3. Schedule - Revised 31 Aug 2022.docx

DOCX document 14 KB Posted

Attached to
127EAW22R0070 - Milsap Bar Bridge Retaining Wall
Solicitation number
127EAW22R0070
Issued by

View the file

Other files

File Type Posted
A00001 - RFI Responses and Revised Schedule.pdf PDF
RFI Official Responses - 1.pdf PDF
6. Davis-Bacon Act WD # CA20220007.pdf PDF
2. Fire Plan.pdf PDF
3. Schedule.docx DOCX document
1. Statement of Work.pdf PDF
5. Specifications.pdf PDF
4. Drawings.pdf PDF
7. RFI Form.docx DOCX document
127EAW22R0070 - Milsap Bar Bridge Retaining Wall.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
15101
Mobilization
1
L.S.
$__________
$__________
20401
Excavation and Embankment
64
C.Y.
$__________
$__________
25501
MSE Wall, Rock Face
120
S.F.
$__________
$__________
40301
Road Resurface, AC, Type II
7
TON
$__________
$__________
BASE TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name:
POC & Title:
Email:
Phone Number:
UEI Number:
Tax ID:

File details come from the government source that posted it. Updated .