AZ FLAP 62(1), King Canyon Trailhead
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 6982AF20B000041
- Agency
-
Federal Highway Administration
Department of Transportation
- Responses due
- Set-aside
- HUBZone
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Tucson AZ 85743 USA
Notice details come from SAM.gov. Updated .
About this opportunity
This solicitation seeks bids for the construction of the AZ FLAP 62(1) King Canyon Trailhead project in Pima County, Arizona. The Department of Transportation Federal Highway Administration is procuring the construction of a 30-stall trailhead parking lot with two horse trailer stalls, as well as entrance improvements including guardrail upgrades to Kinney Road near Saguaro National Park. Bids are due by October 9, 2020 and the contract is a firm-fixed price arrangement with an anticipated performance period of December 2020 through February 2021. Evaluation will be based on price.
The project is designated as a HUBZone set-aside. The primary NAICS code is 237110 and PSC code R499 covers the road construction work. The estimated budget range valued the contract between $250,000 to $700,000 to be performed in Tucson, Arizona. Ten potential bidders were identified including three who submitted bids ranging from $388,285 to $507,415 with an engineer's estimate of $440,000.
Notice text
2 versions
Update #2 · Latest ·
THIS IS A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE AVAILABLE.
THIS PROJECT IS BEING ADVERTISED ON A HUBZONE SET-ASIDE BASIS.
PROJECT DETAILS: AZ FLAP 62(1) King Canyon Trailhead
This project consists of the construction and paving of a trailhead parking lot which will include approximately 30 parking stalls and two horse trailer stalls. Additional entrance improvements will be made to Kinney Road which include upgrading existing guardrail. The project is located near the Saguaro National Park at the King Canyon Trail within Pima County, Arizona.
Anticipated Schedule
The anticipated construction duration is from November 2020 to January 2021.
Funding
The estimated cost range is between $250,000 and $700,000.
Update #1 ·
THIS IS A REQUEST FOR BID – PLANS AND SPECIFICATIONS ARE AVAILABLE.
THIS PROJECT IS BEING ADVERTISED ON A HUBZONE SET-ASIDE BASIS.
PROJECT DETAILS: AZ FLAP 62(1) King Canyon Trailhead
This project consists of the construction and paving of a trailhead parking lot which will include approximately 30 parking stalls and two horse trailer stalls. Additional entrance improvements will be made to Kinney Road which include upgrading existing guardrail. The project is located near the Saguaro National Park at the King Canyon Trail within Pima County, Arizona.
Anticipated Schedule
The anticipated construction duration is from December 2020 to February 2021.
Funding
The estimated cost range is between $250,000 and $700,000.
Files
Show all 13
Notice history
| Notice | Type | Posted |
|---|---|---|
| AZ FLAP 62(1), King Canyon Trailhead | Award Notice | |
| This notice | Solicitation | |
| AZ FLAP 62(1), King Canyon Trailhead | Pre-Solicitation | |
| AZ FLAP 62(1), King Canyon Trailhead | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| ND NP THRO 204(1) Buck Hill Road | Federal Highway Administration | No set-aside | |
| AZ BL COLO 7528(1) Burro Creek Road | Federal Highway Administration | Total Small Business | |
| UT NP ARCH 100(2) Bridges on Delicate Arch Road | Federal Highway Administration | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity