area Tenkiller Lake, Oklahoma Award Award Notice
This notice Latest solicitation Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors