911th Vehicle Maintenance Shop at Fort Belvoir, VA

Closed Special Notice Posted

This opportunity was awarded. See the award notice from , or the latest solicitation from .

Solicitation number
W912DR21R0018
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Fort Belvoir VA 22060 USA

Notice details come from SAM.gov. Updated .

About this opportunity

This Special Notice from the U.S. Army Corps of Engineers, Baltimore District, solicits feedback from the construction community regarding the potential use of a Project Labor Agreement for the 911th Vehicle Maintenance Shop project at Fort Belvoir, Virginia, estimated to exceed $20 million. The agency seeks to understand the potential impacts and advantages of using a PLA on this large-scale construction effort.

The notice requests responses to a series of questions by March 31st to gather market data on the use of PLAs on similar past projects in the local area. Contractors are asked to provide details on project costs, schedules, labor needs and any challenges experienced on projects completed in the last 2-5 years. This market survey will help the agency determine the appropriate acquisition approach to maximize economy and efficiency on this vehicle maintenance facility construction project at Fort Belvoir as mandated by Federal Acquisition Regulation. Responses are limited to seven pages and must be submitted via email by the stated deadline.

Notice text

Y- 911th Vehicle Maintenance Shop at Fort Belvoir, Virginia

W912DR21R0018                                                                                                              

The U.S. Army Corps of Engineers, Baltimore District, is soliciting comments from the construction community addressing the potential use of a Project Labor Agreement (PLA) for a large scale construction project (exceeding $20 million) located at Fort Belvoir, VA.

Project Description: 

The project is to construct a standard-design medium Vehicle Maintenance Shop to include hazardous waste storage and oil storage buildings, vehicle parking lot, open and organizational equipment storage and heavy equipment parking with options for a vehicle storage building and Company Operations Facility. Construction will include special foundations and connection to Energy Monitoring Control Systems (EMCS), intrusion detection systems (IDS) installation, fire alarm and suppression and building information system. Supporting Facilities include electric services, water and gas distribution and wastewater collection lines, a water pump for fire suppression system, access road, pavements, curbs and gutters, storm drainage, site preparation, environmental studies and documentation, and information systems. Antiterrorism/force protection measures include laminated glass windows in reinforced frames, reinforced exterior doors, security lighting, barriers, and visual screening. Heating and air conditioning will be provided by stand-along systems. Measures in accordance with the Department of Defense (DoD) Minimum Antiterrorism for Buildings standards will be provided. Facilities will be designed to a minimum life of 40 years in accordance with DoD's Unified Facilities Code (UFC 1-200-02) including energy efficiencies, building envelope and integrated building systems performance. Sustainability and Energy measures will be provided. Access for individuals with disabilities will be provided. Comprehensive building and furnishings related to interior design services are required. Demolish 1 Building (5,147 SF), 1 Modular Buildings (4,820 SF) and Air Conditioning (Estimated 150 Tons).

PLA Background Information:

A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C. 158(f).

Federal Acquisitions Regulation (FAR) 22.503, Policy states: Project Labor Agreement (PLA) is a tool that agencies may use to promote economy and efficiency in Federal procurement.  Pursuant to Executive Order 13502, agencies are encouraged to consider requiring the use of project labor agreements in connection with large-scale construction projects.  An agency may, if appropriate, require that every contractor and subcontractor engaged in construction on the project agree, for that project, to negotiate or become a party to a project labor agreements will (1) advance the Federal Government’s interest in achieving economy and efficiency in Federal procurement, producing labor-management stability, and ensuring compliance with laws and regulations governing safety and  health, equal employment opportunity, labor and employment  standards, and other matters; and (2) be consistent with law. 

Reference: FAR 52.222-33 Notice of Requirement for Project Labor Agreement, Clause: FAR 52.222-34 Project Labor Agreement.

The construction community is invited to comment on the use of PLA’s by responding to the following questions:

  1. Do you have knowledge that a PLA has been used in the local areas on projects of this kind?  If so, please provide supporting documentation.
  2. Are you aware of skilled labor shortage in the areas for those crafts that will be needed to complete the referenced project?  If so, please elaborate and provide supporting documentation where possible.
  3. Are you aware of time sensitive issues/scheduling requirements that would affect the rate at which the referenced project should be completed?  If so, please elaborate and provide supporting documentation where possible.
  4. Identify specific reasons why or how you believe a PLA would advance the Federal Governments interest in achieving economy and efficiency in federal procurement.
  5. Identify specific reasons why you do not believe a PLA would advance the Federal Governments interest in achieving economy and efficiency in federal procurement.
  6. Identify any additional information you believe should be considered on the use of a PLA on the referenced project.
  7. Identify any additional information you believe should be considered on the non-use of a PLA on the referenced project. 

The information gathered in this exercise should include the following information on projects completed in the last 2-5 years:

  1. Project Name and Location
  2. Detailed Project Description
  3. Initial Cost Estimate vs. Actual Final Cost
  4. Was the project completed on time?
  5. Number of craft trades present on the project
  6. Was a PLA used?
  7. Were there any challenges experienced during the project?

Responses are to be sent via email to Michael Getz at michael.j.getz@usace.army.mil no later than 11:00 AM (EST) on 31 March 2021.  Responses are limited to seven (7) pages

This is NOT A REQUEST FOR PROPOSAL and does not constitute any commitment by the Government.  Reponses to this labor market survey will be used by the Government to make appropriate acquisition decisions.  All interested sources must respond to future solicitation announcements separately from responses to this survey.

Notice history

Notice Type Posted
911th Vehicle Maintenance Shop at Fort Belvoir, VA Award Award Notice
911th Vehicle Maintenance Shop at Fort Belvoir, VA Latest solicitation Solicitation
911th Vehicle Maintenance Shop at Fort Belvoir, VA Pre-Solicitation
This notice Special Notice
911th Vehicle Maintenance Shop at Fort Belvoir, VA Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
PLA RFI for Repair of Waterfront Utility Services Transmitted via a Utilidor Tunnel at NSB Kings Bay, GA Kings Bay, Georgia, United States · NAICS 237110 Naval Facilities Engineering Command No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors