2022 BORDEAUX CREEK AOP CULVERT REPLACEMENT / Nebraska National Forest

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
1284LM22Q0095
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Chadron, Nebraska 69337, United States

Notice details come from SAM.gov. Updated .

Notice text

2 versions

Update #2 · Latest ·

Refer to Amendments 1-2 for Q&A, and Amendment 3 for changes. 

Refer to the Solicitation and Attachments for details. 

The USDA Forest Service, Nebraska National Forest (Region 2) intends to award a single, firm-fixed-price stand alone contract for the installation and replacement of an existing culvert on National Forest Service Road (NFSR) 723 Little Wolf East with a new aquatic organism passage (AOP) style concrete box culvert.  

The magnitude of this Construction Project (IAW FAR 36.204) is: Between $100,000 and $250,000.

It is estimated that once the contract is awarded, the notice to proceed for materials will be issued.  Work is expected to begin on or around July 5, 2023.  The contract time shall be 100 calendar days from the effective notice to proceed; all work must be completed no later than October 15, 2023; the contract time shall not exceed this date.

Submit your quote to the Contracting Officer (CO), Darrin Jackson by email at darrin.jackson@usda.gov.  Refer to Section L and M for additional information.  If you have any questions, contact the Contracting Officer at the email listed above.

Contracting Mailing Address:
Idaho Panhandle National Forest 
Supervisors Office
Attn: Darrin Jackson - 1284LM22Q0095
3232 West Nursery Road
Coeur d’Alene, ID 83815
 

Update #1 ·

See the Soliciation and Attachments for details. 

The USDA Forest Service, Nebraska National Forest (Region 2) intends to award a single, firm-fixed-price stand alone contract for the installation and replacement of an existing culvert on National Forest Service Road (NFSR) 723 Little Wolf East with a new aquatic organism passage (AOP) style concrete box culvert.  

The magnitude of this Construction Project (IAW FAR 36.204) is: Between $100,000 and $250,000.

It is estimated that once the contract is awarded, the notice to proceed for materials will be issued.  Work is expected to begin on or around July 5, 2023.  The contract time shall be 100 calendar days from the effective notice to proceed; all work must be completed no later than October 15, 2023; the contract time shall not exceed this date.

Submit your quote to the Contracting Officer (CO), Darrin Jackson by email at darrin.jackson@usda.gov.  Refer to Section L and M for additional information.  If you have any questions, contact the Contracting Officer at the email listed above.

Contracting Mailing Address:
Idaho Panhandle National Forest 
Supervisors Office
Attn: Darrin Jackson - 1284LM22Q0095
3232 West Nursery Road
Coeur d’Alene, ID 83815
 

Files

Notice history

Notice Type Posted
2022 BORDEAUX CREEK AOP CULVERT REPLACEMENT / Nebraska National Forest Award Award Notice
This notice Latest solicitation Solicitation
2022 BORDEAUX CREEK AOP CULVERT REPLACEMENT / Nebraska National Forest Original Pre-Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors