63100PR270000009 Repair Floating Dock
Open Special Notice Posted
- Solicitation number
- 70ZL74
- Agency
- Not on record
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Yorktown, Virginia 23690, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Coast Guard is issuing Special Notice 63100PR270000009 for repair of nine floating Jet Dock Systems at Building 292, with responses due November 9, 2026. No set-aside is used, but the attached statement of work designates the work as sole source because Jet Dock Systems Inc holds exclusive patent rights and sells the products only directly from its Cleveland, Ohio facility. The contractor provides all labor, materials, and equipment to remove and replace 18 large and 40 small module assemblies, keel deflection systems, pontoon straps and hardware, and 45 structural and pontoon guide beams, and to install cathodic protection on those beams. Scope also includes approximately six pontoons, freshwater washdown hoses, bunk tusk systems, and new inner bunk systems for 29-foot RB-S II (8,400 lbs), 26-foot TANB (7,300 lbs), and 26-foot CB-OTH-V (7,470 lbs) boats, per drawing 2-29202-1. Work must commence within 30 calendar days of award and finish within 150 days. A mandatory site visit and preconstruction conference are required. Before work begins, the contractor submits a project schedule, safety plan, material submittals, bond, and insurance. Work is limited to 7:00 AM to 5:00 PM, Monday through Friday, excluding federal holidays, unless the COR approves in advance with 48 hours' notice. Work must comply with COE EM 385 1-1 (2014 Edition), OSHA, the National Electrical Code, and NFPA standards. NAICS is 237990 and PSC is Z2PZ.
Notice text
Contractor to provide all labor, materials, and equipment necessary to repair the floating Jet Docks, BLDG 292. Work consists of:
- Remove and replace 18 damaged large Module Assemblies (MAs).
- Remove and replace 40 open well style or damaged small MAs and replace with standard small MAs.
- Remove and replace keel deflection system (KDS) on all nine docks.
- Remove and replace all pontoon straps and hardware (36” lifting eyes) for all nine docks.
- Remove and replace all 27 structural support beams and all 18 pontoon guide beams across all nine docks – 45 total.
- Install new cathodic protection system on all beams – 45 total.
- Remove valves and wiring on powerhead for all nine docks and replace with standard valves and wires.
- Install two freshwater washdown hoses, 40 ft length, per dock – 18 total.
- Install protection system between MAs and piling – one per dock, nine total.
- Install bunk tusk system, one per dock, nine total.
- Rebuild the dock stern to include intermediate corrugation support on all nine docks.
- Remove and replace any damaged pontoons with the same size and kind. If no longer in production, replace with closest approximation – approximately 6 pontoons.
- Install additional MAs on docks that are assigned the 29 ft RB-S II boats – 5 docks total, approximately 30 large MAs, 5 small MAs.
- Install new inner bunk systems on all docks to accommodate the boats described below:
- 29 ft RB-S II boats (8,400 lbs),
- 26 ft TANB boats (7,300 lbs), and
- 26 ft CB-OTH-V boats (7,470 lbs).
- Calibrate existing and replacement pontoons for the boats described above.
- For a layout of dock assignments, refer to the included drawing 2-29202-1.
Files
| File | Type | Posted |
|---|---|---|
| 12a. 31300766 SOW.pdf | ||
| 12a. 31300766 Drawing.pdf | ||
| 12a. Construction Provision and Clauses.pdf |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity