This federal contract opportunity announcement solicits offers for a roof replacement project at a child care facility in Miami, Florida. The Federal Aviation Administration Boston Enroute Construction Office seeks to replace the roof through a small business set-aside contract with a NAICS code of 238160 and size standard of $16.5 million. The solicitation package includes specifications, drawings and wage rates. The estimated price range for the roof replacement requirement is $100,000 to $400,000. Payment and performance bonds are required. A mandatory site visit is scheduled for July 21, 2021, and offerors must register for the visit by emailing the contact by July 20. The solicitation number is 697DCK-21-R-00350. Offerors must be registered in the System for Award Management to be eligible for award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment0003.pdf | ||
| Amendment0002.pdf | ||
| amendment0001ccf.pdf | ||
| 19000693 - ZMA CCF Roof SOW - Specs FINAL.pdf | ||
| wagerate618.pdf | ||
| RFO697DCK-21-R-00350.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
FLMIAMI
CHILD
MIAMI CENTER
ZMA-19000693-A001
z m a a .d g n
28'30'13'
31'28'13'
LW
MC 10/05/2020
PROJECT ENGINEER MGR: ENROUTE/FSS ENGR CTR
19000693
C O
N S
T R
U
IO
ENGINEERING SERVICES
ENROUTE/FSS
THIS DRAWING PRODUCED ON ASO REGION MICROSTATION SYSTEM
ATO - TECHNICAL OPERATIONS EASTERN SERVICE AREA
ROOF PLAN
REPLACE CHILD CARE FACILITY ROOF
-1
-a
/0
/2
:3
:1
P
M lo tt e d b y
V
-C
A E
G -E
D
B
F
H
8 7 6 5 4 3 2 1
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV
DATE
APPROVED
DESCRIPTION JCN
REDLINE
APVD
IS
A B C D E
SHEET NOTES
RTU
KHVU
EF-1
L
R.D. R.D. R.D.
ROOF HATCH
RIDGE LINE
EF-2
R.D.
EF-3
R.D. R.D.
A003
GENERAL NOTES
SCUPPER (TYP.) SCUPPER (TYP.)SCUPPER (TYP.)
SCUPPER (TYP.)SCUPPER (TYP.) SCUPPER (TYP.)
WORK AREA
SCALE: 1/8" = 1'-0"
8' 16'08'
PV
ACCORDANCE WITH PROJECT SUBMITTAL PROCEDURES.
USE. SDS AND PRODUCT DATA MUST BE REVIEWED AND APPROVED BY COR PRIOR TO USE IN
CONTRACTOR MUST COORDINATE USAGE OF ANY CHEMICALS OR SEALANTS WITH COR PRIOR TO6.
OF UNEXPECTED WEATHER. ROOF AREAS IN THE EVENT
DAY. ENSURE SUFFICIENT TEMPORARY COVERAGE MATERIALS IS AVAILABLE TO COVER OPEN
TRANSITION FROM NEW ROOF TO EXISTING ROOF MUST BE SEALED AT THE END OF EACH WORK
CONTRACTOR MUST NOT DEMOLISH MORE ROOF THAN CAN BE REPLACED IN A SINGLE SHIFT.5.
COVER BOARD LAY PATTERNS, RIDGELINE, AND INDUCTION WELD PATTERNS.
LENGTH AND FREQUENCY FOR CORNERS, EDGES, CRICKETS AND FIELD, INSULATION AND
PROCEDURES. INCLUDE ENGINEERS REPORT DETAILING MECHANICAL FASTENER PATTERN,
ROOF SYSTEM FOR REVIEW AND APPROVAL BY COR IN ACCORDANCE WITH PROJECT SUBMITTAL
PRIOR TO COMMENCING WORK THE CONTRACTOR MUST PROVIDE SHOP DRAWINGS OF NEW 4.
DUST DURING CONSTRUCTION. DEBRIS MUST BE REMOVED BY CONTRACTOR DAILY.
BY COR. AREAS AROUND DUMPSTERS MUST BE KEPT CLEAN AND FREE OF EXCESS DEBRIS AND
DEBRIS MUST BE PROVIDED BY THE CONTRACTOR. DUMPSTERS LOCATIONS TO BE DETERMINED
CONTRACTOR MUST NOT USE FAA DUMPSTERS. DUMPSTERS FOR DISPOSAL OF CONSTRUCTION3.
DUMPSTER PICKUP AT ALL TIMES. SECURE ACCESS GATES AT THE END OF WORK DAY.
DAYCARE DELIVERIES AND TRASHCONTRACTOR MUST MAINTAIN ACCESSIBILITY FOR EACH
CABLES (UNDERGROUND UTILITIES) MAY RUN THROUGH STAGING AREA AND ELSEWHERE.
CONTRACTOR MUST DO NO DIGGING WITHOUT PRIOR PERMISSION FROM THE COR. BURIED
CONSTRUCTION STAGING AREA. MATERIALS MUST BE NEATLY STORED AND PROTECTED.
STORAGE OF CONSTRUCTION MATERIALS AND TRAILERS ON SITE MUST BE LIMITED TO THE2.
ATTACHMENT AND A REPAIR COST ESTIMATE ON A SQUARE FOOT BASIS.
CONTRACTOR MUST PROVIDE SHOP DRAWINGS FOR THE CORRUGATED STEEL DECK AND
REINFORCEMENT IF REQUIRED, TO COMPLY WITH THE LATEST FLORIDA BUILDING CODE (FBC).
THE PROFESSIONAL ENGINEER MUST MAKE RECOMMENDATIONS FOR REPAIR OR ADDITIONAL
TEK SCREWS FOR DECK ATTACHMENT. AFTER THE INSPECTION DECK, PUDDLE WELDS AND
REGISTERED STRUCTURAL ENGINEER TO INSPECT THE EXISTING CONDITION OF THE METAL
PRIOR TO REMOVING EXISTING ROOFING SYSTEM THE CONTRACTOR MUST HIRE A FLORIDA1.
NORMAL HOURS OF OPERATION.
OPERATIONS. WORK OVER ENTRANCE MAY BE REQUIRED OUTSIDE OF FACILITY
COORDINATE WORK OVER ENTRANCE WITH COR TO MINIMIZE IMPACT TO FACILITY
PROVIDE EXTENDABLE LADDER SAFETY POST FOR ROOF ACCESS LADDER.
NEW FINISHED SURFACE. SEE DETAIL 7/A003. (TYPICAL)
SECURE CONDENSATE DRAIN LINE SUPPORT BLOCKS TO PADS, SECURE PADS TO
REPLACE CONDENSATE DRAIN LINES FOR RTUS. (TYPICAL)
REMOVE, PROTECT, STORE AND REATTACH PARAPET CAP.
FINISHED SURFACE.
EXTEND ELECTRICAL PENETRATIONS TO MATCH PREVIOUS PROTRUSION ABOVE NEW
ABOVE NEW FINISHED SURFACE. (TYPICAL)
EXTEND DOWN-CONDUCTOR PENETRATIONS TO MATCH PREVIOUS PROTRUSION
(TYPICAL)
EXTEND VENTS TO MATCH PREVIOUS PROTRUSION ABOVE NEW FINISHED SURFACE.
PROVIDE NEW METAL COUNTER FLASHING ON CURBS. (TYPICAL)
PROVIDE TPO ROOF SYSTEM OVER INTERIOR SPACE AND SOUTH ENTRANCE AWNING.
ROOF PLAN - NEW WORK
zma-19000693-a001
2020-12-09T06:39:34-0500
ROBERT L BELTON
2020-12-08T11:06:20-0500
MICHAEL T L COX
ZMA-19000693-A002
a
FOR COR APPROVAL.
SHOP DRAWINGS, AND LAYOUT
ROOF. SUBMIT PRODUCT DATA,
RAILING AROUND PERIMETER OF
PROVIDE FALL PROTECTION
CATCH WIND.
NOT SO LARGE AS TO
DRAINAGE SLIT IS
APPROVAL. ENSURE
ON LAYOUT FOR COR
SUPPORTS. SUBMIT
DRAIN LINE
UNDER CONDENSATE
TERMINALS, AND
WIRES, UNDER AIR
UNDER GROUNDING
PROVIDE PADS
PATHWAY PADS AND
PROVIDE ROOF
FALL PROTECTION, ROOF PAD AND
LIGHTNING PROTECTION PLAN
LAYOUT FOR COR APPROVAL.
DATA, SHOP DRAWINGS, AND
PATIO ROOF. SUBMIT PRODUCT
RAILING AROUND PERIMETER OF
PROVIDE FALL PROTECTION
:2 lo tt e
A B C D E
NOTES
EF-1
EF-3
EF-2
TYPES OF CONNECTIONS.
TERMINAL LOCATIONS. THE SHOP DRAWING SHALL ALSO HAVE DETAILS SHOWING THE DIFFERENT
SHALL INCLUDE "D" SIZE PLAN DRAWING OF ROOF TOP SHOWING PATHS OF CONDUCTORS, AND
3. PROVIDE SUBMITTAL OF LIGHTNING PROTECTION DESIGN TO FAA COR FOR APPROVAL. DESIGN
FAA COR IF DIMENSIONAL ERRORS OR DESIGN CONFLICTS OCCUR.
WORK THAT IS IMPROPERLY INSTALLED OR LOCATED. THE INSTALLER/DESIGNER SHALL NOTIFY THE
COORDINATE THE WORK SHALL TAKE RESPONSIBILITY FOR THE WORK AND ANY PORTION OF THE
CONDITIONS BEFORE THE WORK IS STARTED. INSTALLERS WHO FAIL TO VERIFY, REVIEW AND
2. THE LIGHTNING PROTECTION INSTALLER/DESIGNER IS TO CHECK AND VERIFY ALL DIMENSIONS AND
MUST BE COMPLETED BY A QUALIFIED LIGHTNING PROTECTION CONTRACTOR.
SYSTEMS. TIE NEW LIGHTNING GROUND AND BONDING SYSTEM INTO EXISTING SYSTEM. ALL WORK
CODE 780 AND THE LIGHTNING PROTECTION INSTITUTE CODE 175 FOR LIGHTNING PROTECTION
THE REQUIREMENTS OF UNDERWRITERS LABORATORY CODE 96/96A, NATIONAL FIRE PROTECTION
1. PROVIDE LIGHTING GROUNDING AND BONDING DESIGN FOR THE FALL PROTECTION THAT WILL MEET
FALL PROTECTION, ROOF PAD, AND LIGHTNING PROTECTION PLAN
PERFORMED BY QUALIFIED LIGHTNING PROTECTION CONTRACTOR.
LIGHTNING PROTECTION SYSTEM INTO EXISTING SYSTEM. ALL WORK TO BE
PREVIOUS AIR TERMINAL COVERAGES ON PARAPET WALL. TIE NEW FALL PROTECTION
NEW AIR TERMINAL COVERAGES ON FALL PROTECTION SYSTEM SUPERCEDE
LIGHTNING PROTECTION CONTRACTOR.
WORK. TIE INTO NEW SYSTEM. ALL WORK TO BE PERFORMED BY QUALIFIED
REINSTALL LIGHTNING PROTECTION SYSTEM AND COMPONENTS REMOVED FOR ROOF
zma-19000693-a002
2020-12-09T06:38:20-0500
ROBERT L BELTON
2020-12-08T11:04:32-0500
MICHAEL T L COX
ZMA-19000693-A003
a
4"4"
DETAILS
lo tt e
A003 NOT TO SCALE
TYPICAL ROOF SYSTEM4
ROOF DRAIN
TPO MEMBRANE
CLASS 1A-195, R30 RATING.
NOTE: TPO ROOF SYSTEM - 80 MIL MECHANICALLY FASTENED.
ON EQUIPMENT
METAL COUNTER FLASHING
ROOF CURB
PREFABRICATED
2 PER SIDE
LAG SCREWS
ROOF OPENING
CONTINUOUS HOOK STRIP
BEAM BEYOND
CLAMPING RING
WATER CUT-OFF MASTIC
NOTES:
4"x4" FIBER CANT
PREMOLDED BOOT
CAULKING
STAINLESS STEEL CLAMP
VENT STACK
WATER BLOCK
HEAT WELDED LAP
PLATES & SCREWS 4 PER STACK
SUBSTRATE BOARD
2. REMOVE AND REINSTALL COPING CAP AS NEEDED.
1. PROVIDE SHOP DRAWINGS OF FLASHING.
CANT
TO OUTSIDE OF PARAPET.
AND MECHANICALLY FASTENS
EXTENDS OVER PARAPET
TPO MEMBRANE FLASHING
PARAPET CAP
SHEET METAL
ABOVE HEAD OF CANT
EXTEND TPO MEMBRANE
FALL PROTECTION
A003 NOT TO SCALE (TYPICAL)
METAL PARAPET CAP (COPING) AND BASE FLASHING
TO INSIDE OF CURB.
AND MECHANICALLY FASTENS
EXTENDS OVER CURB
TPO MEMBRANE FLASHING
POLY-ISO BOARD INSULATION R-30 MIN.
EXISTING DECK
5/8" FIREGUARD TYPE X DENS DECK
SCUPPER
DRAIN SUMP.
6. FIELD SPLICES MUST BE LOCATED AT LEAST 6 INCHES OUTSIDE THE
12 INCHES.
5. INSULATION TAPER SHALL NOT BE STEEPER THAN 6 INCHES IN
1/4" MAXIMUM.
4. HOLE IN MEMBRANE MUST EXCEED SIZE OF DRAIN PIPE BY
FROM THE ATTACHMENT POINTS OF THE DRAIN CLAMPING RING.
3. CUT THE MEMBRANE SO IT EXTENDS A MINIMUM OF 1/2 INCH (13 MM)
COMPRESSION ON WATER CUT-OFF MASTIC.
2. ALL BOLTS OR CLAMPS MUST BE IN PLACE TO PROVIDE CONSTANT
1. REMOVE ALL LEAD AND OTHER FLASHING.
COVER BOARD
POLY-ISO BOARD INSULATION
PREMOLDED PENETRATION FLASHING 3
MECHANICAL CURB DETAIL
PROTECTION
FALL
PARAPET
FALL PROTECTION
STRAP ANCHOR
CONDENSATE DRAIN
STONE AND TPO ROOF
ROOF PAD ADHERED TO PAVING
CONDENSATE DRAIN SUPPORT BLOCK
PAVING STONE
SEE SPECIFICATIONS FOR SUBMITTAL REQUIREMENTS.
3. BASIS OF DESIGN IS PRS GUARDRAIL BY LEADING EDGE SAFETY, LLC.
EXCEED CURRENT OSHA 1926.502 REQUIREMENTS.
ANCHORING GUIDELINES FOR THE SUBSTRATE. MUST MEET OR
2. ANCHOR FALL PROTECTION ACCORDING TO MANUFACTURERS
INCLUDE HEIGHT OF RAILINGS AND FASTENING DETAILS.
1. PROVIDE SHOP DRAWINGS OF FALL PROTECTION.
1/2" DENS DECK COVER BOARD
zma-19000693-a003
2020-12-09T06:38:39-0500
ROBERT L BELTON
2020-12-08T11:00:05-0500
MICHAEL T L COX
ZMA-19000693-D001
d
DEMOLITION PLAN
-d
:4
:5 lo tt e
RIDGE LINE
ROOF PLAN - DEMOLITION PLAN
7 PROTECT ALL EXHAUST FANS AND PLUMBING VENTS.
NORMAL HOURS OF OPERATION.
OPERATIONS. WORK OVER ENTRANCE MAY BE REQUIRED OUTSIDE OF FACILITY
COORDINATE WORK OVER ENTRANCE WITH COR TO MINIMIZE IMPACT TO FACILITY
PROTECTION CONTRACTOR.
REINSTALLATION. ALL WORK TO BE PERFORMED BY A QUALIFIED LIGHTNING
SYSTEM AS NEEDED TO PERFORM ROOFING WORK. SYSTEM IS TO BE RETAINED FOR
REMOVE, PROTECT, AND STORE EXISTING LIGHTNING GROUNDING AND BONDING
REPLACE CONDENSATE DRAIN LINES FOR RTUS. (TYPICAL)
REMOVE, PROTECT, STORE AND REATTACH PARAPET CAP.
RECEIVE TPO ROOF SYSTEM.
REMOVE CONSTRUCTION DEBRIS FROM SITE. CLEAN DECKING AND PREPARE TO
DEMOLISH EXISTING MODIFIED BITUMENOUS ROOF DOWN TO EXISTING DECKING.
TO BE DEMOLISHED DOES NOT CONTAIN ASBESTOS.
PERFORM TESTS ON EXISTING FIELD, FLASHING, AND SEALANTS TO VERIFY MATERIAL
ACCORDANCE WITH PROJECT SUBMITTAL PROCEDURES.
USE. SDS AND PRODUCT DATA MUST BE REVIEWED AND APPROVED BY COR PRIOR TO USE IN
CONTRACTOR MUST COORDINATE USAGE OF ANY CHEMICALS OR SEALANTS WITH COR PRIOR TO6.
OF UNEXPECTED WEATHER. ROOF AREAS IN THE EVENT
DAY. ENSURE SUFFICIENT TEMPORARY COVERAGE MATERIALS IS AVAILABLE TO COVER OPEN
TRANSITION FROM NEW ROOF TO EXISTING ROOF MUST BE SEALED AT THE END OF EACH WORK
CONTRACTOR MUST NOT DEMOLISH MORE ROOF THAN CAN BE REPLACED IN A SINGLE SHIFT.5.
PROTECTIVE BOARD LAY PATTERNS, RIDGELINE, AND INDUCTION WELD PATTERNS.
LENGTH AND FREQUENCY FOR CORNERS, EDGES, CRICKETS AND FIELD, INSULATION AND
PROCEDURES. INCLUDE ENGINEERS REPORT DETAILING MECHANICAL FASTENER PATTERN,
ROOF SYSTEM FOR REVIEW AND APPROVAL BY COR IN ACCORDANCE WITH PROJECT SUBMITTAL
PRIOR TO COMMENCING WORK THE CONTRACTOR MUST PROVIDE SHOP DRAWINGS OF NEW 4.
DUST DURING CONSTRUCTION. DEBRIS MUST BE REMOVED BY CONTRACTOR DAILY.
BY COR. AREAS AROUND DUMPSTERS MUST BE KEPT CLEAN AND FREE OF EXCESS DEBRIS AND
DEBRIS MUST BE PROVIDED BY THE CONTRACTOR. DUMPSTERS LOCATIONS TO BE DETERMINED
CONTRACTOR MUST NOT USE FAA DUMPSTERS. DUMPSTERS FOR DISPOSAL OF CONSTRUCTION3.
WORK DAY. DUMPSTER PICKUP AT ALL TIMES. SECURE ACCESS GATES AT THE END OF EACH
CONTRACTOR MUST MAINTAIN ACCESSIBILITY FOR DAYCARE DELIVERIES AND TRASH
CABLES (UNDERGROUND UTILITIES) MAY RUN THROUGH STAGING AREA AND ELSEWHERE.
CONTRATOR MUST DO NO DIGGING WITHOUT PRIOR PERMISSION FROM THE COR. BURIED
STAGING AREA. MATERIALS MUST BE NEATLY STORED AND PROTECTED. CONSTRUCTION
STORAGE OF CONSTRUCTION MATERIALS AND TRAILERS ON SITE MUST BE LIMITED TO THE 2.
TIMELINES WHILE THE ROOF IS OPEN AND THE INTERIOR OF THE BUILDING EXPOSED.
ATTACHMENT AND A REPAIR COST ESTIMATE ON A SQUARE FOOT BASIS TO MINIMIZE DECISION
CONTRACTOR MUST PROVIDE SHOP DRAWINGS FOR THE CORRUGATED STEEL DECK AND
REINFORCEMENT IF REQUIRED, TO COMPLY WITH THE LATEST FLORIDA BUILDING CODE (FBC).
RECOMMENDATIONS FOR REPAIR OR ADDITIONALPROFESSIONAL ENGINEER MUST MAKE
DECK, PUDDLE WELDS AND TEK SCREWS FOR DECK ATTACHMENT. AFTER THE INSPECTION THE
REGISTERED STRUCTURAL ENGINEER TO INSPECT THE EXISTING CONDITION OF THE METAL
PRIOR TO REMOVING EXISTING ROOFING SYSTEM THE CONTRACTOR MUST HIRE A FLORIDA1.
zma-19000693-d001
2020-12-09T06:37:15-0500
ROBERT L BELTON
2020-12-08T10:58:10-0500
MICHAEL T L COX
ZMA-19000693-E501
e
LIGHTNING PROTECTION DETAILS
-e
:4 lo tt e
RADIUS
BONDING LUG
ALUMINUM CONDUCTOR
ROOF DRAIN
LADDER
VENT
HOLDER @3'-0" O/C
ADHESIVE CABLE
#A186X: CAST ALUM
ALUM
BONDING LUG
#A561:
TEE SPLICER
#A706: ALUM
SPLICER
#229S: BIMETAL
(EXISTING DOWN CONDUCTOR)
COPPER CABLE
#509: 10STR. X 14GA. BARE
#A561: CAST ALUMINUM
MIN. 8"
#A706 TEE SPLICER
ALUMINUM (NEW)
BOND CLAMP ALUM
#A240X:
BI-METAL
EXISTING COPPER
CABLE TO GROUND
ROD/COUNTERPOISE
EXISTING PVC
CABLE GUARD
CABLE TO GROUND
ROD/COUNTERPOISE
STRUCTURE
BUILDING
EXISTING COPPER
NO. 229S,
E501 NOT TO SCALE (TYPICAL)
DOWN CONDUCTOR CONNECTION DETAIL
BONDING CONNECTORS AND INSTALLATION HARDWARE
DOWN CONDUCTOR CONNECTION DETAIL
ROOF DRAIN BONDING DETAIL
PIPE RAILING AIR TERMINAL DETAIL
LBS. PER 1000')
STRANDS OF #13AWG WIRES - 190
LIGHTNING CONDUCTOR (37
NO. A37R, CLASS II, ALUMINUM
HORIZONTALLY
AIR TERMINAL BASE MOUNTED
NO. APRB1.5/2AT58 PIPE RAILING
INSTALLED BY OTHERS
RAILING, PROVIDED AND
GALVANIZED STEEL PIPE
FLAT SURFACE AIR TERMINAL DETAIL 3
PIPE RAILING CONNECTION DETAIL
HORIZONTALLY
UNIVERSAL BASE MOUNTED
NO. AUBU58I, ALUMINUM
LBS. PER 1000')
STRANDS OF #13AWG WIRES - 190
LIGHTNING CONDUCTOR (37
NO. A37R, CLASS II, ALUMINUM
LBS PER 1000')
*13AWG WIRES -190
CONDUCTOR (37 STRANDS OF
ALUMINUM LIGHTNING
NO A37R CLASS 11,
BASE CONNECTION
CONNECT ABOVE
ALUMINUM PIPE CLAMP
NO APC -1/1.25
INSTALLED BY OTHERS
RAILING, PROVIDED AND
GALVANIZED STEEL PIPE
TERMINAL WITH SAFETY TIP
CLASS II, ALUMINUM AIR
NO. 5824-ASTAT, 5/8"x 24"
CABLE FASTENER, EVERY 3' MAX.
NO. A262, ALUMINUM ADHESIVE
ALUMINUM AIR TERMINAL WITH SAFETY TIP
NO. 5824-ASTAT, 5/8" X 24" CLASS II,
FOR SUBMITTAL REQUIREMENTS.
IS CALLED OUT TO ESTABLISH A BASIS OF DESIGN. SEE SPECIFICATION
1. FOR THIS DRAWING THOMPSON LIGHTNING PROTECTION HARDWARE
PER 1000')
#13AWG WIRES - 190 LBS.
CONDUCTOR (37 STRANDS OF
NO. A37, CLASS II, ALUMINUM
IN
GENERAL NOTE
FLASHING
CLAMP ALUM
FLAT METAL
CABLE TO
#A142X:
BOND STRAP
#A800:
#A141:
BOND LUG
#A551:
ALUM SPLICER
#A423:
BOND PLATE
#A702:
zma-19000693-e501
2020-12-09T06:37:37-0500
ROBERT L BELTON
2020-12-08T10:57:38-0500
MICHAEL T L COX
ZMA-19000693-G001
COVER SHEET, INDEX AND VICINITY MAP
-g
PROJECT
LOCATION
HIALEAH
HIALEAH
GARDENS
CORAL
GABLES
SOUTH
MIAMI
BEACH
NORTH
BEACH
SPRINGS
SWEETWATER
KENDALL
LAKES
I
TURNP
IKE
X
W Y
PALMETTO
DOLPHIN EXPWY
AIRPORTEXPWY
EXP
WY
SHULA
CAUSEWAY
KEY
BISCAYNE
SUNSET DR
BIRD RD.
CORAL WAY
TAMIAMI
FLAGER ST
SW 24 ST
SW 8 ST
NW 25 ST
NW 36 ST
J
NW 54 ST
NW 79 ST
NW 103 ST
NW 135 ST
NW 183 ST
NW 186 ST
DI
XI
HWY
J.F.K. 71 ST
OKEECHOBEE RD
S
VENETIAN CSWY
MCARTHUR CSWY
RICKENBACKER CSWY
BISCAYNE
BAY
INTERNATIONAL
AIRPORT
NW 58 ST
W 49 ST
DRAWING INDEX
DESCRIPTIONDRAWING NO. DATEREV.
ZMA-19000693-E501
ZMA-19000693-A003
ZMA-19000693-A002
ZMA-19000693-A001
ZMA-19000693-D001
ZMA-19000693-G002
ZMA-19000693-G001
10/05/2020
LIGHTNING PROTECTION DETAILS
DETAILS
LIGHTNING PROTECTION PLAN
FALL PROTECTION, ROOF PAD AND
ROOF PLAN
DEMOLITION PLAN
SITE PLAN
COVER SHEET, INDEX AND VICINITY MAP
MIAMI, FL 33166
7500 NW 58TH ST,
ADDRESS:
T OF TRANSPO
T A
IC
OF
STATES
IT
TM
EN
CHILD CARE FACILITY (CCF)
MIAMI AIR ROUTE TRAFFIC CONTROL CENTER (ARTCC)
CCF - MIAMI, FLORIDA
AVIA
TRAT
SI
NI
VICINITY MAP
NOT TO SCALE
/1 lo tt e zma-19000693-g001
2020-12-17T22:16:23-0500
ROBERT L BELTON
2020-12-17T17:14:41-0500
MICHAEL T L COX
ZMA-19000693-G002
g lo tt e
G002
NW 58TH STREET
HOUSE
GUARD
BLDG.
2 STORY BRICK & METAL
ARTCC BUILDING
1 STORY CBS BUILDING
CHILD CARE CENTER
.R
(P
GATE
GENERAL LEGEND
04' 4' 8'
SCALE: 1/4" = 1'-0"
GRAPHIC SCALE
NORTH ARROW
EXISTING WORK, UON
NEW WORK, UON
CONTRACTOR, UON
DEMOLITION BY
DETAIL REFERENCE
DETAIL DESIGNATION
DETAIL IS DRAWN
SHEET ON WHICH
A012
SECTION DESIGNATION
SECTION IS CUT
SHEET ON WHICH
ABBREVIATIONS
LIMIT OF DEMOLITION
CONNECT TO EXISTING
M101
INCHIN
INSIDE DIAMETERID
MINIMUMMIN
MANUFACTURERMFG
MAXIMUMMAX
.R
(P
BUILDING
NCO
AND STAGING AREA
CONTRACTOR PARKING
GALVANIZEDGALV
GUAGEGA
FEETFT
NOT TO SCALENTS
NATIONAL PIPE THREADNPT
OUTSIDE DIAMETEROD
ON CENTEROC
KITCHEN HOOD VENTILATION UNITKHVUK
REPRESENTATIVE
CONTRACTING OFFICERS COR
PLUMBING VENTPV
POUNDS PER SQUARE INCHPSI
ROOFTOP UNITRTU
ROOF DRAINRD
REQUIREDREQ'D
REFERENCEREF
POLYOLEFIN
THERMOPLASTIC-TPO
TYPICALTYP
NOTED
UNLESS OTHERWISE UON
FOR DAYCARE DELIVERIES AND TRASH DUMPSTER PICKUP AT ALL TIMES. SECURE ACCESS GATES AT THE END OF EACH WORK DAY.
CABLES (UNDERGROUND UTILITIES) MAY RUN THROUGH STAGING AREA AND ELSEWHERE. CONTRACTOR MUST MAINTAIN ACCESSIBILITY
SHALL BE NEATLY STORED AND PROTECTED. CONTRACTOR SHALL DO NO DIGGING WITHOUT PRIOR PERMISSION FROM THE COR. BURIED
STORAGE OF CONSTRUCTION MATERIALS AND TRAILERS ON SITE SHALL BE LIMITED TO THE CONSTRUCTION STAGING AREA. MATERIALS 9.
DAILY THAT THE SEVERE WEATHER PLAN CAN BE IMPLEMENTED.
WEATHER FORECAST. THE CONTRACTOR MUST NOT REMOVE MORE OF THE ROOF THAN CAN BE REPLACED IN A SINGLE SHIFT. VERIFY
CONTRACTOR AND COR MUST HAVE A DAILY DISCUSSION TO DETERMINE GO/NO GO STATUS FOR ROOF TEAR OFF BASED ON LOCAL 8.
AND ORDINANCES DURING THE CONSTRUCTION PHASE OF THIS PROJECT.
OF THE INDUSTRY. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO MEET ALL FAA ORDERS, FEDERAL, STATES, AND LOCAL CODES
THE CONTRACTOR OF THIS PROJECT SHALL BE QUALIFIED AND FULLY KNOWLEDGEABLE OF THE APPLICABLE CODES AND STANDARDS 7.
ALL CONSTRUCTION SHALL BE DONE IN A NEAT AND WORKMANLIKE MANNER IN ACCORDANCE WITH THE PLANS AND SPECIFICATIONS.6.
SCALE: 1" = 60'
60' 60'0 120'
THESE TO DICTATE THE FIELD WORK. THE COR SHALL STOP WORK ACTIVITIES IF FIELD WORK DEVIATES FROM THE APPROVED COORDINATION DRAWINGS.
CONDITIONS. THE CONTRACTOR SHALL ENSURE THE COORDINATION DRAWINGS ARE APPROVED BY THE COR PRIOR TO INSTALLATION AND SHALL USE
ELEMENTS. INDICATE IN THE COORDINATION DRAWINGS ANY DEVIATION FROM THE DESIGN TO FIT THE NEW INSTALLATION TO THE ACTUAL FIELD
INDICATE DIMENSIONS, DISTANCES, AND ELEVATIONS THAT RELATE TO THE NEW EQUIPMENT AND COMPONENTS WITHIN THE SPACE AND THE BUILDING
IF REQUESTED BY COR, THE CONTRACTOR SHALL SUBMIT COORDINATION DRAWINGS FOR THE APPROVAL OF THE COR. COORDINATION DRAWINGS SHALL 5.
ROUTING OF UTILITIES TO FIT THE CONDITIONS ENCOUNTERED ON SITE ONCE APPROVED BY THE COR AND AT NO ADDITIONAL COST TO THE FAA.
THE CONTRACTOR SHALL BE RESPONSIBLE TO FIELD VERIFY THE EXACT CONDITIONS ON SITE TO ADJUST, OR MODIFY EQUIPMENT LOCATIONS AND4.
THE COR AT LEAST 10 DAYS IN ADVANCE.
OR CIRCUIT BREAKER AT ANY TIME. WORK REQUIRING PERMANENT, TEMPORARY, OR PARTIAL ELECTRICAL/WATER OUTAGES SHALL BE COORDINATED WITH
ONLY FAA PERSONNEL MAY OPERATE CIRCUIT BREAKERS AND VALVES. THE CONTRACTOR SHALL NOT OPEN (DE-ENERGIZE) OR CLOSE (ENERGIZE) ANY VALVE3.
EXTREME CAUTION MUST BE PRACTICED WHEN WORKING ON ANY OF THE BUILDING UTILITIES (ELECTRICAL, MECHANICAL, FIRE, OR PLUMBING). 2.
THE GOVERNMENT.
CONDITIONS, EQUIPMENT AND MATERIAL SUPPLIERS AND WITH ALL PROJECT REQUIREMENTS TO PRODUCE AN ACCEPTABLE PRODUCT FOR SITE
THE CONSTRUCTION PROCESS. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY AND CONFIRM ALL INFORMATION PROVIDED HERE WITH
THESE CONTRACT DRAWINGS ARE SCHEMATIC IN NATURE AND ARE NOT INTENDED TO SHOW ALL POSSIBLE CONDITIONS TO BE ENCOUNTERED DURING 1.
STANDARDSTD
SPECIFICATIONSSPEC
E EXHAUST FANEF
zma-19000693-g002
2020-12-09T06:36:50-0500
ROBERT L BELTON
2020-12-08T10:54:58-0500
MICHAEL T L COX