B & F Project 24Z1AIT Building 1 Interior Upgrade Sprinkler System
Closed Solicitation Posted
- Solicitation number
- 15B11124Q0000022
- Agency
-
Federal Correctional Institution Memphis
Correctional Facilities, Department of Justice
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 333998 All Other Miscellaneous General Purpose Machinery Manufacturing
- PSC
- 1290 Miscellaneous Fire Control Equipment
- Place of performance
- Bartlett, Tennessee 38134, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Justice, Bureau of Prisons, Federal Correctional Institution Memphis is seeking a contractor to upgrade the sprinkler system in Building I at their facility. The key requirements include furnishing and installing a new backflow preventer, removing and replacing existing sprinkler heads and piping, disconnecting and capping an existing fire sprinkler line, replacing sprinkler heads in classrooms and restrooms, installing new sprinkler piping, and adding sway braces, retainer straps, and flexible couplings. All new sprinkler systems must be tested in accordance with NFPA 13. The solicitation number is 15B11124Q0000022 and the deadline for responses is September 17, 2024.
This is a one-time, facility-specific project set aside for small businesses. The place of performance is Bartlett, TN 38134, USA. No incumbent or current contractor information is provided, and the potential award value or budget range is not specified. The NAICS code is 333998 - All Other Miscellaneous General Purpose Machinery Manufacturing, and the PSC code is 1290-P - Miscellaneous Fire Control Equipment.
Notice text
The FCI Memphis is a facility with a rated capacity of 862 low-security inmates within a secure perimeter fence. The Building I was previously utilized in a factory setting when FPI(Federal Prison Industries) used the building. The sprinkler system of Building I will need some upgrades due to the change of use for an inmate programming unit.
The contractor will provide labor, equipment, and materials needed to complete the project at Building I. The work includes, but is not limited to the following:
1. The contractor will furnish and install a new backflow preventer at the base of the wet pipe system.
2. The contractor will remove existing pendant fire sprinkler heads and drops throughtout the openceiling with rotating existing pipe upward for new tees and sprinkler heads.
3. The contractor will disconnect and cap the 2-inch fire sprinkler line through the wall for the adjacent building that is being demolished.
4. The classrooms and restrooms will need the fire sprinkler heads replaced and fitted for new grid/sheetrock ceilings. See the attached approved drawings of the layout.
5. Install new fire sprinkler piping above grid/sheetrock ceilings in restrooms to add fire sprinkler coverage and adjust fire sprinkler heads for proper clearances.
6. Install sway braces, retainer straps, and flexible couplings to protect the system piping from damage due to earthquakes in accordance with NFPA 13.
7. Test all new fire sprinkler systems in accordance with NFPA 13.
Files
| File | Type | Posted |
|---|---|---|
| Upgrade Sprinkler System.pdf |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| 2-STEP SEALED BID - TINKER AFB WWYK250019 Remove and Replace Fire Sprinkler in Plasma Booth Dust Collectors and Replace the Building F/A System, B3221 | Air Force Sustainment Center | Total Small Business |