Advanced Notice: Maintenance Dredging of the Long Island Intracoastal Waterway Federal Navigation Project at Bellport Bay and Moriches Bay, Suffolk County, New York
Closed Special Notice Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- W912DS25BA011
- Agency
-
ENDIST New York
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KF Construction Of Dredging Facilities
- Place of performance
- Moriches, New York 11955, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The New York District of the U.S. Army Corps of Engineers (USACE) has issued a Special Notice for maintenance dredging of the Long Island Intracoastal Waterway (LIIW) Federal Navigation Project located in Bellport Bay and Moriches Bay, Suffolk County, New York. The project involves removing approximately 30,000 cubic yards of sand from the waterway, with planned placement along the shoreline of Cupsogue Beach County Park and/or Smith Point County Park. The dredging will be conducted to a depth of -6 feet Mean Lower Low Water (MLLW) plus 2 feet of allowable overdepth. The Special Notice was published on May 7, 2025, with a response deadline of May 22, 2025, and is classified as an unrestricted procurement under the NAICS category of Other Heavy and Civil Engineering Construction.
The primary objective of this project is to alleviate shoaling and maintain the authorized project dimensions, ensuring safe navigation for the U.S. Coast Guard and boating interests while simultaneously providing beneficial use of dredged material for shoreline stabilization. The government intends to award the contract by the end of August 2025, with work anticipated between October 2025 and January 2026. Contractors will be required to commence work within five calendar days of receiving the notice to proceed and maintain a minimum production rate of 2,000 cubic yards per calendar day. The estimated project cost ranges between $1,000,000 and $5,000,000, with liquidated damages of $2,722 per calendar day of delay assessed for incomplete work. The project will likely utilize a hydraulic cutterhead dredge, multiple barges, tugboats, pipeline, and land-based equipment such as bulldozers. All dredging and placement activities must meet federal, state, and local regulatory criteria.
Notice text
The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the Long Island Intracoastal Waterway (LIIW) Federal Navigation Project at Bellport Bay and Moriches Bay. The proposed maintenance dredging would remove approximately 30,000 cubic yards (CY) of sand with placement along the shoreline of Cupsogue Beach County Park and/or Smith Point County Park, subject to availability of funds. The placement areas are approximately 1.25 to 4.5 miles from the dredging area. Dredging would be required to a depth of -6 feet Mean Lower Low Water (MLLW) plus 2 feet allowable overdepth. The dredged material consists primarily of sand.
The purpose of the proposed work is to alleviate the effects of shoaling and maintain the authorized project dimensions, thereby providing safe and economical use of LIIW by the U.S. Coast Guard and navigational boating interests while providing future beneficial use of the dredged material as shoreline stabilization for Cupsogue Beach County Park and/or Smith Point County Park.
Based on past dredging cycles, it is anticipated that the proposed work will be performed by utilizing a hydraulic cutterhead dredge. Additionally, multiple barges, tugboats, pipeline and land based equipment such as bulldozers, will be needed to perform the work during the dredging or placement activities. The dredging and placement along the shoreline would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the dredging and placement sites are located.
Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the notice to proceed and maintain an integrated production rate of at least 2,000 cubic yards per calendar day for the dredging and placement of the dredged sand. The presence of dredging equipment in the channel will impact vessel traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact.
The work is estimated to cost between $1,000,000 and $5,000,000. It is the intention of the government to award in end of August 2025 and the proposed work is anticipated to take place between October 2025 and January 2026.
Liquidated Damages of $2,722.00 per calendar day of delay will be assessed to the contractor until all work under the contract is accepted as complete.
This is an unrestricted procurement.
Notice history
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Sources Sought for FY26 Atlantic Intracoastal Waterway Maintenance Dredging ��������� Select Sites | ENDIST Savannah | No set-aside | |
| James River Dredging Industry Day-Post Event Docs | ENDIST Norfolk | Total Small Business | |
| Construction Services for Confined Aquatic Disposal Cell Construction and Maintenance Dredging of the Providence River Federal Navigation Project, Providence, Rhode Island. | ENDIST New England | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity