AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
P00001 08/29/2022
6. ISSUED BY CODE 84LM 7. ADMINISTERED BY (If other than Item 6) CODE 84LM
USDA-FS CSA INTERMOUNTAIN 2
R1, LOLO NATIONAL FOREST
24 FORT MISSOULA
MISSOULA, MT 59804
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
1284LM22Q0095
9B. DATED (SEE ITEM 11)
08/20/2022
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods (a) By completing Items 8 and 15, and returning 0 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
2022 BORDEAUX CREEK AOP CULVERT REPLACEMENT
Nebraska National Forest – Pine Ridge R.D.
The purpose of this amendment is to Questions and Answers to provide the offeror’s information only; see page 2 for details. The response date and time remains unchanged for Sep 19, 2022 04:30 pm PDT.
If you have any questions, please contact the Contracting Officer, Darrin Jackson at darrin.jackson@sda.gov.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER
DARRIN JACKSON
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
08/29/2022
(Signature of person authorized to sign) (Signature of CO)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
mailto:darrin.jackson@sda.gov
CONTINUATION OF SF30, BLOCK 14 Solicitation No.: 1284LM22Q0095 / Amendment No.: P00001
Project Name: 2022 Bordeaux Creek AOP Culvert Replacement Forest: Nebraska N.F. / Page 2 of 2
Questions and Answers:
Q: I can’t find the gradation for the foundation fill.
Response: For the gradation on the foundation fill, the spec (FP 14 704.01) has the info for this material. I got this info from the designer. It looks to me like what we want is an aggregate material that has a max. particle size of 2” and has only 6% max. fine material that passes the 200 sieve. The contractor can find something close to this and submit it for our approval. If I get more info from the designer, I’ll pass it on.
Q: I went and looked at the jobsite and what is the plan for the 10 ton bridge we have to cross to bring in all equipment and materials.
Response: The 10-ton bridge. It is on Dawes County Road – Bordeaux Creek. There are 3 other roads that can access the Little Wolf Road #723 off of Bordeaux Road. One comes in from the south and 2 come in from the east. The Offeror should be able to look on Goggle Earth and see these roads. COR would have to talk with the Dawes County Road Superintendent about any permitting.
Q: What is the plan for the staging area, can we use that turnaround and what are we doing with the grubbings and the pipe and other removals likes trees and grass?
Response: See Drawing Sheet C-02, Excavation and Specification 204.14. These state the unsuitable excavation may be disposed of at a designated site within ¼ mile (west of work site). At this time, if any large trees are cut down to facilitate work, they are to be disposed of by the contractor off Forest Service lands.
Q: Is there a spot that you have we can take grubbings or dirt or do we have to dispose ourselves.
Response: Disposed of by the contractor off Forest Service lands.
Q: Do we need to have a Quality Control Agency do this or can we have our own people do this?
Response: No, a quality control agency is NOT required. You will assign qualified personnel (employee or subcontractor) as the Quality Control Manager (QCM). Ensure to provide any subcontractor(s) information and their roles for this project. Refer to Section H (page 12) and Section L (page 32) for additional information.
Q: Will you need as-built drawings for this project done?
Response: This project does not require as-builts drawings.
But if there are any changes to the design shown on the drawings, that the Contractor shall show and provide the “approved” changes on their copy of the plans (generally in a red color, with dimensions), and provide the Contracting Officer and COR with a copy of the changes at the end of the contract, prior to submitting for final payment.
The Government will require any shop drawings for materials used as shown on the List of required Submittals so we can approve (according to the specifications and drawings) what the Contractor is proposing to do or the materials they plan on using.
Q: What is the Due date on the Bid?
Response: Date Quotes are due is September 19, 2022 by 1630 PDT. You can find this on page 1 of the SF-18 (Block 10).
Q: Is there someone that can meet me at jobsite to look at it and go over it.
Response: There is no site visit scheduled at this time, but you may contact Nathaniel Marcoe (COR) to see if there is a date/time he can schedule to meet you. His contact information is, P: 308-432-0303, Email:
nathaniel.marcoe@usda.gov.
mailto:nathaniel.marcoe@usda.gov
| 2022-08-29T08:44:29-0700 | |
| DARRIN JACKSON |