CO BR UCPO Blue Mesa Road(1) Blue Mesa Road

Pre-Solicitation Posted

Solicitation number
6982AF27B000009
Agency
Responses due
Not on record
Set-aside
Total Small Business

Opportunity facts

Place of performance
Gunnison, Colorado 81231, United States
Points of contact

Notice details come from SAM.gov. Updated .

About this opportunity

The Federal Highway Administration is preparing to procure rehabilitation of Blue Mesa Road in Gunnison County, Colorado, under a Total Small Business set-aside, with the full solicitation to be posted on SAM.gov. Blue Mesa Road is a 1.44-mile corridor providing access to the Bureau of Reclamation Power Plant and Pine Creek Trailhead on the Curecanti National Recreation Area. Schedule A rehabilitates 0.86 miles of gravel roadway to asphalt concrete and reconstructs 0.24 miles of existing asphalt, including a raised profile at the US 50 intersection, culvert replacement, ADA parking stalls, and rockfall mitigation. Principal quantities include 2,500 tons of Type 1 asphalt concrete pavement and 3,280 linear feet of ditch reconditioning. Option X converts 0.34 miles from the BOR gate to the Blue Mesa Power Plant and installs 6-inch electrical conduit for a future automatic gate. Option Y installs 2,215 LF of 6-inch conduit with 2 ft x 2 ft maximum trenching from the electric security gate to the power plant.

The draft Special Contract Requirements file lists a contract completion date of October 15, 2027, and bars onsite work before May 4, 2027. It requires a Stormwater Pollution Prevention Plan under Colorado Construction General Permits, qualified SWPPP developers, erosion control supervisors, and biologists for pre-construction nest surveys during the March 1 through August 31 breeding season. Culvert repair at Station 152+92 requires trenchless rehabilitation of a 78-inch corrugated metal pipe. Contractors must maintain 15-foot clearance from Western Area Power Administration transmission lines at all times and give 10 days' advance notice before blasting near those lines between Stations 100+00 and 120+00. Electronic Contractor's Daily Records and submittals go through the Masterworks system. Weekend operations are permitted, and nighttime work is governed by specification FP-24 156.07. Blasting authorization, onsite start timing, and water supply location will be addressed in SCR 108.01 with the formal solicitation.

The pre-bid site visit was scheduled for November 4, 2026, at 10:00 a.m. MDT at the Pine Creek Trailhead Parking Lot, and attendance was non-mandatory. Attendees were required to confirm by email to cflacquisitions@dot.gov by October 30, 2026. The agenda, sign-in sheet, and answered questions are to be posted to SAM.gov. A pre-advertisement Q&A dated November 4, 2026, addresses five questions, and bid submission and bid bond requirements will be addressed in the full solicitation.

Notice text

THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT NAME: CO BR UCPO Blue Mesa Road(1) Blue Mesa Road


Blue Mesa Road is a 1.44-mile corridor located in Gunnison County, CO and provides access to the Bureau of Reclamation (BOR) Power Plant and Pine Creek Trailhead recreational activities on the Curecanti National Recreational Area.

SCOPE OF THE WORK

 Schedule A: Proposed rehabilitation of 0.86 miles to replace existing gravel roadway with asphalt concrete pavement. Reconstruction/Rehabilitation, as needed, for 0.24 miles of existing asphalt to incorporate raising roadway profile at US 50 intersection, drainage improvements including replacement and/or lining of damaged culverts, relocation of traffic counters, formalize parking area with ADA stalls, signing and striping, ditch reconditioning, rockfall mitigation.


Option X: Proposed rehabilitation of 0.34 miles to replace existing gravel roadway with asphalt concrete pavement from BOR gate to Blue Mesa Power Plant, drainage improvements to include replacement of damaged culverts, signing and striping, ditch reconditioning, installation of 6” electrical conduit for purposes of future automatic gate installation.


Option Y: Proposed 6-inch electric conduit installation and 2 ft x 2 ft max trenching for 2,215 LF miles from the electric security gate to The Blue Mesa Power Plant. Conduit will provide future access for BOR to provide electric connection to security gate.
 

PRINCIPAL WORK ITEMS:
Schedule A:

  • 15225-0000 Slope, Reference, and Clearing and Grubbing Control: 1.051 MILE
  • 20301-1900 Removal of Pipe Culvert: 5 EACH
  • 20401-0000 Roadway Excavation: 1,500 CU YD
  • 30201-2000 Roadway Aggregate, Method 2: 2,500 CU YD
  • 30302-1000 Ditch Reconditioning: 3,280 LN FT
  • 40301-0100 Asphalt Concrete Pavement, Type 1: 2,500 TON
  • 60103-0140 Concrete, Headwall for 24-Inch Pipe Culvert (L-Shaped): 3 EACH
  • 60103-0160 Concrete, Headwall for 30-Inch Pipe Culvert: 1 EACH
  • 60103-0280 Concrete, Headwall for 66-Inch Pipe Culvert (Includes Wingwalls): 1 EACH
  • 60201-0800 24-Inch Pipe Culvert: 255 LN FT
  • 60201-0900 30-Inch Pipe Culvert: 45 LN FT
  • 60707-1200 Lining 66-Inch Pipe Culvert (HDPE Slipline): 110 LN FT
  • 60707-1300 Lining 72-Inch Pipe Culvert (HDPE Slipline): 190 LN FT
  • 63401-0300 Pavement Markings, Type B, Solid: 46,000 LN FT

Option X:

  • 15225-0000 Slope, Reference, and Clearing and Grubbing Control: 0.38 MILE
  • 20420-0000 Embankment Construction: 200 CU YD
  • 30201-2000 Roadway Aggregate, Method 2: 700 CU YD
  • 40301-0100 Asphalt Concrete Pavement, Type 1: 650 TON
  • 56603-0000 Reinforced Shotcrete: 180 SQ YD
  • 60704-0000 Cleaning Culvert in Place: 7 EA
  • 63401-0300 Pavement Markings, Type B, Solid: 8,500 LN FT

Option Y:

  • 63610-3410 Conduit, 6-Inch, HDPE (Schedule 40): 2,215 LN FT
  • 63621-1000 Utility Box, Pullbox: 6 EA
  • 63622-0000 Utility Trench: 2,215 LN FT

ANTICIPATED SCHEDULE
Advertisement: November 2026
Award: January 2027
NTP: April 2027
Construction: May 2027- October 2027

ESTIMATED COST RANGE: Between $2,000,000 and $5,000,000

 A NON-MANDATORY PRE-BID SITE VISIT WILL BE HELD NOVEMBER 4TH, 2026 AT 10:00AM. PLEASE SEE ATTACHEMENTS FOR ADDITIONAL INFORMATION 

Files

Notice history

Notice Type Posted
This notice Latest pre-solicitation Pre-Solicitation
CO BR UCPO Blue Mesa Road(1) Blue Mesa Road Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
CO OMAD 300(71) Minuteman Missile Access Cheyenne, Wyoming, United States · NAICS 237310 Federal Highway Administration Total Small Business
GAOA Brainard Lake Recreation Area Deferred Maintenance Ward, Colorado 80481, United States · NAICS 237310 Forest Service Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors