About this opportunity

This pre-solicitation notice seeks engineering and construction services to replace the Norris Creek Bridge over Norris Creek within the Sierra National Forest in Madera County, California. The damaged bridge will be fully replaced with a prefabricated steel structure measuring 70 feet by 24 feet. The Federal Highway Administration through the Central Federal Lands Highway Division intends to award a small business set-aside contract to remove the existing bridge and reconstruct the roadway approaches up to 150 feet on both ends. Proposals are due by September 30th and it is anticipated the contract will be awarded in December following an October advertisement.

The opportunity is set aside for total small businesses. The work involves removing the existing structure, excavating and embanking 8,500 cubic yards of material, placing 250 cubic yards of riprap and 300 tons of roadway aggregate. A 70-foot by 256-foot prefabricated steel bridge will be installed along with 200 tons of asphalt pavement and 150 linear feet of guardrail. The estimated magnitude for engineering and construction services is between $700,000 to $2,000,000. Key equipment and labor quantities include 80 hours of equipment and 40 hours of labor.

Notice text

THIS IS NOT A REQUEST FOR BID

PLANS AND SPECIFICATIONS ARE NOT AVAILABLE

THE SOLICITATION WILL BE A SMALL BUSINESS SET-ASIDE

CA ERFO SIERRA NF 05S07(1) - NORRIS CREEK BRIDGE

PROJECT DESCRIPTION AND LOCATION:  The Sierra National Forest (SNF) sustained significant damage to transportation facilities, including bridges during the 2020 fire season. The US Forest Service (FS) is requesting that the Central Federal Lands Highway Division (CFLHD) perform engineering and construction services to replace the Norris Creek Bridge structure utilizing Emergency Repair for Federally Owned Roads (ERFO) and Forest Service funds.

The project site is located approximately 37.2 miles northeast of Oakhurst, CA on Forest Service Route 05S007 (Beasore Road) within Sierra National Forest in Madera County, CA.

The original bridge was a one lane, two-way traffic single span structure at a 15-degree skew.  It had an overall bridge length of 37 feet, roadway width (curb to curb) of 14.1 ft, and deck width (outside to outside) of 15.4 ft.  

SCOPE OF THE WORK: The purpose of the project is to replace the Norris Creek Bridge over Norris Creek within Sierra National Forest in Madera County, California.  The bridge was completely damaged by fire in 2020 and will be fully replaced with a prefabricated steel bridge. A two-lane, 70-ft x 24-ft proposed structure is anticipated.

The roadway approaches will be reconstructed for up to 150 feet on either end of the bridges. The bridge and a short section of the roadway approaches will be asphalt overlaid to match the existing roadway section. Bridge rail and guardrail with terminals will be included.

Items worth noting:

  • The work will be listed within a single Schedule (Schedule A) and no options are proposed.
  • Adjacent segments of Forest Route 05S007 will remain closed during construction and can be used for contractor staging and storage. 
  • Access is to both sides of the bridge is possible by an approximate 7.5-mile detour.
  • Deep foundations (micro-piles or drilled shafts) are anticipated

PRINCIPAL WORK ITEMS:

Approximate quantities for major work items:

  • 1 (LPSM) of Removal of Existing Structures and Obstructions
  • 8500 CUYD of Excavation/Embankment Construction       
  • 250 CUYD of Riprap
  • 300 TON of Roadway Aggregate
  • 70-ft x 256-ft of Prefabricated Steel Bridge
  • 200 TON of Asphalt Pavement                     
  • 150 LNFT of Guardrail, including terminals
  • 80 hours of Equipment Hours
  • 40 hours of Labor Hours

ANTICIPATED SCHEDULE:

Advertise:  October 2022

Award:  December 2022 

ESITMATED MAGNITUDE: Between $700,000 and $2,000,000 

Notice history

Notice Type Posted
CA erfo sierra NF 05S07(1) norris creek bridge Award Award Notice
CA erfo sierra NF 05S07(1) norris creek bridge Latest solicitation Solicitation
This notice Pre-Solicitation
CA erfo sierra NF 05S07(1) norris creek bridge Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Humbolt pacific crest trail bridge replacement Bridgeport, California 93517, United States · NAICS 237310 Forest Service No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors