Atchafalaya River, Bayous Chene, Boeuf and Black, Bayou Chene and Avoca Island Cutoff, Maintenance Dredging, Assumption, St. Mary and Terrebonne Parishes, Louisiana ED 24-024

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
W912P824B0053
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Louisiana, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The Department of the Army Corps of Engineers Engineering District New Orleans is seeking bids for the Atchafalaya River, Bayous Chene, Boeuf and Black, Bayou Chene and Avoca Island Cutoff, Maintenance Dredging project in Assumption, St. Mary and Terrebonne Parishes, Louisiana. The work consists of the satisfactory removal and disposal of all shoal material within the limits of work, including dike construction. The estimated time of completion is 371 calendar days for the Base Work and an additional 39 calendar days for Optional Work, if exercised. The solicitation includes 34 drawings and specifications, and any questions must be received by email no later than August 26, 2024.

This is an unrestricted procurement with no set-aside. The estimated value of the contract is between $25,000,000 and $100,000,000. Potential offerors include Crosby Dredging, Encore Dredging Partners, Manson Construction Co., Orion Marine Group, and Weeks Marine Inc. The place of performance is Assumption, St. Mary and Terrebonne Parishes, Louisiana.

Notice text

2 versions

Update #2 · Latest ·

Atchafalaya River, Bayous Chene, Boeuf and Black, Bayou Chene and Avoca Island Cutoff, Maintenance Dredging, Assumption, St. Mary and Terrebonne Parishes, Louisiana ED 24-024

The work consists of satisfactory removal and disposal of all shoal material within the limits of work including dike construction as described and as shown on the contract drawings. The estimated time of completion for Base Work is 371 calendar days and 39 additional calendar days for Optional Work, if exercised, after receipt of notice to proceed. The solicitation includes 34 drawings and specifications.

Any questions regarding this solicitation must be received via email by 12:00 pm CT Tuesday, September 3, 2024.

Update #1 ·

Atchafalaya River, Bayous Chene, Boeuf and Black, Bayou Chene and Avoca Island Cutoff, Maintenance Dredging, Assumption, St. Mary and Terrebonne Parishes, Louisiana ED 24-024

The work consists of satisfactory removal and disposal of all shoal material within the limits of work including dike construction as described and as shown on the contract drawings. The estimated time of completion for Base Work is 371 calendar days and 39 additional calendar days for Optional Work, if exercised, after receipt of notice to proceed. The solicitation includes 34 drawings and specifications.

Any questions regarding this solicitation must be received via email by Monday, August 26, 2024.

Files

Notice history

Similar open opportunities

Opportunity Agency Set-aside Responses due
Atchafalaya river BAY, bar, and crewboat cut cutterhead dredge NOS. 4-2026,  OM26062 Louisiana, United States · NAICS 237990 ENDIST New Orleans No set-aside
Atchafalaya river BAY, bar, and crewboat cut cutterhead dredge NOS. 1-2026,  OM26059 Louisiana, United States · NAICS 237990 ENDIST New Orleans No set-aside
Atchafalaya river BAY, bar, and crewboat cut cutterhead dredge NOS. 3-2026, OM26061 Louisiana, United States · NAICS 237990 ENDIST New Orleans No set-aside
Atchafalaya river BAY, bar, and crewboat cut cutterhead dredge NOS. 1-4 2026 70118, United States · NAICS 237990 ENDIST New Orleans No set-aside
Atchafalaya river BAY, bar, and crewboat cut cutterhead dredge NOS. 2-2026, OM26060 Louisiana, United States · NAICS 237990 ENDIST New Orleans No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors