About this opportunity

This solicitation seeks mechanical site preparation and fuels reduction services on the Stanislaus National Forest in California. The USDA Forest Service is requesting these services to prepare 354 acres across 14 units for future planting efforts. Contractors must utilize mechanical equipment like masticators, grapple piles, and feller bunchers, as well as hand treatments to reduce hazardous fuels. Work must be completed between January 16 and April 21, 2023, considering environmental and slope restrictions. Proposals are due by January 18, 2023, and the selected contractor will be responsible for providing all necessary equipment, labor, supervision and insurance to complete the project objectives.

There is no set-aside designated for this opportunity. The primary NAICS code is 115310 and PSC code D301. No incumbent or current contractor is named. The solicitation does not provide an estimated value but covers preparation of 354 acres across the Stanislaus National Forest in the Rim Fire area, accessible from Forest Roads 3N01 and 1S03. Work shall be performed under the direction of the Stanislaus National Forest Supervisor's Office in Sonora, California.

Notice text

2 versions

Update #2 · Latest ·

SAM Posting Update 1/10/23 - Corrections include the following: 

Quotes due extension - 1/18/23 at 12:00pm PST, Q&A uploaded (includes Mech Site Prep Data Table), and Section J. document added - titled Mechanized Equipment Operations RCAs. 

Scope of Work
Description of Work: The intent of this contract is to secure services for site preparation, fuels reduction prior to planting, and increasing safety by mechanical equipment, hand treatment, or a combination of both. Each unit may require multiple types of equipment and/or treatments to achieve desired reduction of fuels, including, but not limited to, grapple piling, mastication,
feller buncher, hand felling, and hand piling. Slope, vegetation amounts, vegetation types, and vegetation heights will be deciding factors. Unless direct treatments are listed by Contracting Officer, it will be the Contractor’s responsibility to determine which methods/equipment shall be used to meet treatment requirements for each unit.
Contractor Responsibility: The Contractor shall provide everything--including, but not limited to, all equipment, supplies, transportation, labor, and supervision--necessary to complete the project, except for that which the contract clearly states is to be furnished by the Government.


Project Location & Description
Location: The project is located on the Stanislaus National Forest, Groveland Ranger District.
Description: Units are located in the Rim Fire Area.
All mastication, grapple piling, and feller buncher operations shall not exceed 45 percent slope gradient.
Hand felling and pile construction may occur on all slope percentages. General unit areas are shown on the enclosed maps and marked on the ground. Unit boundaries are flagged in blue and yellow flagging tied together or solid yellow flagging.
Accessibility: Work site access instruction, as given here, is for information only. It shall be the responsibility of the Contractor to determine the most suitable route to the project area. Predicted access route for project access is as follows: NORTH Units - From the US Forest Service, Groveland Ranger District Office, head east on Highway 120 to the Cherry Lake Road (1N07) junction. Then head north on Cherry Lake Road to Forest Road 3N01 (Recreation Road 31). Turn west onto Road 3N01 and continue to the west towards the project area. All units can be accessed off Forest Roads off 3N01. SOUTH Units - From the US Forest Service,
Groveland Ranger District Office, head east on Highway 120 to the Sawmill Road (1S03) junction. OR continue east on Highway 120. Turn north onto Evergreen Road and then west on 1S03 towards the project area. All units can be accessed off Forest Roads off 3N01 or 1S03.
Unit access routes are subject to change and will be determined based on road conditions existing immediately prior to and during the implementation of the contract. The Government will not provide special maintenance nor snow plowing to open roads or keep roads open. Any prospective Contractor desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing from the Contracting Officer soon enough to allow a reply to reach all prospective Contractors before the solicitation closing date. Oral explanations or instructions given before the award of a contract will not be binding.
Exclusions (Non-work Areas): Non-work areas will be identified by any of the following: 1) mapping, 2) flagged with specified color, or 3) verbal instructions. These are areas of natural regeneration, streamside protection zones, areas with an excessive amount of rock or rock outcrops, and areas that may have been treated previously. No tractor intrusion, disturbance, or damage shall be allowed in these areas without approval from Contracting Officer.


Maps
Any maps included in Section J are general in nature and are not to be considered as
definitively identifying locations.

Restrictions on Work
Work may be performed at any time during the period of the contract, except as outlined here.
Nothing in this part shall be construed to take away any of the Government's rights under the Suspension of Work Clause (52.242-14).

Restrictions are as follows:
1. In accordance with the fire plan, if included in Section J.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
3. Hours of Operation: Contractor shall limit treatment operations within ¼ mile of residences and campgrounds to weekdays and non-holidays only, between the hours of 7:00 a.m. and 6:00 p.m.
4. Control Areas (CAs) – No activity shall be allowed in these areas. The only exception to this includes CA-9 (Clarkia spp.) sites during the Clarkia spp. dry season (approximately July 16 thru November 30); limitations within these sites are listed later in this document.
5. Limited Operating Period (LOP) – No activity will be allowed during the following LOPs, unless surveys confirm that nesting is not occurring.
a) Northern Goshawk (NOGO): February 15 thru September 15.
b) Great Grey Owl (GGO): March 1 thru August 15, within .25 miles of the activity center.
c) Spotted Owl (SOP): March 1 thru August 31, within .25 miles of the activity center.
d) California Red Legged Frog (CRLF): Prohibited within 1 mile of area identified as suitable CRLF breeding habitat during the wet season (first rain fall event depositing more than .25 inches of rain on or after October 15 thru April 15).
e) Within 300 feet of occupied Western Pond Turtle (WPT) habitat, May 15 thru July 15.

Update #1 ·

Scope of Work
Description of Work: The intent of this contract is to secure services for site preparation, fuels reduction prior to planting, and increasing safety by mechanical equipment, hand treatment, or a combination of both. Each unit may require multiple types of equipment and/or treatments to achieve desired reduction of fuels, including, but not limited to, grapple piling, mastication,
feller buncher, hand felling, and hand piling. Slope, vegetation amounts, vegetation types, and vegetation heights will be deciding factors. Unless direct treatments are listed by Contracting Officer, it will be the Contractor’s responsibility to determine which methods/equipment shall be used to meet treatment requirements for each unit.
Contractor Responsibility: The Contractor shall provide everything--including, but not limited to, all equipment, supplies, transportation, labor, and supervision--necessary to complete the project, except for that which the contract clearly states is to be furnished by the Government.


Project Location & Description
Location: The project is located on the Stanislaus National Forest, Groveland Ranger District.
Description: Units are located in the Rim Fire Area.
All mastication, grapple piling, and feller buncher operations shall not exceed 45 percent slope gradient.
Hand felling and pile construction may occur on all slope percentages. General unit areas are shown on the enclosed maps and marked on the ground. Unit boundaries are flagged in blue and yellow flagging tied together or solid yellow flagging.
Accessibility: Work site access instruction, as given here, is for information only. It shall be the responsibility of the Contractor to determine the most suitable route to the project area. Predicted access route for project access is as follows: NORTH Units - From the US Forest Service, Groveland Ranger District Office, head east on Highway 120 to the Cherry Lake Road (1N07) junction. Then head north on Cherry Lake Road to Forest Road 3N01 (Recreation Road 31). Turn west onto Road 3N01 and continue to the west towards the project area. All units can be accessed off Forest Roads off 3N01. SOUTH Units - From the US Forest Service,
Groveland Ranger District Office, head east on Highway 120 to the Sawmill Road (1S03) junction. OR continue east on Highway 120. Turn north onto Evergreen Road and then west on 1S03 towards the project area. All units can be accessed off Forest Roads off 3N01 or 1S03.
Unit access routes are subject to change and will be determined based on road conditions existing immediately prior to and during the implementation of the contract. The Government will not provide special maintenance nor snow plowing to open roads or keep roads open. Any prospective Contractor desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing from the Contracting Officer soon enough to allow a reply to reach all prospective Contractors before the solicitation closing date. Oral explanations or instructions given before the award of a contract will not be binding.
Exclusions (Non-work Areas): Non-work areas will be identified by any of the following: 1) mapping, 2) flagged with specified color, or 3) verbal instructions. These are areas of natural regeneration, streamside protection zones, areas with an excessive amount of rock or rock outcrops, and areas that may have been treated previously. No tractor intrusion, disturbance, or damage shall be allowed in these areas without approval from Contracting Officer.


Maps
Any maps included in Section J are general in nature and are not to be considered as
definitively identifying locations.

Restrictions on Work
Work may be performed at any time during the period of the contract, except as outlined here.
Nothing in this part shall be construed to take away any of the Government's rights under the Suspension of Work Clause (52.242-14).

Restrictions are as follows:
1. In accordance with the fire plan, if included in Section J.
2. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
3. Hours of Operation: Contractor shall limit treatment operations within ¼ mile of residences and campgrounds to weekdays and non-holidays only, between the hours of 7:00 a.m. and 6:00 p.m.
4. Control Areas (CAs) – No activity shall be allowed in these areas. The only exception to this includes CA-9 (Clarkia spp.) sites during the Clarkia spp. dry season (approximately July 16 thru November 30); limitations within these sites are listed later in this document.
5. Limited Operating Period (LOP) – No activity will be allowed during the following LOPs, unless surveys confirm that nesting is not occurring.
a) Northern Goshawk (NOGO): February 15 thru September 15.
b) Great Grey Owl (GGO): March 1 thru August 15, within .25 miles of the activity center.
c) Spotted Owl (SOP): March 1 thru August 31, within .25 miles of the activity center.
d) California Red Legged Frog (CRLF): Prohibited within 1 mile of area identified as suitable CRLF breeding habitat during the wet season (first rain fall event depositing more than .25 inches of rain on or after October 15 thru April 15).
e) Within 300 feet of occupied Western Pond Turtle (WPT) habitat, May 15 thru July 15.

Files

File Type Posted
QandA.docx DOCX document
HUD Mech Site Prep RCAs.docx DOCX document
127EAS23Q0008 Solicitation Mechanical Fuels Reduction.docx DOCX document
Mech Site Prep Data Table.xls XLS spreadsheet
127EAS23Q0008 Solicitation Mechanical Fuels Reduction.pdf PDF
Fire Plan.pdf PDF
FY23 HUD MechSitePrep All Units (1).pdf PDF
Forestry Wage Determination.pdf PDF

Similar open opportunities

Opportunity Agency Set-aside Responses due
Forest Service Hand Thinning, MATOC North Rockies/Great Basin Missoula, Montana 59804, United States · NAICS 115310 Forest Service No set-aside
Intermountain Stewardship BPA Ogden, Utah 84401, United States · NAICS 115310 Forest Service No set-aside
Pacific Southwest (PSW) STEWARDSHIP BPA (R5 Multiple Forests) Quincy, California 95971, United States · NAICS 115310 Forest Service No set-aside
End of the World Long Term Stewardship Grangeville, Idaho, United States · NAICS 113310 Forest Service No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors