QnA 9 24 20.pdf

PDF 379 KB Posted

Attached to
AZ FLAP 62(1), King Canyon Trailhead
Solicitation number
6982AF20B000041
Issued by

About this file

This document contains questions and answers from a pre-bid meeting for solicitation number 6982AF20B000041. The project consists of constructing and paving a trailhead parking lot with approximately 30 parking stalls and two horse trailer stalls, as well as entrance improvements to Kinney Road including upgraded guardrail. The project location is near Saguaro National Park at the King Canyon Trail in Pima County, Arizona. The anticipated construction period is December 2020 to February 2021. Amendment A001 provides a revised completion date. The estimated cost range for the project is between $250,000 and $700,000. The Department of Transportation Federal Highway Administration is the contracting agency.

View the file

Other files

File Type Posted
Bid Tabs - AZ FLAP 62(1) King Canyon Trailhead .pdf PDF
Bid Opening Summary .pdf PDF
Amendment A002 10.7.2020.pdf PDF
Interested Vendor List 10 2 2020.pdf PDF
QnA 9 28 20.pdf PDF
Amendment A001.pdf PDF
QnA - 9 15 2020 - King Canyon Trailhead.pdf PDF
FP-14_Eng.pdf PDF
Plans - AZ FLAP 62(1)_King Canyon Trailhead.pdf PDF
6982AF20B000041.pdf PDF
Hydraulics Tech Memo.pdf PDF
Utility Summary.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for AZ FLAP 62(1), King Canyon Trailhead

September 15, 2020

Questions Answers 1 See Note to Bidders in Answer section. NOTE TO BIDDERS: U.S. Mailing providers such as: FedEx; UPS and USPS, have been experiencing a large volume due to COVID-

19. Please plan the mailing of your bids accordingly. Late bids will not be considered and processed in accordance with FAR provision 52.214-7.

2 Is it necessary to arrange a time for a site visit? If so who would be the point of contact?

The existing parking area is currently open to the public, so no need to coordinate a site visit.

September 24, 2020

Questions Answers 3 What is the anticipated Award date? Please see Amendment A001 for the subject project.

4 What is the anticipated NTP date? Please see Amendment A001 for the subject project.

5 Has the Government allowed a reasonable amount of time for construction?

Amendment A001 has been issued which lists a revised completion date.

6 Has the Government considered the Federal Holidays and Surrounding Days in the completion time?

Amendment A001 has been issued which lists a revised completion date.

7 Who is designated as the PE? The COE? This has not been determined yet.