Boiler Thermal Efficiency Improvements - Boiler Repairs at 27A, A6, 7CC. Naval Station Newport, Newport RI
Award Notice Posted
- Solicitation number
- N4008516R4639
- Agency
-
Naval Facilities Engineering Command
Department of the Navy, Department of Defense
- Awarded
- to Kisan-Pike
- Set-aside
- Total Small Business
Opportunity facts
- Contract number
- N4008514D52480010 Federal contract award
- NAICS code
- 541330 Engineering Services
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
Provide all labor, materials, transportation, equipment, supplies
and supervision as required for each relocated boiler @ 27A and A6.
a) Pipe in relocated boiler’s steam supply to existing steam header.
b) Pipe in relocated boiler’s feedwater supply to feedwater supply header
c) Pipe in relocated boiler’s bottom blowdown system to existing bottom blowdown header.
d) Pipe in relocated boiler’s surface blow system to second isolation valve.
e) Pipe in relocated boiler’s gas train to existing gas supply pipe
f) Wire in relocated boiler’s boiler/burner/blower/VFD power supply (A6 and 27A) and control
wiring (27A) where indicated. Wire in feedwater control valve, conductivity sensor, and surface
blowdown valve
g) Pipe in relocated boiler’s Safety valve discharge piping.
h) Connect stack from boiler breaching to existing stack/vent connector.
i) Insulate all mechanical systems equal to adjacent original construction
j) Wire in control system for bldg.
27A and make boiler 100 % operational (27A only)
k) Provide all labor, materials, transportation, equipment, supplies and supervision as required for
piping in Heat Exchanger and Heater Coil located in the boiler 4 area, 7CC
Update #1 ·
Provide all labor, materials, transportation, equipment, supplies
and supervision as required for each relocated boiler @ 27A and A6.
a) Pipe in relocated boiler’s steam supply to existing steam header.
b) Pipe in relocated boiler’s feedwater supply to feedwater supply header
c) Pipe in relocated boiler’s bottom blowdown system to existing bottom blowdown header.
d) Pipe in relocated boiler’s surface blow system to second isolation valve.
e) Pipe in relocated boiler’s gas train to existing gas supply pipe
f) Wire in relocated boiler’s boiler/burner/blower/VFD power supply (A6 and 27A) and control
wiring (27A) where indicated. Wire in feedwater control valve, conductivity sensor, and surface
blowdown valve
g) Pipe in relocated boiler’s Safety valve discharge piping.
h) Connect stack from boiler breaching to existing stack/vent connector.
i) Insulate all mechanical systems equal to adjacent original construction
j) Wire in control system for bldg.
27A and make boiler 100 % operational (27A only)
k) Provide all labor, materials, transportation, equipment, supplies and supervision as required for
piping in Heat Exchanger and Heater Coil located in the boiler 4 area, 7CC.
Files
| File | Type | Posted |
|---|---|---|
| Attachment_1_N4008516R4638_Bid_Schedule.docx | DOCX document | |
| RFP_N4008516R4638_Boiler_Thermal_Efficiency.docx | DOCX document | |
| Attachment_2_Statement_of_Work.pdf | ||
| Attachment_4_FY16_Base_Access_Request_.xlsx | XLSX spreadsheet |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity