Advance notice to industry: upcoming progressive design-build other transaction procurement

Closed Special Notice Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Fort Stewart, Georgia 31314, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The U.S. Army Corps of Engineers, Savannah District, issued an advance notice on July 21, 2026, alerting industry to an upcoming progressive design-build Other Transaction Agreement (OTA) procurement for barracks construction at Fort Stewart, Georgia, with an anticipated release of the Request for Qualifications/Request for White Papers on July 28, 2026. This is a non-committal planning notice only, not a formal solicitation.

The project involves design and construction of a new 86-bed Permanent Party Unaccompanied Enlisted Personnel Housing (UEPH) Barracks with a maximum gross area of 41,710 square feet, demolition of existing Building 212 following completion and turnover of the new facility, parallel site preparation, utility infrastructure, factory-based manufacturing, and procurement and installation of all furniture, furnishings, and equipment. The facility is intended to provide housing functionally and technically comparable to private-sector housing, with 485 square feet per occupant.

Procurement authority derives from 10 U.S.C. 2808a (Facility Construction or Repair). The project is coded NAICS 236220 (Commercial and Institutional Building Construction) and PSC Y1FC (Construction of Troop Housing Facilities). Anticipated maximum value is $38 million. The notice targets construction industry contractors, industrialized manufacturers, and modular integrators. The formal RFQ/white paper solicitation will appear on SAM.gov in late July 2026.

Notice text

ADVANCE NOTICE TO INDUSTRY: UPCOMING PROGRESSIVE DESIGN-BUILD OTHER TRANSACTION PROCUREMENT

W912HH-26-9-0001

Fort Stewart Building 212 UEPH Barracks Repair by Replacement Pilot Program

U.S. Army Corps of Engineers (USACE) – Savannah District
Anticipated Release Date: July 28, 2026
Project: PN 111716 Bldg 212 Repair by Replacement, Fort Stewart, Georgia
Statutory Authority: 10 U.S.C. § 2808a (Other Transaction Authority for Facility Construction and Repair)
NAICS Code: 236220 (Commercial and Institutional Building Construction)
PSC Code: Y1FC (CONSTRUCTION OF TROOP HOUSING FACILITIES)
Anticipated Maximum Value (NTE): $38,000,000

NOTICE PURPOSE & PLANNING CONTEXT

The U.S. Army Corps of Engineers (USACE), Savannah District, is issuing this Advance Notice to alert the construction industry, industrialized manufacturers, and modular integrators to an upcoming design-build opportunity.

This project will be executed as an Other Transaction Agreement (OTA) under the statutory authority of 10 U.S.C. § 2808a, Facility Construction or Repair.  

This is NOT a formal solicitation. This notice is for planning purposes only and is non-committal. The official Request for Qualifications (RFQ) / Request for White Papers is anticipated for release on SAM.gov in late July 2026.

PROJECT SCOPE

This project consists of the design and construction of a new 86-bed Permanent Party Unaccompanied Enlisted Personnel Housing (UEPH) Barracks and the demolition of the existing building 212 at Fort Stewart, GA, after the new barracks has been turned over and completed. The scope includes parallel site preparation, utility infrastructure, factory-based manufacturing, and the procurement and installation of all necessary furniture, furnishings, and equipment (FF&E).

The new facility will have a maximum gross area of 41,710 square feet (485 sq ft per occupant) and is intended to provide housing that is functionally and technically comparable to similar private-sector housing. Barracks functional spaces will adhere to the 2025 Army Barracks Standard for Permanent Party Unaccompanied Housing, Junior Enlisted and Junior NCOs Memorandum for square footages, with the exception of the required room module layout.

ANTICIPATED TWO-STEP SELECTION PROCESS

USACE Savannah District intends to utilize a streamlined, two-step qualifications-based selection (QBS) process to identify the most qualified partner. The information below could change before the final release of the request for white papers.

STEP 1: REQUEST FOR QUALIFICATIONS (RFQ) / WHITE PAPERS

Interested firms will submit a concise written qualifications package (maximum of 15 pages). Submissions will be evaluated against two main elements:

  • Capability and Experience

    • Relevant Experience: Demonstration of more than two (2) new construction projects of similar size (minimum 30,000 SF) and scope (multi-unit housing, dormitories, barracks). Renovations are not accepted as comparable.
    • Innovation & Speed: Documented use of innovative, accelerated, or off-site delivery techniques that successfully compressed schedule and cost.
  • Technical and Management Approach
    • Understanding: Demonstrated understanding of the project goals, constraints and affordability to stay within the budget ceiling.
    • Design Management: Approach to managing the design process, ensuring compliance with the 2025 Army Barracks Standard, UFCs, and standard building codes.
    • Manufacturing Experience: Explain the current manufacturing process and output and how that would relate and support this project.
    • Collaborative DB Philosophy: The firm’s management philosophy regarding Collaborative DB, focusing on partnership and transparent costing.
    • Organizational Structure: Clarity and effectiveness of the proposed Organizational Chart identifying key roles and reporting lines.

 The Government will shortlist and invite up to three (3) of the most highly qualified firms to Step 2.

STEP 2: PITCH MEETINGS & FACILITY TOURS

The Step 2 evaluation moves away from written proposals to assess physical plant readiness and live team dynamics:

  • Interactive Pitch Meetings: Shortlisted firms will participate in a confidential, collaborative working session with the USACE Project Delivery Team to evaluate:
  • Collaborative Capability & Risk Management (Pitch Presentation): Joint scope validation, real-time technical problem-solving, team chemistry.
  • Facility Site Visits: The Evaluation Team will tour the shortlisted firms' proposed manufacturing plants to verify production capacity and plant readiness.

TENTATIVE PROCUREMENT SCHEDULE

The Savannah District is executing this acquisition on an aggressive timeline to meet critical end-of-fiscal-year deadlines:

Milestone Event                                             Target Date

Release of Request for White Papers (RFQ)- July 28, 2026

Step 1 Submissions (White Papers) Due- August 6, 2026

Notification of Step 1 Shortlist- August 18, 2026

Step 2 Factory Site Visits / Tours and Pitch Presentations- August 19 – September 2, 2026

Selection of Most Highly Qualified Partner- September 8, 2026

Initiate Phase 1 Agreement & Terms Negotiations- September 9

OT Agreement Award (Full NTE Obligation)- September 30, 2026

Inquiries & SAM.GOV TRACKING

All preliminary general inquiries, clarification requests, and communications regarding this advance notice must be submitted via ProjNet: https://www.projnet.org/projnet

Bidder Inquiry Key: UTKUDU-RCT6X2

All future procurement files, notices, and the final RFQ solicitation package will be posted to the System for Award Management (SAM.gov) and the PIEE Solicitation Module. Interested parties are solely responsible for monitoring SAM.gov for official releases and updates.

OFFICIAL DISCLAIMER

This advance notice does not constitute a Request for Proposals (RFP), a Request for White Papers, or a promise by the Government to issue a solicitation in the future. The Government is not seeking proposals or bids at this time. USACE is not responsible for any administrative, travel, engineering, or proposal costs incurred by industry in response to this notice or in preparation for Step 1 submissions.

Notice history

Notice Type Posted
BLDG 212 Fort Stewart GA OTA Award Award Notice
BLDG 212 Fort Stewart GA OTA Latest solicitation Solicitation
This notice Special Notice
Sources Sought / RFI: Market Intelligence for Potential OTA - BLDG 212 Barracks Replacement, Fort Stewart, GA Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Market Intelligence: JDWC Progressive Design-Build OTA Fort Bragg, North Carolina 28310 · NAICS 236220 ENDIST Savannah No set-aside
Fort Stewart Base Operations - W5168W26RA014 Fort Stewart, GA 31314 · NAICS 561210 Department of the Army Total Small Business
RFI: Fort Wolters H Barracks Mineral Wells, Texas 76067, United States · NAICS 236220 ENDIST Fort Worth No set-aside
Infantry Platoon Battle Course (IPBC) Fort Bragg, North Carolina Fort Bragg, NC · NAICS 236220 ENDIST Savannah No set-aside
Sources Sought - Construction Repair Building 6413 Secure Space (511669 & 519580) Barksdale AFB Barksdale AFB, Louisiana 71110, United States · NAICS 236220 ENDIST Fort Worth No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity