About this opportunity

The Department of Veterans Affairs Medical Center at West Haven, Connecticut issued a notice of intent to award a sole-source firm-fixed-price contract for replacement of one 150kVA TMEiC uninterruptible power supply for a Canon Aquilion One PRISM CT system, with responses due by August 3, 2026 at 4:30 PM Eastern Time. The Government intends to award without competition unless respondents submit clear and convincing evidence that competition would be advantageous. The VA Medical Center determined that only one responsible source exists and no other supplies or services will satisfy agency requirements based on compatibility with the existing Canon CT equipment.

The contractor must deliver the specified 150kVA TMEiC UPS unit to the Radiology Department at 950 Campbell Avenue, West Haven, Connecticut, and provide complete installation, operation, and service documentation within three business days of award. The equipment must meet defined technical specifications including 480 VAC three-phase input and output at 60Hz, minimum 400 VDC DC voltage, reflected current THD of 3% at full load, 20-millisecond transient recovery time, and not exceed 860 pounds with dimensional limits of 81 inches height (plus 19.7 inches clearance), 33 inches depth (plus 40 inches service clearance), and 28 inches width. The contractor shall remove and dispose of the existing UPS, install the new system, and complete all work within 180 days of award during normal business hours, Monday through Friday, 7 AM to 5 PM, excluding Federal Holidays. Contracting Specialist Manases Cabrera at manases.cabrera@va.gov or 781-687-4418 is the point of contact.

Notice text

This notice is being published in accordance with the Federal Acquisition Regulation (FAR) Part 5, requiring the dissemination of information on proposed contract actions. This is a notice of intent to award a sole-source contract pursuant to 10 U.S.C 2304 (C)(1), as implemented by FAR 6, only one responsible source, and no other supplies or services will satisfy agency requirements, and brand-name descriptions.

The Department of Veterans Affairs Medical Center located at 950 Campbell Ave, West Haven CT 06516 has a requirement for the replacement of the one (1) uninterruptible power supply for the Canon Aquilion One PRISM CT system.

The Government intends to award a firm-fixed-price sole source contract.

A determination by the Government not to compete with this proposed contract based upon responses to this notice is solely within the discretion of the Government. This notice of intent is not a request for competitive proposals. This is a written notice to inform the public of the Government's intent to award on a sole source basis.

Interested parties may identify their interest and capability to respond to the requirement. Any response to this notice must show clear and convincing evidence that competition will be advantageous to the Government.

Please contact Manasés Cabrera, Contracting Specialist, with the responses or questions regarding this requirement at manases.cabrera@va.gov.

This notice will close on August 3, 2026, at 4:30 PM Eastern Standard Time (EST)

STATEMENT OF WORK FOR THE REPLACEMENT OF THE UNINTERRUPTIBLE POWER SUPPLY FOR THE CANON CT SYSTEM

BACKGROUND

West Haven VA Medical Center requires the replacement of the one (1) uninterruptible power supply for the Canon Aquilion One PRISM CT system.

OBJECTIVES

Deliver one (1) 150Kva TMEiC uninterruptible power supply (UPS) to the West Haven VA Medical Center. The contractor shall electronically provide all documentation required for installation, operation, and maintenance immediately upon award. Contractors shall provide breakdowns, make the existing UPS safe, removal and disposal of the existing UPS and delivery and installation of the new UPS including the reconnection, configuration, testing and start-up by go-live of system.

SCOPE

Deliver one (1) 150kVA TMEiC uninterruptible power supply (UPS) to the West Haven VA Medical Center. Provide documentation required for deinstallation, installation, operation and maintenance upon award. Perform breakdown, removal/disposal of existing UPS and delivery/installation of new UPS.

UPS REQUIREMENTS

Provide and install one 150kVA TMEiC UPS system meeting the following minimum requirements:

Quantity: One (1) TMEiC Uninterruptible Power Supply

480 VAC Input, 60Hz

480 VAC Output, 60Hz

3 phase 3-wire plus ground

Reflected Current THD:

3% typical at 100% load

5% typical at 50% load

Minimum DC Voltage of 400 VDC

Transient recovery time of 20ms

Overload capacity:

105% to 100% load for 1 hour

111% load for 2 minutes

120% to 150% load for 1 minute

Must have a force air cooling method

The system must not exceed 860 pounds

Shall not exceed the following dimensions:

Height: 81 max equipment height

Plus 19.7 max clearance requirement above equipment

Depth: 33 max equipment depth

Plus 40 max service clearance requirement in front of equipment

Width: 28

Provide UPS documentation including installation, operation, and service manuals, electrical schematics, site preparation requirements, environmental requirements, and dimensional drawings of the UPS

TASKS

Provide documentation to the COR electronically, within 3 business days of award, including installation manual, operation manual, service manual, electrical schematics, site preparation requirements, environmental requirements, and dimensional drawings of the UPS.

Deliver one (1) 150kVA TMEiC Uninterruptible Power Supply, which meet the UPS requirements defined in this statement of work, to the West Haven VA Medical Center.

Provide services that include breakdown, removal/disposal of existing UPS, delivery/installation of new UPS and testing/configuration of the new UPS

DELIVERABLES

Complete the replacement of the one (1) 150kVA TMEiC uninterruptible power supply for the Canon Aquilion One PRISM CT system.

PERIOD OF PERFORMANCE

Deliverables shall be performed within 180 days of contract award. All work shall occur during normal business hours 7 AM-5 PM, Monday-Friday, excluding Federal Holidays.

PLACE OF PERFORMANCE

VA Connecticut Healthcare System

Radiology Department, Building 1, Room G187F

950 Campbell Ave.

West Haven, CT 06516

NARA Records Management Requirements

The following standard items relate to records generated in executing this contract:

Citations to pertinent laws, codes and regulations such as 44 U.S.C. Chapter 21, 29, 31, and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.

Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.

Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.

Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.

The Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.

The Government Agency owns the rights to all data/records produced as part of this contract.

The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. The Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.

The Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].

No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage, or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.

The Contractor is required to obtain the Contracting Officer s approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under or relating to this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.

Files

File Type Posted
36C24126Q0674.docx DOCX document

Similar open opportunities

Opportunity Agency Set-aside Responses due
J065--FY27 SERVICES (BASE+4) - Canon CT Service Contract Department of Veterans Affairs Buffalo VA Medical Center · NAICS 811210 Veterans Integrated Service Network 2 No set-aside
6130--Uninterruptible Power Supply (UPS) for Pharmaceutical Refrigerators East Indianapolis VA Clinic Indianapolis IN 46229 · NAICS 335999 Veterans Integrated Service Network 10 No set-aside
J065--Philips Imaging Equipment preventative maintenance and repair services at the Northport VA Medical Center NAICS 811210 Veterans Integrated Service Network 2 No set-aside
6135--UPS Battery Replacement VA San Diego Healthcare System San Diego CA 92161 · NAICS 335910 Veterans Integrated Service Network 22 No set-aside
J061--Uninterruptible Power Supply St. Louis VA Medical Center NAICS 811210 Veterans Integrated Service Network 15 No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity