Ashurst lake, long lake and moqui recreation site improvements

Closed Solicitation Posted

Solicitation number
12837120Q0180
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

NAICS code
238990 All Other Specialty Trade Contractors
PSC
Y1AA Construction Of Office Buildings
Place of performance
Payson AZ 85541 USA

Notice details come from SAM.gov. Updated .

Notice text

4 versions

Update #4 · Latest ·

Award Notice - Contract 12837120C0115 awarded in amount of $88,740.00 to ARCH GOVERNMENT SERVICES LLC. , PO BOX 2177, QUEEN CREEK AZ 85142-6426

OFFERS/ BIDs can be E-mailed to Contracting officer:  Columbus Campbell,  columbus.campbell@usda.gov

Amendment 0001

Added:
Exhibit 4 Site Visit Contractor Q&A
Exhibit 5 Map Location, Double Vault Spec's, and Vault Excavation
Exhibit 6 Asbestos & Lead Analysis
Copies : 0 changed to 1

The project consists demolition of existing toilets, Ashurst Lake is base bid item, Forked Pine is an optional bid item.

Removal and relocation of an existing vault toilet, Long Lake north to Moqui campground. This will require a crane with appropriate lifting capacities and truck/trailer capable of hauling a CXT tioga vault toilet building.

Excavation, preparation and backfill of vault holes. Preparation and compaction of vault hole bedding.

Relocating of any unsuitable or excess material to nearby onsite locations. Demolition of sidewalk at Long Lake north is a base bid item and replacement of sidewalk at Long Lake south optional bid item. Excavation and installation septic holding tank at Ashurst Lake base bid item

*Site Visit* Friday August 28, 2019 09:00 AM MS. POC: Kristina Brown, p: 928-527-8283 kristina.brown2@usda.gov

Contracting Officer: Columbus Campbell, 609-760-7587, columbus.campbell@usda.gov

Update #3 ·

OFFERS/ BIDs can be E-mailed to Contracting officer:  Columbus Campbell,  columbus.campbell@usda.gov

Amendment 0001

Added:
Exhibit 4 Site Visit Contractor Q&A
Exhibit 5 Map Location, Double Vault Spec's, and Vault Excavation
Exhibit 6 Asbestos & Lead Analysis
Copies : 0 changed to 1

The project consists demolition of existing toilets, Ashurst Lake is base bid item, Forked Pine is an optional bid item.

Removal and relocation of an existing vault toilet, Long Lake north to Moqui campground. This will require a crane with appropriate lifting capacities and truck/trailer capable of hauling a CXT tioga vault toilet building.

Excavation, preparation and backfill of vault holes. Preparation and compaction of vault hole bedding.

Relocating of any unsuitable or excess material to nearby onsite locations. Demolition of sidewalk at Long Lake north is a base bid item and replacement of sidewalk at Long Lake south optional bid item. Excavation and installation septic holding tank at Ashurst Lake base bid item

*Site Visit* Friday August 28, 2019 09:00 AM MS. POC: Kristina Brown, p: 928-527-8283 kristina.brown2@usda.gov

Contracting Officer: Columbus Campbell, 609-760-7587, columbus.campbell@usda.gov

Update #2 ·

Amendment 0001

Added:
Exhibit 4 Site Visit Contractor Q&A
Exhibit 5 Map Location, Double Vault Spec's, and Vault Excavation
Exhibit 6 Asbestos & Lead Analysis
Copies : 0 changed to 1

The project consists demolition of existing toilets, Ashurst Lake is base bid item, Forked Pine is an optional bid item.

Removal and relocation of an existing vault toilet, Long Lake north to Moqui campground. This will require a crane with appropriate lifting capacities and truck/trailer capable of hauling a CXT tioga vault toilet building.

Excavation, preparation and backfill of vault holes. Preparation and compaction of vault hole bedding.

Relocating of any unsuitable or excess material to nearby onsite locations. Demolition of sidewalk at Long Lake north is a base bid item and replacement of sidewalk at Long Lake south optional bid item. Excavation and installation septic holding tank at Ashurst Lake base bid item

*Site Visit* Friday August 28, 2019 09:00 AM MS. POC: Kristina Brown, p: 928-527-8283 kristina.brown2@usda.gov

Contracting Officer: Columbus Campbell, 609-760-7587, columbus.campbell@usda.gov

Update #1 ·

The project consists demolition of existing toilets, Ashurst Lake is base bid item, Forked Pine is an optional bid item.

Removal and relocation of an existing vault toilet, Long Lake north to Moqui campground. This will require a crane with appropriate lifting capacities and truck/trailer capable of hauling a CXT tioga vault toilet building.

Excavation, preparation and backfill of vault holes. Preparation and compaction of vault hole bedding.

Relocating of any unsuitable or excess material to nearby onsite locations. Demolition of sidewalk at Long Lake north is a base bid item and replacement of sidewalk at Long Lake south optional bid item. Excavation and installation septic holding tank at Ashurst Lake base bid item

*Site Visit* Friday August 28, 2019 09:00 AM MS. POC: Kristina Brown, p: 928-527-8283 kristina.brown2@usda.gov

Contracting Officer: Columbus Campbell, 609-760-7587, columbus.campbell@usda.gov

Files

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors