127EAW22R0070 - Milsap Bar Bridge Retaining Wall
Closed Solicitation Posted
- Solicitation number
- 127EAW22R0070
- Agency
-
Forest Service
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Berry Creek, California 95916, United States
Notice details come from SAM.gov. Updated .
Notice text
2 versions
Update #2 · Latest ·
127EAW22R0070 - Milsap Bar Bridge Retaining Wall - Amendment A00001
The purpose of this solicitation amendment is to post RFI round 1 responses and revised schedule.
Attached is "RFI Official Responses - 1" and "3. Schedule - Revised 31 Aug 2022" which are hereby incorporated into any subsequent contract award. Failure to use the revised schedule will result in your proposal being non-responsive.
///////////////////////////////////////////////////////////////////////////////////////////////////////////////
127EAW22R0070 - Milsap Bar Bridge Retaining Wall
Plumas National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $250,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, August 31st, 2022.
An organized pre-proposal site visit will be held. See Provision 452.237-71 on page 37 for complete details. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
*** This project will not begin until MAY 2023***
PLEASE RSVP TO THE SITE VISIT BY EMAILING: GREGORY.CUNNINGHAM@USDA.GOV
Update #1 ·
127EAW22R0070 - Milsap Bar Bridge Retaining Wall
Plumas National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $250,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, August 31st, 2022.
An organized pre-proposal site visit will be held. See Provision 452.237-71 on page 37 for complete details. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
*** This project will not begin until MAY 2023***
PLEASE RSVP TO THE SITE VISIT BY EMAILING: GREGORY.CUNNINGHAM@USDA.GOV
Files
| File | Type | Posted |
|---|---|---|
| 3. Schedule - Revised 31 Aug 2022.docx | DOCX document | |
| RFI Official Responses - 1.pdf | ||
| A00001 - RFI Responses and Revised Schedule.pdf | ||
| 3. Schedule.docx | DOCX document | |
| 6. Davis-Bacon Act WD # CA20220007.pdf | ||
| 127EAW22R0070 - Milsap Bar Bridge Retaining Wall.pdf | ||
| 7. RFI Form.docx | DOCX document | |
| 1. Statement of Work.pdf | ||
| 4. Drawings.pdf | ||
| 2. Fire Plan.pdf | ||
| 5. Specifications.pdf |