The Bureau of Land Management (BLM) Billings Field Office is partnering with Milton Ranch, LLC to upgrade the water storage system servicing the BLM grazing allotment by purchasing two 20,000 gallon ribbed, horizontal fiberglass storage tanks. The contractor is responsible for providing, transporting, and offloading the tanks at the Sundance Lodge wareyard managed by the Billings BLM Field Office. The tanks must meet specific manufacturing, design, and storage criteria, and will be used for non-potable water to service livestock.

List of products and services to be provided by the contractor:

  1. Two 20,000 gallon ribbed, horizontal fiberglass storage tanks
  2. Transportation and offloading of the tanks at the specified location
  3. Tanks must meet or exceed ASTM D3299, ASTM D4097, and AWWA D120 standards
  4. Tanks must withstand a 5-psig air-pressure test with 5:1 safety factor
  5. Tanks must support accessory equipment when installed according to tank manufacturers current Installation Manual and Operating Guidelines
  6. Tanks must have a structural wall thickness of a minimum 0.375” or thicker if load calculations require
  7. Tanks must be capable of storing approximately 20,000 gallons of water products with specific gravity up to 1.1
  8. Tanks must be vented to atmospheric pressure
  9. Tanks must be manufactured with 100% resin and glass-fiber reinforcement with no sand fillers
  10. Tanks must have a capacity of 20,000 plus gallons
  11. Tanks must have nominal outside diameter of approximately 12 feet
  12. Tanks must have approximate overall length of 26 feet
  13. Each tank must have one manway, flanged and 30"-nominal diameter, complete with gasket, bolting hardware and FRP cover
  14. Each tank must have one air vent fitting at the top of the radius of the tanks
  15. One tank must have a FRP top dome nozzle that shall be 4 inches, flat-faced and flanged
  16. The tank with the overflow must have two FRP bottom dome nozzles, and one tank needs only one FRP bottom dome nozzle
  17. FRP access openings must be 30” in diameter
  18. PVC Risers and FRP lids must be provided by the tank manufacture for field installation on access openings
  19. Saddles must be provided to the BLM for short term

Notice text

2023 STORAGE TANKS

Files

File Type Posted
Sol_140L3623Q0048_Amd_0001.pdf PDF
A04_Revised_Statement_of_Work_0001.pdf PDF
B09_Q_A_Doc_0001.docx DOCX document
A04_Statement_of_Work.pdf PDF
A04_Schedule_of_Items.pdf PDF
Sol_140L3623Q0048.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
Nmso wildlife water guzzler tank supply NAICS 326199 — Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors