127EAW21R0024 - Jerseydale Campground Phase 3

Closed Solicitation Posted

This opportunity was awarded. See the award notice from .

Solicitation number
127EAW21R0024
Agency
Responses due
Set-aside
Total Small Business

Opportunity facts

Place of performance
Mariposa CA 95338, United States

Notice details come from SAM.gov. Updated .

Notice text

3 versions

Update #3 · Latest ·

127EAW21R0024 - Jerseydale Campground Phase 3 - Amendment A00002


The purpose of this solicitation amendment is to post RFI round 2 responses.


Attached is "RFI Official Responses - 2" which are hereby incorporated into any subsequent contract award.

//////////////////////////////////////////////////////////////////////////////////////////////

127EAW21R0024 - Jerseydale Campground Phase 3 - Amendment A00001


The purpose of this solicitation amendment is to post RFI round 1 responses.


Attached is "RFI Official Responses - 1" which are hereby incorporated into any subsequent contract award.

//////////////////////////////////////////////////////////////////////////////////////////////

127EAW21R0024 - Jerseydale Campground Phase 3
Sierra National Forest
Bass Lake Ranger District


FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $200,000
Set Aside: Total Small Business Set Aside


IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal

All Requests for Information (RFI's) shall be submitted to the Contract Specialist, Gregory Cunningham, not later than 1300 hours on May 25th, 2021.


An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

Update #2 ·

127EAW21R0024 - Jerseydale Campground Phase 3 - Amendment A00001


The purpose of this solicitation amendment is to post RFI round 1 responses.


Attached is "RFI Official Responses - 1" which are hereby incorporated into any subsequent contract award.

//////////////////////////////////////////////////////////////////////////////////////////////

127EAW21R0024 - Jerseydale Campground Phase 3
Sierra National Forest
Bass Lake Ranger District


FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $200,000
Set Aside: Total Small Business Set Aside


IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal

All Requests for Information (RFI's) shall be submitted to the Contract Specialist, Gregory Cunningham, not later than 1300 hours on May 25th, 2021.


An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

Update #1 ·

127EAW21R0024 - Jerseydale Campground Phase 3
Sierra National Forest
Bass Lake Ranger District


FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $100,000 and $200,000
Set Aside: Total Small Business Set Aside


IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal

All Requests for Information (RFI's) shall be submitted to the Contract Specialist, Gregory Cunningham, not later than 1300 hours on May 25th, 2021.


An organized pre-proposal site visit will not be held. Each offeror is expected to visit the site. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

Files

Show all 12

Notice history

Notice Type Posted
127EAW21C0011 - Jerseydale Campground Phase 3 Award Award Notice
This notice Latest solicitation Solicitation

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors