This document is a Solicitation Amendment 0002 for the federal contract opportunity W912P824B0053, Atchafalaya River, Bayous Chene, Boeuf and Black, Bayou Chene and Avoca Island Cutoff, Maintenance Dredging, Assumption, St. Mary and Terrebonne Parishes, Louisiana ED 24-024.

The amendment provides responses to industry questions regarding the solicitation. Key details include:

  • The bid opening date remains unchanged.
  • Note 7 on the bid schedule is revised to confirm that Bid Item 0006, not 0005, is excluded from the Variation in Estimated Quantity clause.
  • The last dredging dates and dimensions are provided for Bayou Black, Bayou Boeuf, and Bayou Chene.
  • Material placement in Penchant East and West is to be a maximum of +6.0 ft NAVD88, not a minimum.
  • Detailed end area survey data is provided for the channels to be dredged.

No other terms or conditions of the solicitation have been changed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The subject solicitation for Atchafalaya Maint Dredging Chene, Boeuf, and Black is hereby amended to answer questions from industry as show n on the attached continuation pages.

The bid opening date and time remains unchanged.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 15

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P824B0053

X 9B. DATED (SEE ITEM 11)

12-Aug-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0002

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Sep-2024

CODE

USACE, CONTRACTING DIVISION

ATTN: HPO CT - ROOM 184

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P824B0053

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - SF 30 CONTINUATION

The following have been added by full text:

QUESTIONS AND ANSWERS

Questions and Answers updated 9/6/2024

QUESTION 1: Note 7 on the bid schedule states that Bid Item 0005 is excluded from the Variation in Estimated Quantity clause. However, the clause states that it applies to item Nos. 0002, 0003, and 0005. Please confirm that Bid Item 0005 is included under the clause.

RESPONSE 1: Inclusion of CLIN 0005 in note 7 is in error. Note should only apply to CLIN 0006. Note is revised with this response to read, “The quantity shown in Item 0006 is for evaluation purposes only. Payment for this line item will be based on the actual quantity used and it shall be excluded from the clause FAR 52.211-18, “VARIATION IN ESTIMATED QUANTITY.”

QUESTION 2: What is the date of last dredging for Bayou Black Sta. 4+00 to 96+00? Please also provide dredging dimensions.

RESPONSE 2: Based on Contract 88-C-0155., The limits of dredging were non-continuous. Work included Station 9+00 C/L to Station 158+00 C/L and from Station 205+00 C/L to Station 251+89.62 C/L Bayou Black - GIWW.

Channel width was 400 feet with dredging to elevation (-)22.0ft MLG with overdepth at (-)24.0ft MLG.

QUESTION 3: What is the date of last dredging for Bayou Boeuf Sta. 4+00 to 96+00? Please also provide dredging dimensions.

RESPONSE 3: Based on Contract 88-C-0155., The limits of dredging was Station 2+00 C/L to Station 96+00 C/L on Bayou Boeuf; The contract involved dredging a 400 foot wide channel to an elevation of (-)22. 0ft MLG and an allowable overdepth to (-)24.0 ft MLG in all the reaches of work except in the upper portion of Bayou Boeuf from Station 2+00 to Station 65+45. In this reach the channel width was 300ft wide and widening to 400ft wide in curves up to Station 95+22. The elevation remained at (-) 22.0ft MLG with overdepth at (-)24.0ft MLG.

QUESTION 4: Section 35 20 23 Paragraph 3.3.1.2 and Note 3 for Plan Sheet C-06 state that material shall be placed in Penchant East and West to a minimum elevation of +6.0 ft NAVD88. Does the Government intend for material to be placed to a minimum elevation of +6.0 ft or a maximum elevation of +6.0 ft?

RESPONSE 4: Material shall be placed in Penchant East and West to a MAXIMUM of +6.0 ft NAVD88.

“Minimum” was in error.

QUESTION 5: What are the survey end areas for all channels to be dredged?

RESPONSE 5: See attached tabulations of end areas.

(End of Summary of Changes)

End Area Avg EA

0+00 2683.748

500.00 2212.14

5+00 1740.523

500.00 1341.37

10+00 942.219

500.00 824.00

15+00 705.771

500.00 663.78

20+00 621.797 -

500.00 615.38

25+00 608.964

500.00 579.00

30+00 549.039

500.00 819.06

35+00 1089.082

500.00 1009.69

40+00 930.29

500.00 846.69

45+00 763.09

500.00 814.95

50+00 866.81

500.00 880.99

55+00 895.163

500.00 897.26

60+00 899.354

500.00 896.98

65+00 894.597

500.00 881.00

70+00 867.412

500.00 880.09

75+00 892.77

500.00 876.44

80+00 860.114

500.00 832.18

85+00 804.247

500.00 767.04

90+00 729.823

500.00 766.39

95+00 802.959

500.00 858.90

100+00 914.844

500.00 978.31

105+00 1041.778

500.00 1097.12

Bayou Black Feb 2024

Station Distance 1V on 2H

1 9/6/2024 1:00 PM

Bayou Black Feb 2024

Station Distance 1V on 2H

110+00 1152.46

500.00 1190.59

115+00 1228.713

500.00 1322.68

120+00 1416.642

500.00 1440.04

125+00 1463.435

500.00 1487.14

130+00 1510.844

500.00 1509.14

135+00 1507.429

500.00 1582.79

140+00 1658.148

500.00 1750.15

145+00 1842.161

500.00 2061.39

150+00 2280.621

500.00 2502.27

155+00 2723.912

500.00 2979.97

160+00 3236.029

500.00 3518.05

165+00 3800.065

500.00 4096.30

170+00 4392.536

500.00 4512.10

175+00 4631.662

500.00 4655.77

180+00 4679.887

500.00 3263.18

185+00 1846.463

500.00 1931.30

190+00 2016.138

500.00 2153.56

195+00 2290.979

500.00 2077.86

200+00 1864.733

500.00 1607.23

205+00 1349.724

500.00 1294.56

210+00 1239.388

500.00 1394.59

215+00 1549.782

500.00 1576.10

2 9/6/2024 1:00 PM

Bayou Black Feb 2024

Station Distance 1V on 2H

220+00 1602.41

500.00 1672.54

225+00 1742.677

500.00 1776.41

230+00 1810.137

500.00 1847.67

235+00 1885.199

500.00 1931.01

240+00 1976.813

500.00 2035.09

245+00 2093.362

500.00 2075.35

250+00 2057.335

Total Rounded

3 9/6/2024 1:00 PM

Bayou Boeuf FEBUARY 2024

0+00 0

500.00 340.50

5+00 680.992

500.00 917.13

10+00 1153.271

500.00 1156.86

15+00 1160.452

500.00 981.66

20+00 802.87 -

500.00 858.53

25+00 914.195

500.00 978.18

30+00 1042.158

500.00 1328.10

35+00 1614.036

500.00 1782.09

40+00 1950.137

500.00 1792.10

45+00 1634.056

500.00 1680.45

50+00 1726.836

500.00 1930.65

55+00 2134.458

500.00 1820.24

60+00 1506.013

500.00 1348.00

65+00 1189.983

500.00 1455.22

70+00 1720.461

500.00 1353.93

75+00 987.402

500.00 891.82

80+00 796.239

500.00 864.05

85+00 931.862

500.00 992.63

90+00 1053.405

500.00 965.56

95+00 877.724

500.00 546.91

100+00 216.089

500.00 288.08

105+00 360.071

500.00 481.19

Station Distance

1 9/6/2024 1:04 PM

Bayou Boeuf FEBUARY 2024

Station Distance

1V on 2H

110+00 602.312

500.00 478.07

115+00 353.823

500.00 237.91

120+00 122

500.00 170.26

125+00 218.514

500.00 208.06

130+00 197.613

500.00 166.55

135+00 135.491

500.00 139.59

140+00 143.684

500.00 178.21

145+00 212.729

500.00 211.44

150+00 210.145

500.00 157.64

155+00 105.127

500.00 164.91

160+00 224.689

500.00 387.96

165+00 551.238

500.00 596.59

170+00 641.949

500.00 588.15

175+00 534.353

500.00 392.71

180+00 251.068

500.00 158.64

185+00 66.212

201.98 56.10

187+01.983 45.985

Total

2 9/6/2024 1:04 PM

Bayou Chene Feb 2024

250+00 2057.335

500.00 1691.63

255+00 1325.928

500.00 1052.76

260+00 779.582

500.00 901.68

265+00 1023.784

500.00 1043.20

270+00 1062.621 -

500.00 1048.97

275+00 1035.326

500.00 697.70

280+00 360.077

500.00 222.45

285+00 84.83

500.00 90.06

290+00 95.295

500.00 73.13

295+00 50.968

500.00 49.54

300+00 48.111

500.00 33.77

305+00 19.432

500.00 53.52

310+00 87.607

500.00 556.71

315+00 1025.821

500.00 677.59

320+00 329.36

500.00 763.73

325+00 1198.107

500.00 1343.14

330+00 1488.165

500.00 1580.83

335+00 1673.494

500.00 1554.77

340+00 1436.042

500.00 1407.89

345+00 1379.739

500.00 1498.32

350+00 1616.904

500.00 1209.09

355+00 801.276

500.00 735.61

Station Distance

1 9/6/2024 1:06 PM

Station Distance

1V on 2H

360+00 669.953

500.00 559.17

365+00 448.381

500.00 562.32

370+00 676.258

500.00 903.11

375+00 1129.964

500.00 1380.28

380+00 1630.599

500.00 1646.90

385+00 1663.203

500.00 1351.58

390+00 1039.959

500.00 883.08

395+00 726.206

500.00 784.40

400+00 842.59

500.00 1075.62

405+00 1308.647

500.00 1609.69

410+00 1910.728

500.00 1880.91

415+00 1851.087

500.00 1708.62

420+00 1566.161

500.00 1327.54

425+00 1088.921

500.00 1019.98

430+00 951.046

500.00 972.18

435+00 993.315

500.00 1096.35

440+00 1199.376

500.00 1582.51

445+00 1965.644

500.00 1663.64

450+00 1361.632

500.00 1166.61

455+00 971.587

500.00 860.86

460+00 750.127

500.00 669.37

465+00 588.615

500.00 554.33

2 9/6/2024 1:06 PM

Station Distance

1V on 2H

470+00 520.041

500.00 392.83

475+00 265.626

500.00 257.90

480+00 250.176

500.00 237.55

485+00 224.931

500.00 210.73

490+00 196.525

500.00 350.75

495+00 504.969

500.00 588.88

500+00 672.79

500.00 744.59

505+00 816.385

500.00 931.85

510+00 1047.311

500.00 952.22

515+00 857.131

500.00 837.86

520+00 818.596

500.00 810.27

525+00 801.948

500.00 752.83

530+00 703.708

500.00 625.25

535+00 546.783

500.00 443.66

540+00 340.539

500.00 296.45

545+00 252.358

499.97 385.28

550+00 518.20

499.97 943.42

555+00 1368.63

499.97 1538.92

560+00 1709.20

499.97 1821.57

565+00 1933.94

499.97 1893.07

570+00 1852.21

499.97 2028.65

575+00 2205.10

499.97 2358.29

3 9/6/2024 1:06 PM

Station Distance

1V on 2H

580+00 2511.49

499.97 2568.99

585+00 2626.48

499.97 2598.68

590+00 2570.89

499.97 2377.63

595+00 2184.38

499.97 2016.81

600+00 1849.25

499.97 1593.82

605+00 1338.40

499.97 1091.87

610+00 845.34

499.97 784.93

615+00 724.52

499.97 752.45

620+00 780.39

499.97 734.73

625+00 689.07

499.97 746.11

630+00 803.15

499.97 902.30

635+00 1001.45

499.97 1073.58

640+00 1145.71

499.97 1035.62

645+00 925.52

499.97 759.19

650+00 592.86

499.97 518.73

655+00 444.61

499.97 338.49

660+00 232.36

499.97 131.79

665+00 31.22

499.97 20.08

670+00 8.93

499.97 4.88

675+00 0.83

499.97 1.71

680+00 2.60

499.97 13.73

685+00 24.86

499.97 22.80

4 9/6/2024 1:06 PM

Station Distance

1V on 2H

690+00 20.74

499.97 21.67

695+00 22.61

499.97 44.56

700+00 66.52

499.97 71.61

705+00 76.71

499.97 101.83

710+00 126.94

499.97 138.45

715+00 149.95

499.97 164.60

720+00 179.26

499.97 247.74

725+00 316.22

499.97 453.92

730+00 591.61

499.97 766.14

735+00 940.67

499.97 811.40

740+00 682.12

499.97 694.81

745+00 707.51

499.97 691.24

750+00 674.97

499.97 650.07

755+00 625.18

499.97 570.14

760+00 515.09

499.97 451.83

765+00 388.57

499.97 310.34

770+00 232.10

499.97 344.93

775+00 457.75

499.97 626.37

780+00 795.00

499.97 787.99

785+00 780.98

499.97 761.66

790+00 742.33

499.97 780.49

795+00 818.65

499.97 1154.23

5 9/6/2024 1:06 PM

Station Distance

1V on 2H

800+00 1489.82

499.97 1732.73

805+00 1975.65

499.97 2166.26

810+00 2356.86

499.97 2643.66

815+00 2930.45

499.97 3087.14

820+00 3243.83

499.97 3353.62

825+00 3463.41

499.97 3146.31

830+00 2829.20

499.97 2434.25

835+00 2039.30

499.97 1694.68

840+00 1350.07

499.97 1265.19

845+00 1180.32

499.97 1132.22

850+00 1084.13

499.97 984.14

855+00 884.16

499.97 1002.95

860+00 1121.74

499.97 1018.19

865+00 914.64

499.97 1009.86

870+00 1105.08

499.97 1126.12

875+00 1147.17

499.97 1176.85

880+00 1206.53

499.97 1111.95

885+00 1017.36

499.97 984.74

890+00 952.12

499.97 901.72

895+00 851.31

499.97 777.33

900+00 703.34

499.97 490.96

905+00 278.59

499.97 426.14

6 9/6/2024 1:06 PM

Station Distance

1V on 2H

910+00 573.70

499.97 638.46

915+00 703.22

499.97 878.49

920+00 1053.76

499.97 1140.20

925+00 1226.63

499.97 1342.94

930+00 1459.25

499.97 1622.08

935+00 1784.92

499.97 1718.09

940+00 1651.27

499.97 1593.60

945+00 1535.93

499.97 1598.11

950+00 1660.29

499.97 1752.41

955+00 1844.54

499.97 1898.52

960+00 1952.51

499.97 1939.52

965+00 1926.52

499.97 1919.96

970+00 1913.39

499.97 1932.79

975+00 1952.18

499.97 2016.16

980+00 2080.13

499.97 2084.81

985+00 2089.48

499.97 1759.10

990+00 1428.71

499.97 1662.94

995+00 1897.17

499.97 1601.81

1000+00 1306.45

499.97 1184.08

1005+00 1061.72

499.97 1035.39

1010+00 1009.05

499.97 865.05

1015+00 721.05

499.97 439.98

7 9/6/2024 1:06 PM

Station Distance

1V on 2H

1020+00 158.91

499.97 690.47

1025+00 1222.03

499.97 1335.58

1030+00 1449.13

499.97 1200.52

1035+00 951.91

499.97 829.58

1040+00 707.24

435.82 367.08

1044+38.82 26.92

Total

8 9/6/2024 1:06 PM

File details come from the government source that posted it. Updated .