The U.S. Fish and Wildlife Service seeks construction services to repair asphalt surfaces at Rocky Mountain Arsenal National Wildlife Refuge in Adams County, Colorado, with quotations due October 23, 2026, at 4:00 PM Mountain Daylight Time. This is a re-solicitation (RFQ 140FGA26Q0080) with no set-aside; Amendment 1, posted October 23, extends the deadline from the original October 29 date and clarifies project scope, roadway transition, reverse capeseal, patching, traffic control, warranty, and scheduling requirements. Offerors must acknowledge receipt of Amendment 1 in their submission.
Place of performance is Rattlesnake Hill Road (FWS Route 101), extending 0.75 miles from Havana Street to a metal swing gate. The road measures 22.7 feet wide and is in poor condition. Work includes full-depth asphalt patching of approximately 338 square yards (6 inches depth) and reverse capeseal surface treatment (slurry leveling course followed by 3/8-inch aggregate placement and compaction) on the entire roadway length, with crack sealing and one-year warranty on reverse capeseal work from completion. Contractor must comply with SECTION 321216 asphalt paving specifications, including material requirements (asphalt binder CDOT PG 64-22 or PG 58-28, emulsified asphalt tack coat, hot-mix asphalt with 10–25 percent recycled content) and installation procedures. Performance runs from November 9, 2026, to March 31, 2027; work must commence within 14 calendar days of notice to proceed. Normal working hours are Monday–Friday, 7:00 AM–4:30 PM, with coordination required outside these hours.
Estimated award value is $100,000 to $250,000. Contract is firm fixed-price with Davis-Bacon wage requirements applying; awards exceeding $150,000 require performance and payment bonds at 100 percent of contract price. Questions are due October 16, 2026. Site visits are scheduled October 6 and October 13 at 10:30 AM MDT (optional but recommended). Evaluation is best-value based on relevant experience with similar pavement preservation and roadway surface treatment projects completed within the last three years and price reasonableness, without formal rating systems or weighted scores. Quotations require Standard Form 1442, itemized cost breakdown, documentation of three similar projects within the past three years, and all applicable FAR representations and certifications. Electronic submission via email to nicole_johnson@ios.doi.gov in PDF or Microsoft Office formats. NAICS 237310 (Highway, Street, and Bridge Construction); PSC Z2LB.
Notice text
2 versions
Update #2 · Latest ·
CO-ROCKY MTN ARSNL NWR-PATCH HILL RD
Amendment 1 incorporates Government responses to vendor questions and revises the solicitation to clarify the project scope, roadway transition requirements, reverse cape seal requirements, asphalt patching requirements, traffic control responsibilities, warranty provisions, and project scheduling considerations. This amendment also revises the instructions regarding submission of similar project experience and extends the proposal due date to allow offerors adequate time to consider the updated solicitation requirements. Offerors shall acknowledge receipt of this amendment in their proposal submission.
Update #1 ·
CO-ROCKY MTN ARSNL NWR-PATCH HILL RD
The US Fish and Wildlife Service Rocky Mountain Arsenal National Wildlife Refuge (NWR) in Adams County, State of Colorado, has a requirement to repair all asphalt surfaces at the refuge's Rattlesnake Hill Road. This is a re-solicitation of RFQ 140FGA26Q0059.
A site visits are scheduled for Tuesday, October 6 AND October 13 at 10:30 am MT. Site Visit registration and meeting location information can be found in Section L of the solicitation, under FAR clause 52.236-27.
Requests for information and quotes shall be submitted via email to Nicole Johnson at nicole_johnson@ios.doi.gov.
Files
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Administrative Parking Lot Repairs | Forest Service | Total Small Business | |
| Jake Rocks Road Reconstruction | Forest Service | Total Small Business | |
| GAOA Brainard Lake Recreation Area Deferred Maintenance | Forest Service | Total Small Business | |
| TX FW LGA 10(5) Steve Thompson Wildlife Drive | Federal Highway Administration | Total Small Business | |
| Access Road Repair National Elk Refuge | — | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity