2023 Poplar Island Spillway Rehabilitation, Talbot County, Maryland
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912DR23B0011
- Agency
-
ENDIST Baltimore
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- Place of performance
- Stevensville, Maryland 21666, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, Baltimore District is soliciting proposals to repair spillway structures and plug unused structures at Poplar Island in Talbot County, Maryland under Solicitation W912DR23B0011. The work includes slip lining pipes, structural repairs to gates and appurtenances, and filling capped pipes to prevent dike impacts. Proposals are due by June 29, 2023 and will be evaluated for technical compliance and price reasonableness, with award expected to be made within 120 days based on a low-price technically acceptable basis.
The set-aside designated total small business opportunity has an estimated construction value between $1-5 million to be performed only by boat on Poplar Island. Under NAICS 237310 and PSC C206, five bids were received by the June 29th deadline ranging from $1.46-3.53 million. Joint Forces Construction, LLC provided the lowest base bid of $1.46 million to be completed within the required 120-day period of performance out of Stevensville, Maryland.
Notice text
6 versions
Update #6 · Latest ·
ABSTRACT OF BIDS
**************************************************************
*****AMENDMENT 0004 6-20-23 ***** AMENDMENT 0003 6-15-2023 ***** AMENDMENT 0002 6-12-2023 ***** AMENDMENT 0001 6-8-2023 ***** Poplar Island is an ecosystem restoration project located in the upper-middle Chesapeake Bay in Talbot County, Maryland, approximately 39 miles south-southeast of the Port of Baltimore and two miles northwest of Tilghman Island. The primary purpose of this contract is to repair two existing spillway structures and plug and abandon several unused spillway structures. Poplar Island utilizes spillway structures to discharge water from inside the island, under the perimeter dikes, and out to the Chesapeake Bay. Each spillway consists of two ? 36-inch corrugated metal pipes of approximately 100 ft in length, which are controlled by individual sluice gates. The Spillway Rehabilitation work consists of slip ling four ? 36-inch corrugated metal pipes with HDPE pipes, and minor structural repairs to the sluice gates and appurtenant features. Abandonment work will include filling and capping between four and eight 36-inch corrugated metal pipes to prevent long term impacts to the island?s perimeter dikes. The estimated magnitude of construction is between $1,000,000.00 and $5,000,000.00. All work will be performed within Cells 1, 3, 4, and 5 of Poplar Island, a remote location accessible only by boat. The Contractor shall provide all necessary labor, equipment, materials, and transportation to perform the construction. The anticipated period of performance is approximately 120 calendar days.
Update #5 ·
*****AMENDMENT 0004 6-20-23 ***** AMENDMENT 0003 6-15-2023 ***** AMENDMENT 0002 6-12-2023 ***** AMENDMENT 0001 6-8-2023 ***** Poplar Island is an ecosystem restoration project located in the upper-middle Chesapeake Bay in Talbot County, Maryland, approximately 39 miles south-southeast of the Port of Baltimore and two miles northwest of Tilghman Island. The primary purpose of this contract is to repair two existing spillway structures and plug and abandon several unused spillway structures. Poplar Island utilizes spillway structures to discharge water from inside the island, under the perimeter dikes, and out to the Chesapeake Bay. Each spillway consists of two ? 36-inch corrugated metal pipes of approximately 100 ft in length, which are controlled by individual sluice gates. The Spillway Rehabilitation work consists of slip ling four ? 36-inch corrugated metal pipes with HDPE pipes, and minor structural repairs to the sluice gates and appurtenant features. Abandonment work will include filling and capping between four and eight 36-inch corrugated metal pipes to prevent long term impacts to the island?s perimeter dikes. The estimated magnitude of construction is between $1,000,000.00 and $5,000,000.00. All work will be performed within Cells 1, 3, 4, and 5 of Poplar Island, a remote location accessible only by boat. The Contractor shall provide all necessary labor, equipment, materials, and transportation to perform the construction. The anticipated period of performance is approximately 120 calendar days.
Update #4 ·
***** AMENDMENT 0003 6-15-2023 ***** AMENDMENT 0002 6-12-2023 ***** AMENDMENT 0001 6-8-2023 ***** Poplar Island is an ecosystem restoration project located in the upper-middle Chesapeake Bay in Talbot County, Maryland, approximately 39 miles south-southeast of the Port of Baltimore and two miles northwest of Tilghman Island. The primary purpose of this contract is to repair two existing spillway structures and plug and abandon several unused spillway structures. Poplar Island utilizes spillway structures to discharge water from inside the island, under the perimeter dikes, and out to the Chesapeake Bay. Each spillway consists of two ? 36-inch corrugated metal pipes of approximately 100 ft in length, which are controlled by individual sluice gates. The Spillway Rehabilitation work consists of slip ling four ? 36-inch corrugated metal pipes with HDPE pipes, and minor structural repairs to the sluice gates and appurtenant features. Abandonment work will include filling and capping between four and eight 36-inch corrugated metal pipes to prevent long term impacts to the island?s perimeter dikes. The estimated magnitude of construction is between $1,000,000.00 and $5,000,000.00. All work will be performed within Cells 1, 3, 4, and 5 of Poplar Island, a remote location accessible only by boat. The Contractor shall provide all necessary labor, equipment, materials, and transportation to perform the construction. The anticipated period of performance is approximately 120 calendar days.
Update #3 ·
***** AMENDMENT 0002 6-12-2023 ***** AMENDMENT 0001 6-8-2023 ***** Poplar Island is an ecosystem restoration project located in the upper-middle Chesapeake Bay in Talbot County, Maryland, approximately 39 miles south-southeast of the Port of Baltimore and two miles northwest of Tilghman Island. The primary purpose of this contract is to repair two existing spillway structures and plug and abandon several unused spillway structures. Poplar Island utilizes spillway structures to discharge water from inside the island, under the perimeter dikes, and out to the Chesapeake Bay. Each spillway consists of two ? 36-inch corrugated metal pipes of approximately 100 ft in length, which are controlled by individual sluice gates. The Spillway Rehabilitation work consists of slip ling four ? 36-inch corrugated metal pipes with HDPE pipes, and minor structural repairs to the sluice gates and appurtenant features. Abandonment work will include filling and capping between four and eight 36-inch corrugated metal pipes to prevent long term impacts to the island?s perimeter dikes. The estimated magnitude of construction is between $1,000,000.00 and $5,000,000.00. All work will be performed within Cells 1, 3, 4, and 5 of Poplar Island, a remote location accessible only by boat. The Contractor shall provide all necessary labor, equipment, materials, and transportation to perform the construction. The anticipated period of performance is approximately 120 calendar days.
Update #2 ·
***** AMENDMENT 0001 6-8-2023 ***** Poplar Island is an ecosystem restoration project located in the upper-middle Chesapeake Bay in Talbot County, Maryland, approximately 39 miles south-southeast of the Port of Baltimore and two miles northwest of Tilghman Island.The primary purpose of this contract is to repair two existing spillway structures and plug and abandon several unused spillway structures. Poplar Island utilizes spillway structures to discharge water from inside the island, under the perimeter dikes, and out to the Chesapeake Bay. Each spillway consists of two ? 36-inch corrugated metal pipes of approximately 100 ft in length, which are controlled by individual sluice gates. The Spillway Rehabilitation work consists of slip ling four ? 36-inch corrugated metal pipes with HDPE pipes, and minor structural repairs to the sluice gates and appurtenant features. Abandonment work will include filling and capping between four and eight 36-inch corrugated metal pipes to prevent long term impacts to the island?s perimeter dikes. The estimated magnitude of construction is between $1,000,000.00 and $5,000,000.00. All work will be performed within Cells 1, 3, 4, and 5 of Poplar Island, a remote location accessible only by boat. The Contractor shall provide all necessary labor, equipment, materials, and transportation to perform the construction. The anticipated period of performance is approximately 120 calendar days.
Update #1 ·
Poplar Island is an ecosystem restoration project located in the upper-middle Chesapeake Bay in Talbot County, Maryland, approximately 39 miles south-southeast of the Port of Baltimore and two miles northwest of Tilghman Island.The primary purpose of this contract is to repair two existing spillway structures and plug and abandon several unused spillway structures. Poplar Island utilizes spillway structures to discharge water from inside the island, under the perimeter dikes, and out to the Chesapeake Bay. Each spillway consists of two ? 36-inch corrugated metal pipes of approximately 100 ft in length, which are controlled by individual sluice gates. The Spillway Rehabilitation work consists of slip ling four ? 36-inch corrugated metal pipes with HDPE pipes, and minor structural repairs to the sluice gates and appurtenant features. Abandonment work will include filling and capping between four and eight 36-inch corrugated metal pipes to prevent long term impacts to the island?s perimeter dikes. The estimated magnitude of construction is between $1,000,000.00 and $5,000,000.00. All work will be performed within Cells 1, 3, 4, and 5 of Poplar Island, a remote location accessible only by boat. The Contractor shall provide all necessary labor, equipment, materials, and transportation to perform the construction. The anticipated period of performance is approximately 120 calendar days.
Files
| File | Type | Posted |
|---|---|---|
| C.04.01 Abstract of Bids W912DR23B0011 Poplar Island Spillway.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| 2023 Poplar Island Spillway Rehabilitation | Award Notice | |
| This notice | Solicitation | |
| 2023 Poplar Island Spillway Rehabilitation, Talbot County, Maryland | Pre-Solicitation | |
| 2023 Poplar Island Spillway Rehabilitation, Talbot County, Maryland | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Mid-Bay James Island Restoration Phase 2 | ENDIST Baltimore | No set-aside | |
| Borough of Millvale, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation | ENDIST Pittsburgh | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity