RFP- $999M RDI #2 UNR IDIQ MATOC
Awarded Award Notice Posted
- Solicitation number
- W9128F19R0043
- Agency
- ENDIST Omaha US Army Corps of Engineers, Department of Defense
- Awarded
- to Cdm-Alberici JV
- Set-aside
- No set-aside
Opportunity facts
- Contract number
- W9128F20D0002 Federal IDV award
- NAICS code
- 236220 Commercial and Institutional Building Construction
- PSC
- Not on record
Notice details come from SAM.gov. Updated .
About this opportunity
This Award Notice is for a $999 million Rapid Disaster Infrastructure Response Multiple Award Task Order Contract issued by the U.S. Army Corps of Engineers Omaha District. The contract facilitates time-sensitive disaster, infrastructure, and construction projects for federal customers requiring flexibility and expediency over an eight year period. Task orders under the contract may involve security and defense mission support, disaster response activities such as debris removal and infrastructure repair, and domestic infrastructure construction projects including roads, bridges, utilities and other facilities. Mobilization within three days of notification may be required for emergency response activities.
Notice text
9 versions
Update #9 · Latest ·
There are seven (7) Contracts awarded under this MATOC with a shared capacity of $999M.
W9128F19D0002
CDM-Alberici
75 State St. STE 701
Boston MA 02109-1940
W9128F20D0003
Aptim Federal Services, LLC
1725 Duke St STE 400
Alexandria VA, 22314
W9128F20D0004
Wood-Cape
751 Arbor Way STE 180
Blue Bell PA 19422-1972
W9128F20D0005
Weston Solutions, Inc.
1400 Weston Way
West Chester PA 19380-1492
W9128F20D0006
ECC Environmental LLC
1240 Bayshore HWY STE 317
Burlingame CA 94010-1805
W9128F20D0007
Conti Federal Services, LLC
2045 Lincoln Hwy
Edison NJ 08817-3334
W9128F20D0008
AECOM Technical Services, Inc.
300 S. Grand Ave STE 1100
Los Angeles CA, 90071-3173
. Awarded Vendors: CDM-Alberici. Contract Award Dollar Amount: $999,000,000.00. Contract Award Date: 2019-10-10.
Update #8 ·
30 July2019- Amendment 0006 is formally posted to FBO with changes to 00 10 00, Attachment #2, Sample Project SOW, Attachment #3, Cost Spreadsheet, and 00 22 00.
Please note that FBO shows this action as Amendment 0007. Disregard Amendment numbering in FBO.
26July2019- Amendment 0005 is formally posted to FBO with changes to Attachment #2, Sample Project SOW, Attachment #3, Cost Spreadsheet, and 00 22 00.
Please note that FBO shows this action as Amendment 0006. Disregard Amendment numbering in FBO.
23July2019- Amendment 0004 is formally posted to FBO with changes to Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0005. Disregard Amendment numbering in FBO.
22July2019- Amendment 0003 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0004. Disregard Amendment numbering in FBO.
12July2019- Amendment 0002 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment 3, Cost Spreadsheet.
Please note that FBO shows this action as Amendment 0003. Disregard Amendment numbering in FBO.
----Break------
11July2019- Amendment 0001 is formally posted to FBO to include the Summary of Work to the RFP.
Please note that FBO shows this action as Amendment 0002. Disregard Amendment numbering in FBO.
-----Break------
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #7 ·
26July2019- Amendment 0005 is formally posted to FBO with changes to Attachment #2, Sample Project SOW, Attachment #3, Cost Spreadsheet, and 00 22 00.
Please note that FBO shows this action as Amendment 0006. Disregard Amendment numbering in FBO.
23July2019- Amendment 0004 is formally posted to FBO with changes to Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0005. Disregard Amendment numbering in FBO.
22July2019- Amendment 0003 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0004. Disregard Amendment numbering in FBO.
12July2019- Amendment 0002 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment 3, Cost Spreadsheet.
Please note that FBO shows this action as Amendment 0003. Disregard Amendment numbering in FBO.
----Break------
11July2019- Amendment 0001 is formally posted to FBO to include the Summary of Work to the RFP.
Please note that FBO shows this action as Amendment 0002. Disregard Amendment numbering in FBO.
-----Break------
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #6 ·
23July2019- Amendment 0004 is formally posted to FBO with changes to Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0005. Disregard Amendment numbering in FBO.
22July2019- Amendment 0003 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0004. Disregard Amendment numbering in FBO.
12July2019- Amendment 0002 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment 3, Cost Spreadsheet.
Please note that FBO shows this action as Amendment 0003. Disregard Amendment numbering in FBO.
----Break------
11July2019- Amendment 0001 is formally posted to FBO to include the Summary of Work to the RFP.
Please note that FBO shows this action as Amendment 0002. Disregard Amendment numbering in FBO.
-----Break------
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #5 ·
22July2019- Amendment 0003 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment #2, Sample Project SOW.
Please note that FBO shows this action as Amendment 0004. Disregard Amendment numbering in FBO.
12July2019- Amendment 0002 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment 3, Cost Spreadsheet.
Please note that FBO shows this action as Amendment 0003. Disregard Amendment numbering in FBO.
----Break------
11July2019- Amendment 0001 is formally posted to FBO to include the Summary of Work to the RFP.
Please note that FBO shows this action as Amendment 0002. Disregard Amendment numbering in FBO.
-----Break------
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #4 ·
12July2019- Amendment 0002 is formally posted to FBO with changes to Sections 00 10 00, 01 11 00, 00 22 00 and Attachment 3, Cost Spreadsheet.
Please note that FBO shows this action as Amendment 0003. Disregard Amendment numbering in FBO.
----Break------
11July2019- Amendment 0001 is formally posted to FBO to include the Summary of Work to the RFP.
Please note that FBO shows this action as Amendment 0002. Disregard Amendment numbering in FBO.
-----Break------
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #3 ·
11July2019- Amendment 0001 is formally posted to FBO to include the Summary of Work to the RFP.
Please note that FBO shows this action as Amendment 0002. Disregard Amendment numbering in FBO.
-----Break------
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #2 ·
05July2019: This Solicitation has been formally posted. Please see attachments for the RFP and supporting documentation.
-------Break-------
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidental design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construction applications and technologies needed to support time-sensitive construction projects in various locations within the U.S. (defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Update #1 ·
On or about 5 July 2019 the government intends to issue a solicitation for $999M. This is a Pre-solicitation for an Unrestricted Indefinite Delivery, Indefinite Quantity (IDIQ) Rapid Disaster Infrastructure (RDI) Response Multiple Award Task Order Contract (MATOC). The shared contract capacity of the MATOC is $999 million for an ordering period of eight (8) years: five (5) base year and one (1) three (3) year option. Task orders within the MATOC may be Firm Fixed Price or Cost Plus Fixed Fee contingent upon the Government's assessment or project risk.
This RDI MATOC facilitates time-sensitive disaster, infrastructure, and construction related activities in support of federally funded customers.
Projects will vary in size, complexity, location, and will require a high degree of flexibility and adaptability on the part of the contractor to respond quickly and effectively. The primary NAICS Code for this solicitation is 236220 - Commercial and Institutional Building Construction with a size standard of $36,500,000.00. All work will be time-sensitive in nature, necessitating an expedited response to mitigate threat to life and property and/or operational impacts to the Government.
Examples include, but are not limited to:
Security and Defense Mission Support.
Support to USACE Protective Design Center of Expertise (PDC) and other federal agencies for time sensitive construction response actions in support of Security and Defense initiatives.
Support to the Department of Homeland Security (DHS).
The DHS mission is to secure our homeland by leading the unified national effort to protect America. The DHS will prevent and deter terrorist attacks and protect against and respond to threats and hazards to the nation. Homeland Security includes, but is not limited to, protection of transportation systems, disruption of threats to installations, protection of critical infrastructure and key assets, positioning of resources to be ready for defense, and activities to ensure health and safety of the United States of America and its citizens.
Disaster Support Response.
The intent of the RDI Disaster Support Response is to provide time-sensitive construction/rehabilitation support. Projects may include, but are not limited to, roads (primary, secondary and short-term temporary fixes), bridges, irrigation systems, coastal and marine resource management and development, dams and other water related structures, electric distribution systems, water and sanitation systems schools, clinics or hospitals, emergency power and other civil engineering works.
In addition, under USACE responsibilities to FEMA, the RDI MATOC may be used to provide USACE Mission Support through the local MSCs or District Commander to address debris removal and/or unwatering activities, provided the requested services are within the scope of the contract.
Infrastructure Construction Support.
The RDI MATOCs may support various time critical infrastructure construction repair/rehabilitation projects with the most prevalent being rehabilitation of levee systems. However, infrastructure construction support may include work on other essential infrastructure facilities, such as: roads, bridges, dams, utility systems (power, water, sewer, telephone, telecommunications) railways, subways, airports, and harbors, which are publicly owned, regulated or maintained by the government. This includes work on buildings, structures or other real property, when necessary to support a larger infrastructure mission assignment.
Each Task Order Request for Proposal will identify when the contractor must mobilize, however, emergency recovery actions may require mobilization within 3 days of Government Notification.
Projects may require incidenal design and ecological/environmental, hazardous waste recovery, and munitions work.
This Scope also encompasses construciton applications and technologies needed to support time-sensitive construction projects in various locations within the U.S.(defined as all 50 states and District of Columbia) and outlying areas as defined by FAR Part 2. Individual Task Orders will further define specific project requirements once identified.
.
Attachments
Show all 25
Notice history
| Notice | Type | Posted |
|---|---|---|
| RFP- $999M RDI #2 UNR IDIQ MATOC | Award Notice | |
| RFP- $999M RDI #2 UNR IDIQ MATOC | Award Notice |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity