AIT Complex Phase IV Headquarters Building Construction Project, Fort Eustis; Virginia.
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W9123624B2014
- Agency
- ENDIST Norfolk US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 236220 Commercial and Institutional Building Construction
- Points of contact
-
- Jacob Coody jacob.w.coody@usace.army.mil (757) 201-7814
- Ekaterina Oxley ekaterina.oxley@usace.army.mil (757) 477-8514
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of the Army Corps of Engineers Engineering District Norfolk is procuring a firm-fixed-price contract for the AIT Complex Phase IV Headquarters Building Construction Project at Fort Eustis, Virginia. The work includes constructing a Battalion Headquarters Building (10,900 SF) and a Brigade Headquarters Building (9,450 SF), along with supporting facilities such as site development, utilities, and other infrastructure. The contract requires adherence to sustainability, energy efficiency, and antiterrorism standards. The statutory cost limitation for this project is $16,000,000. Proposals are due by June 20, 2024, and the government estimate for the project is $19,869,699.
This opportunity is set aside for small businesses. The solicitation received bids from 8 offerors, with total bid prices ranging from $17,003,058 to $22,162,343. The place of performance is Fort Eustis, Virginia, and the NAICS code is 236220 - Commercial and Institutional Building Construction. The PSC code is Y1AZ-P, Construction of Other Administrative Facilities and Service Buildings.
Notice text
5 versions
Update #5 · Latest ·
Amendment 0006: Issued to provide ProjNet Inquiries and Responses and revised attachment. Amendment 0005: Issued to revise the Wage Determination and provide revised attachments, which are related to answers provided in ProjNet. Amendment 0004: Issued to extend bid due date and bid opening date. Amendment 0003: Issued to provide scalable drawings. The Norfolk District, Corps of Engineers is procuring a firm-fixed-price contract for the AIT Complex Phase IV Headquarters Building Construction Project at Fort Eustis (Joint Base Langley Eustis); Virginia. The work will include construction of a standard design Battalion Headquarters Building (10,900 SF) and a standard design Brigade Headquarters Building (9,450 SF), both being single story facilities. Construction includes: special foundation, fire protection and alarm systems and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage, and site improvements. Heating and air conditioning will be provided by self-contained systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. The project will provide a building that will be safe to personnel, protect mission critical assets and comply with current design criteria and all applicable codes. All utility connection work required by the contract documents will need to be coordinated with the Privatized Utility Providers at JBLE-Eustis.In accordance with FAR 36.205, the statutory cost limitation for AIT Complex Phase IV Headquarters Building Construction Project is $16,000,000.00. This amount applies to CLINs 0001 through 0004. The Government shall reject an offer if its prices exceed applicable statutory limitations, unless laws or agency procedures provide pertinent exemptions. If in the Government?s interest, the contracting officer reserves the right to award of separate contracts for individual items whose prices are within or subject to applicable statutory limitations.
Update #4 ·
Amendment 0005: Issued to revise the Wage Determination and provide revised attachments, which are related to answers provided in ProjNet.Amendment 0004: Issued to extend bid due date and bid opening date. Amendment 0003: Issued to provide scalable drawings. The Norfolk District, Corps of Engineers is procuring a firm-fixed-price contract for the AIT Complex Phase IV Headquarters Building Construction Project at Fort Eustis (Joint Base Langley Eustis); Virginia. The work will include construction of a standard design Battalion Headquarters Building (10,900 SF) and a standard design Brigade Headquarters Building (9,450 SF), both being single story facilities. Construction includes: special foundation, fire protection and alarm systems and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage, and site improvements. Heating and air conditioning will be provided by self-contained systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. The project will provide a building that will be safe to personnel, protect mission critical assets and comply with current design criteria and all applicable codes. All utility connection work required by the contract documents will need to be coordinated with the Privatized Utility Providers at JBLE-Eustis.In accordance with FAR 36.205, the statutory cost limitation for AIT Complex Phase IV Headquarters Building Construction Project is $16,000,000.00. This amount applies to CLINs 0001 through 0004. The Government shall reject an offer if its prices exceed applicable statutory limitations, unless laws or agency procedures provide pertinent exemptions. If in the Government?s interest, the contracting officer reserves the right to award of separate contracts for individual items whose prices are within or subject to applicable statutory limitations.
Update #3 ·
Amendment 0004: Issued to extend bid due date and bid opening date. Amendment 0003: Issued to provide scalable drawings. The Norfolk District, Corps of Engineers is procuring a firm-fixed-price contract for the AIT Complex Phase IV Headquarters Building Construction Project at Fort Eustis (Joint Base Langley Eustis); Virginia. The work will include construction of a standard design Battalion Headquarters Building (10,900 SF) and a standard design Brigade Headquarters Building (9,450 SF), both being single story facilities. Construction includes: special foundation, fire protection and alarm systems and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage, and site improvements. Heating and air conditioning will be provided by self-contained systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. The project will provide a building that will be safe to personnel, protect mission critical assets and comply with current design criteria and all applicable codes. All utility connection work required by the contract documents will need to be coordinated with the Privatized Utility Providers at JBLE-Eustis.In accordance with FAR 36.205, the statutory cost limitation for AIT Complex Phase IV Headquarters Building Construction Project is $16,000,000.00. This amount applies to CLINs 0001 through 0004. The Government shall reject an offer if its prices exceed applicable statutory limitations, unless laws or agency procedures provide pertinent exemptions. If in the Government?s interest, the contracting officer reserves the right to award of separate contracts for individual items whose prices are within or subject to applicable statutory limitations.
Update #2 ·
Amendment 0003: Issued to provide scalable drawings.The Norfolk District, Corps of Engineers is procuring a firm-fixed-price contract for the AIT Complex Phase IV Headquarters Building Construction Project at Fort Eustis (Joint Base Langley Eustis); Virginia. The work will include construction of a standard design Battalion Headquarters Building (10,900 SF) and a standard design Brigade Headquarters Building (9,450 SF), both being single story facilities. Construction includes: special foundation, fire protection and alarm systems and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage, and site improvements. Heating and air conditioning will be provided by self-contained systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. The project will provide a building that will be safe to personnel, protect mission critical assets and comply with current design criteria and all applicable codes. All utility connection work required by the contract documents will need to be coordinated with the Privatized Utility Providers at JBLE-Eustis.In accordance with FAR 36.205, the statutory cost limitation for AIT Complex Phase IV Headquarters Building Construction Project is $16,000,000.00. This amount applies to CLINs 0001 through 0004. The Government shall reject an offer if its prices exceed applicable statutory limitations, unless laws or agency procedures provide pertinent exemptions. If in the Government?s interest, the contracting officer reserves the right to award of separate contracts for individual items whose prices are within or subject to applicable statutory limitations.
Update #1 ·
The Norfolk District, Corps of Engineers is procuring a firm-fixed-price contract for the AIT Complex Phase IV Headquarters Building Construction Project at Fort Eustis (Joint Base Langley Eustis); Virginia. The work will include construction of a standard design Battalion Headquarters Building (10,900 SF) and a standard design Brigade Headquarters Building (9,450 SF), both being single story facilities. Construction includes: special foundation, fire protection and alarm systems and Energy Monitoring Control Systems (EMCS) connection. Sustainability and energy enhancement measures are included. Supporting facilities include site development, utilities and connections, lighting, paving, parking, walks, curbs and gutters, storm drainage, information systems, landscaping and signage, and site improvements. Heating and air conditioning will be provided by self-contained systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. The project will provide a building that will be safe to personnel, protect mission critical assets and comply with current design criteria and all applicable codes. All utility connection work required by the contract documents will need to be coordinated with the Privatized Utility Providers at JBLE-Eustis.In accordance with FAR 36.205, the statutory cost limitation for AIT Complex Phase IV Headquarters Building Construction Project is $16,000,000.00. This amount applies to CLINs 0001 through 0004. The Government shall reject an offer if its prices exceed applicable statutory limitations, unless laws or agency procedures provide pertinent exemptions. If in the Government?s interest, the contracting officer reserves the right to award of separate contracts for individual items whose prices are within or subject to applicable statutory limitations.
Attachments
| File | Type | Posted |
|---|---|---|
| Abstract of Offerors-W9123624B2014-signed.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| AIT Complex Phase IV Headquarters Building Construction Project, Fort Eustis; Virginia. | Award Notice | |
| AIT Complex Phase IV Headquarters Building Construction Project, Fort Eustis; Virginia. | Solicitation | |
| AIT Phase IV Headquarters Buildings | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity