CA FTBR Senator Wash (1) Ferguson Road to Imperial Dam

Pre-Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
6982AF20B000042
Agency
Responses due
Not on record
Set-aside
Total Small Business

Opportunity facts

Place of performance
Winterhaven Ca Usa

Notice details come from SAM.gov. Updated .

About this opportunity

This pre-solicitation notice is for a road repaving project along 2.5 miles of Ferguson Road to Imperial Dam in Imperial County, California. The Department of Transportation Federal Highway Administration will rehabilitate the existing pavement by pulverizing and reusing it as base material before repaving. Construction phasing and traffic control will be crucial to minimize disruptions. The project is estimated to cost between $1,500,000 and $2,500,000 and will be completed between December 2020 and April 2021.

This project is designated as a total small business set-aside. Key work includes 9,000 tons of asphalt pavement, 2.5 miles of full depth reclamation, and 1,200 tons of aggregate base. The anticipated advertisement date is September 2020, bid opening is October 2020, and award date is November 1, 2020.

Notice text

THIS PROJECT WILL BE ADVERTISED AS A TOTAL SMALL BUSINESS SET ASIDE.

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT NUMBER: CA FTBR Senator Wash (1)

PROJECT NAME: Ferguson Road to Imperial Dam

PROJECT DESCRIPTION: This project consists of repaving approximately 2.5 miles of roadway in Imperial County, California. The existing pavement will be pulverized and reused as base material prior to paving. Construction phasing, temporary traffic control, and timely completion of construction will be crucial to minimize disruptions to recreation area visitors throughout construction and achieve customer satisfaction. 

SIGNIFICANT QUANTITIES:

  • 9,000 tons of asphalt concrete pavement,
  • 2.5 miles of full depth reclamation,
  • 1,200 tons of aggregate base.

COST RANGE: The proposed project is estimated at a cost between $1,500,000 and $2,500,000.

CONSTRUCTION DURATION: December, 2020 to April, 2021

ADDITIONAL INFORMATION:

Anticipated Advertisement: September, 2020

Anticipated Bid Opening: October, 2020

Anticipated Award: November 1, 2020

Notice history

Notice Type Posted
CA FTBR Senator Wash (1) Ferguson Road to Imperial Dam Award Award Notice
CA FTBR Senator Wash (1) Ferguson Road to Imperial Dam Latest solicitation Solicitation
This notice Pre-Solicitation
CA FTBR Senator Wash (1) Ferguson Road to Imperial Dam Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors