CA FTFW MERC 915(1), TRAILS(1), Trail and Parking Area
Closed Solicitation Posted
- Solicitation number
- 6982AF19B000017
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Merced National Wildlife Refuge Merced County CA 95341 USA
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
THIS PROJECT WILL BE ADVERTISED ON A TOTAL SMALL BUSINESS SET ASIDE BASIS.
CA FTFW MERC 915(1), Trail(1) Parking Area and Trails. The project is located in Merced National Wildlife Refuge, which is approximately 15 miles southwest of Merced, CA in Merced County. The project consists of the rehabilitation of 1.1 miles of trail system for Schedule A and approximately 0.84 miles of trails on Option X. Additional work consists of re-gravelling of small parking area, construction of ABA concrete parking pads, concrete sidewalk, signage, and striping.
Proposed improvements include parking rehabilitation and construction, aggregate base, parking concrete pads, signing, pavement markings, and aggregate surface for trails.
Significant quantities are as follows:
Schedule A:
2,600 TON of aggregate surface course
1.1 miles of aggregate surface reconditioning
110 SQYD of minor concrete pavement, plain, 6-inch depth
Option X:
1,150 TON of aggregate surface course
0.84 miles of aggregate surface reconditioning
The anticipated advertisement date is September2019. Construction is anticipated from November 2019 to February 2020.
Update #1 ·
THIS PROJECT WILL BE ADVERTISED ON A TOTAL SMALL BUSINESS SET ASIDE BASIS.
THIS IS NOT A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.
CA FTFW MERC 915(1), Trail(1) Parking Area and Trails. The project is located in Merced National Wildlife Refuge, which is approximately 15 miles southwest of Merced, CA in Merced County. The project consists of the rehabilitation of 1.1 miles of trail system for Schedule A and approximately 0.84 miles of trails on Option X. Additional work consists of re-gravelling of small parking area, construction of ABA concrete parking pads, concrete sidewalk, signage, and striping.
Proposed improvements include parking rehabilitation and construction, aggregate base, parking concrete pads, signing, pavement markings, and aggregate surface for trails.
Significant quantities are as follows:
Schedule A:
2,600 TON of aggregate surface course
1.1 miles of aggregate surface reconditioning
110 SQYD of minor concrete pavement, plain, 6-inch depth
Option X:
1,150 TON of aggregate surface course
0.84 miles of aggregate surface reconditioning
The anticipated advertisement date is September2019. Construction is anticipated from November 2019 to February 2020.
Files
| File | Type | Posted |
|---|---|---|
| Bid_Opening_Summary.pdf | ||
| Q&A_10-15-19.pdf | ||
| Q&A_10-7-19.pdf | ||
| Q&A_Oct_1-2019.pdf | ||
| QnA_9.24.2019.pdf | ||
| Amendment_A00l.pdf | ||
| CA_FTFW_MERC_915(1),_Trail(1)_100__FINAL_Plans.pdf | ||
| 6982AF19B000017.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity