ZJX-1404273-Specifications-Final.pdf

PDF 3 MB Posted

Attached to
AHU Replacement at the Jacksonville ARTCC, Hilliard, FL
Solicitation number
697DCK-21-R-00432
Issued by

About this file

This federal solicitation seeks proposals to replace three air handling units at the Jacksonville Air Route Traffic Control Center in Hilliard, Florida. The Federal Aviation Administration's Boston Enroute Construction Office issued a Request for Offer set aside for small businesses. The project entails replacing air handling units 510, 515, and 520. The estimated price range for the requirement is $750,000 to $1,000,000. Payment and performance bonds are required. Due to COVID-19 restrictions, an in-person site visit will be scheduled at a later date. Offerors must be registered in the System for Award Management and submit proposals in accordance with the instructions and criteria outlined in Sections L and M of the solicitation. Proposals are due by the date specified in the solicitation.

View the file

Other files

File Type Posted
Amendment0002.pdf PDF
697DCK-21-R-00432amendment0001.pdf PDF
RFO697DCK21R00432.pdf PDF
wagerates.pdf PDF
ZJX-1404273-Drawings-Final.pdf PDF
COVID-19 Contractual Requirement 21-3-17.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Aviation Administration

ZJX Air Route Traffic Control Center Hilliard, FL

AHU: 510,515 and 520 REPLACEMENT.

SPECIFICATION

MARCH 2021

Specification number: FAA-ZJX-1404273

AHU 510, 515, AND 520 REPLACEMENT PROJECT MARCH 2021

JACKSONVILLE AIR ROUTE TRAFFIC CONTROL CENTER FAA-ZJX-1404273

TABLE OF CONTENTS 00 01 10 - 1

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 01 14 00

SUMMARY

WORK RESTRICTIONS

01 14 13 SITE ACCESS, CONSTRUCTION LIMITS

01 14 16 COORDINATION AND TESTING

01 25 00 SUBSTITUTION PROCEDURES

01 32 16 CONSTRUCTION SCHEDULES

01 33 00 SUBMITTALS

01 35 29 01 35 99

HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES

COVID-19 SAFETY REQUIREMENTS

01 65 10 MATERIALS AND EQUIPMENT

01 71 33 PROTECTION OF WORK AND PROPERTY

01 73 00 EXECUTION

01 73 29 CUTTING AND PATCHING

01 74 00 01 77 00 01 78 23 01 78 36 01 78 39

CLEANING

CONTRACT CLOSEOUT

OPERATIONS & MAINTENANCE MANUALS

WARRANTIES AND GUARANTIES

PROJECT RECORD DOCUMENTS

DIVISION 02 - EXISTING CONDITIONS

02 41 19 SELECTIVE STRUCTURE DEMOLITION

DIVISION 03 – CONCRETE

03 30 00 CAST-IN PLACE CONCRETE

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 13 PENETRATION FIRESTOPPING

DIVISION 08 – OPENINGS

08 91 00 HURRICANE RATED LOUVERS

DIVISION 09 - THERMAL AND MOISTURE PROTECTION

09 67 23 09 96 00

RESINOUS FLOORING

HIGH PERFORMANCE COATINGS

DIVISION 22 – PLUMBING

22 13 19 SANITARY WASTE PIPING SPECIALTIES

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

23 00 00 BASIC MECHANICAL MATERIALS AND METHODS.

23 05 19 METERS AND GAGES FOR HVAC PIPING

23 05 23 GENERAL-DUTY VALVES FOR HVAC PIPING

23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 19 HVAC EQUIPMENT AND PIPING INSULATION

23 09 00 INSTRUMENTATION AND CONTROLS FOR HVAC

TABLE OF CONTENTS 00 01 10 - 2

23 21 13 HYDRONIC PIPING

23 30 00 AIR DUCT ACCESSORIES

23 31 13 23 37 13 23 73 13

METAL DUCTS

DIFFUSERS REGISTERS AND GRILLES

INDOOR BASIC AIR HANDLING UNITS

DIVISION 26 - ELECTRICAL

26 05 00 COMMON WORK RESULTS FOR ELECTRICAL

26 05 19 LOW VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS

26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS

26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS

DIVISION 28 – FIRE DETECTION SYSTEM

28 31 00 FIRE DETECTION AND ALARM

APPENDIX A – FAA ORDER 1217H ELECTRICAL WORK, PREMISES WIRING

END OF TABLE OF CONTENTS

GENERAL REQUIREMENTS 01 00 00-1

SECTION 01 00 00 GENERAL REQUIREMENTS

PART 1 – GENERAL

1.1 SCOPE

Scope - These specifications, together with referenced specifications, standards, construction drawings specified on the Contract Documents and the conditions of the Construction Contract cover the requirements of the Federal Aviation Administration (FAA) for the work associated with this project.

1.2 REPAIR AND PROTECTION

A. General: Upon completion of inspection, testing, sample taking and similar services, repair damaged construction and restore substrates and finishes.

B. Protect construction exposed by, or for quality control service activities, and repaired construction.

C. Contractor is responsible for, but not limited to, all repair and protection of existing equipment, systems and services, associated with or affected by the contract requirements and work area.

1.3 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced. Such standards are made a part of the Contract Documents by reference.

B. Publication Dates: Comply with the standards in effect as of the date of the Contract Documents.

C. Conflicting Requirements: Where compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different but apparently equal to the COR for a decision before proceeding.

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Refer uncertainties to the COR for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on the Project must be familiar with industry standards applicable to its construction activity. Copies of applicable industry standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction activity, the

Contractor shall obtain copies directly from the publication source and make them available on request.

GENERAL REQUIREMENTS 01 00 00-2

E. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where abbreviations and acronyms are used in the Specifications or other Contract Documents, they mean the recognized name of the trade association, standards-generating organization, authorities having jurisdiction, or other entity applicable to the context of the text provision. Refer to Gale Research's "Encyclopedia of Associations" or ‘Columbia Books' "National Trade & Professional Associations of the U.S.," which are available in most libraries.

1.4 RECORD DRAWINGS

The Government shall provide the Contractor with an electronic copy of the record drawings in .PDF format. During the course of construction, the addition of new graphics or text shall be in green; the removal of any text or graphics shall be in red. Any additional notes or general information shall be noted in blue. These “as-builts” shall be submitted to the FAA both in hard and soft copy; number of copies to be determined by the COR. As-Built progress shall be reviewed as part of each pay application submitted by the Contractor.

END OF SECTION 01 00 00

SUMMARY OF WORK 01 11 00 - 1

SECTION 01 11 00 SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Scope of Work - These specifications, together with the referenced specifications, standards, and drawings specified in the contract documents cover the requirements for all work associated with the following activities in the Power Services Building located at the Jacksonville (ZJX) ARTCC located in Hilliard, FL.

The work shall include:

1. Power Services Building Air Handler Replacement

a. Remove existing AHU’s 510,515, and 520

b. Resurface mechanical room floor

c. Provide and install two 57 ton CHW AHU's for AHU 510 and 515

d. Provide and install one 25 ton CHW AHU for AHU 520.

e. Mount new AHU's on existing concrete pads.

f. Provide and install new ductwork to existing floor penetrations, and exterior louver. Supply and return ductwork shall have floor supports.

g. Install and test new control devices as shown on contract drawings.

h. Provide and install isolation dampers on supply and return ductwork.

i. Provide and install duct mounted smoke detectors on supply and return for AHUs 510 and

515, and return smoke detector for AHU 520.

j. Provide and install new steel piping from existing isolation valve and fittings (strainer, balancing valve, control valve, thermometers, pressure gauges) to each AHU with 1-1/2" Polystyrene insulation with color coded jacket with labeling.

k. Replace all chilled water piping insulation with new insulation and color coded jacket with labeling in room.

l. Provide and install airflow stations on outside air ductwork for AHU-510,515, and AHU- 520.

m. Remove exhaust fan in mechanical room and seal openings with insulated panels matching existing material gauge, color, finish and pattern.

n. Modify existing Class A Fire Alarm System.

The General Contractor (GC) shall be expected to work during day times, 07:00 AM to 5:00 PM. Night work may be required as needed. Extensive coordination between the GC and the COR shall be required at all times in order to maintain an operational facility. Prospective bidders are strongly recommended to perform a site visit to assess the actual conditions before submitting a bid. Site visits should be arranged thru the Contracting Officer’s Office.

2. FAA Holiday Moratorium - No work shall be scheduled or take place during the week of and the weekend preceding and following: Thanksgiving, Christmas, and New Year’s. Only emergency work to restore critical services to the Facility will be considered and a moratorium waiver must be submitted and approved. The moratorium period will not be counted against the contract construction duration of the project.

SUMMARY OF WORK 01 11 00 - 2

3. FAA Holidays Observed - The FAA also observes the following Holidays: : Birthday of Martin Luther King, Jr., Washington’s Birthday, Memorial Day, Independence Day, Labor Day, Columbus Day, and Veterans Day.

Any work required on any observed Holiday must be coordinated with the Contracting Officer Representative (COR) two weeks in advance. The Holiday observances will not be counted against the contract construction duration of the project.

4. Intent of Specifications - This specification identifies all material, labor, and equipment required to perform this work. All work performed and all materials and equipment used are subject to approval by the Contracting Officer (CO) and /or the Contracting Officer Representative (COR). This shall include but is not limited to inspection, scheduling, reporting and submittals.

5. Title - Titles to division and sections of the specifications and notes and titles on drawings referring to subcontractors, division of work by trade, or type of work, are introduced merely for convenience in reading the specifications and drawings and do not imply any separate contractual arrangements of work assignments. Such separations into titled divisions and sections shall not operate to make the Government an arbiter to establish subcontract limits between the contractor and subcontractors, or between the subcontractors themselves.

6. Contract Documents - The drawings form a part of the construction requirements for this project.

The Contractor shall not use dimensions scaled from drawings. All dimensions shown on the drawings shall be field verified by the contractor prior to construction. Any discrepancies between the drawings and specifications and the existing conditions shall be referred to the CO for adjustment before any work affected is performed.

7. Precedence of Contract Documents - In the event of a difference between the following contract provisions, the order of precedence to determine which provision shall govern is:

1. Contract Clauses and Provisions

2. Project Specifications

3. Project Drawings

Any discrepancies between the contract provisions, the specifications and the contract drawings shall be referred to the CO for a written determination in accordance with Contract Clause entitled Order of Precedence.

8. Contracting Officer -The term "Contracting Officer" (CO) as used herein denotes the person designated to act on behalf of the Government in the performance of this contract. Where reference is made to "Federal Aviation Administration" (FAA), "Contracting Officer's Representative" (COR), or the like, this shall mean the Contracting Officer or his/her authorized representative.

9. Contractor Superintendence - In accordance with Contract Clause entitled SUPERINTENDENCE BY THE CONTRACTOR, the Contractor shall at all times during performance of this contract and until the work is completed and accepted, directly superintend the work or assign and have on site a competent superintendent with the authority to act for the Contractor. The Contractor shall submit a Project Organizational Chart with the key personnel identified and their qualifications for the Government’s review and approval. If, in the event the Contractor is not on site, on site activities shall cease immediately, or a competent superintendent with the authority to act for the Contractor must be appointed in writing to the CO and COR.

SUMMARY OF WORK 01 11 00 - 3

1.2 SPECIAL REQUIREMENTS

A. Asbestos Containing Materials - No new materials supplied by the contractor for this construction shall contain asbestos or lead-based products. The contractor shall verify that all materials, including those supplied by third parties, are asbestos free and/or lead-based free materials.

1. Contractor certification requirements. - The contractor shall provide to the Contracting Officer (CO) a signed and notarized document stating that to the best of his/her knowledge, no asbestos containing or lead-based materials were used during the construction, renovation, and/or modernization of this facility.

2. Safety Data Sheets. - The contractor shall submit Safety Data Sheets (SDS) with all submittals for review and approval by the Contracting Officer Representative. New materials found to contain asbestos and/or lead-based products will be automatically disapproved. Copies of all SDS sheets shall be provided to the facility FAA personnel for the building records. The contractor shall comply with all health and safety provisions outlined in each SDS and shall follow all OSHA guidelines regarding personnel protection.

3. Hazardous materials.- If the FAA COR suspects the presence of asbestos or lead-based products in the new materials, the FAA will sample the suspect material to verify that no asbestos containing material or lead-based material were used. If these materials are found to contain asbestos or lead-based products, the cost of the survey and all subsequent removal/replacement of any hazardous materials shall be at the contractors’ expense.

B. Work plan and scheduling - Prior to the Contracting Officer issuing the Notice To Proceed (NTP), the contractor shall submit for approval a plan and schedule of his work.

C. Sequence of work - The contractor shall be responsible for scheduling all aspects of the work and coordinating among the different trades involved in the project. The Federal Aviation Administration (FAA) has developed a list of milestones that the contractor shall be required to meet.

D. Construction Activities and Milestones – Construction Activities and Milestones below shall be included in the submitted schedule. They are provided for guidance, but are not intended to direct how and when contract activities shall be ordered or take place in the submitted schedule.

1. Submittal Approval

2. Order Long Lead Items

3. Notice To Proceed

a) Scheduled by the FAA’s CO

4. Establish Protection Of Personnel And Equipment

a) Lockout Utilities

5. Installation and start up of AHU 510

6. Installation and start up of AHU 515.

7. Installation and start up of AHU 520.

SUMMARY OF WORK 01 11 00 - 4

8. Remove Personnel and Equipment Protection

a) Remove equipment lockout devices

9. Operator training on new units.

10. Deliver Closeout Documents

11. Contactor Acceptance Inspection

12. Closeout Job

E. Driveway Closures - Contractor shall maintain access to the loading dock at all times.

F. New Utility Work - Interface all existing utility work with new utility work as indicated in the plans and specifications.

END OF SECTION 01 11 00

WORK RESTRICTIONS 01 14 00 - 1

SECTION 01 14 00 WORK RESTRICTIONS

A. Perform administrative job related requirements necessary for the proper conduct of the Work as indicated in this section and to comply with the General Conditions.

1.2 SUBMITTALS

A. Project Safety Program: Provide Project Safety Program for review and approval by the COR.

1.3 COORDINATION AND ACCESS TO SITE

A. The work is at a critical facility which must remain operational 24 hours a day 7 days a week.

The Contractor must not interfere with or disrupt air traffic operations. The work shall not discharge static electricity, damage, or interfere with other equipment at the facility, and security shall not be compromised.

B. General Area Requirements: The Contractor must confine operations, activities, storage of materials, and employee parking within the project boundaries and the approved staging and loading/unloading areas. Any additional space the Contractor deems necessary must be submitted to the COR for review and approval, or be obtained off site, at no additional cost to the Government.

C. Security Requirements: This project is on a restricted entry site and no compromise of the security system in any nature or of any duration may be made without prior approval of the Contracting Officer. Generally, such compromises, when approved, will be less than 24 hours in duration.

D. Facility Access Badges: A temporary access badge is required for each person, who must be a U.S. citizen, to access the site. There are two types of temporary access badges available for the Contractor: a security badge, which requires a background check and grants escort privileges, and a visitor's badge, which does not require a background check and requires being escorted while on site. The security badge will be limited in number and is intended for a few lead installers who will routinely be on site supervising the work and escorting their workers, subcontractors, and vendors. The visitor's badge is intended for non-supervisory crew members, delivery drivers, and other support or occasional personnel, who must be escorted while on site.

Badges must be worn by all people in plain sight at all times while on site.

1. Security Badge: In order to conduct work on site, the contractor must obtain security clearances and security badges for the lead project installers. The estimated amount of time necessary to fill in the security clearance application and visit the FAA Security Officer on site (including picture taking and security briefing/training) for photo ID badging is approximately eight hours for each applicant. After the security clearance application is submitted to the FAA, it may take up to three weeks to process the application and approve the person for security badging. Then it will take approximately

WORK RESTRICTIONS 01 14 00 - 2

one hour on site to be entered into the facility security system. Personnel without security badges will not be allowed to work on site unless they are escorted by badged contractor personnel with escort privileges, or by badged FAA personnel with escort privileges as a last resort. Delays caused by the unavailability of FAA personnel for escorting contractor personnel will not be grounds for project cost or schedule adjustments. The Contractor must ensure that all Government issued security badges are returned to the Contracting Officer prior to final acceptance of the project.

2. Visitor Badges: Each work day, the Contractor will be responsible for ensuring that all

Contractor personnel, upon entering the premises, present proper Government-issued photo identification, such as a valid driver’s license, and receive a Government visitor badge from the Facility Security Office and wear the badge in sight when on the premises. The visitor badges are generally issued for up to one day, as determined by the Facility Security Office.

3. The Contractor must ensure that the badges are turned in when they leave the site, or at the end of the day or specified period, and upon termination or completion of the employee’s work on the project. At least five days before the pre-construction meeting and prior to commencement of work, the Contractor must provide the COR with a list of names of all personnel who will be working at the site, in alphabetical order, with their last name, first name, driver’s license number and state, company name and their telephone number. The Contractor must revise the list as required to remain current. The Contractor shall notify the COR in writing when personnel are no longer employed by the Contractor of subcontractor, or when they no longer have work at the site. Prior to receiving their badges, all Contractor personnel must attend a security briefing, up to one hour in length, to be conducted on site by the Facility Security Office. Contractor personnel will not be permitted to enter the site without a badge.

E. Some areas in the facility are classified as controlled areas that require government escort of

Contractor’s personnel. Contractor’s personnel must not violate any security regulations pertaining to the facility. The Contracting Officer has the authority to remove anyone from the site, including anyone who is determined to be a security risk. This authority extends to the entire complex, not just the buildings.

F. The Government has the right to search anything or anyone at any time on the facility. If, in the judgment of facility personnel, there is a cause to search a vehicle, container, or person, such a search will be made.

G. Contractor Deliveries: The Contractor must provide an individual, submitted to and approved by the COR, who will be responsible for arranging site access for periodic or unscheduled Contractor deliveries. This individual must coordinate with the COR and facility security personnel, prior to the delivery, for site access of the delivery vehicle. Facility security personnel must be provided, at a minimum, with the name of the vendor, the driver’s name, and the purpose for site access. Delivery vehicles arriving at the gate without prior notice and acceptance will be denied access. Delivery vehicles shall only contain items being delivered to FAA; if vehicles contain deliveries for recipients other than FAA at the Jacksonville ARTCC, the vehicle will not be allowed on site. The Contractor assumes complete liability for the actions of delivery personnel and vehicles while on site.

WORK RESTRICTIONS 01 14 00 - 3

H. Work hours: Normal work hours are 6:00 a.m. to 4:30 p.m., Monday through Friday. No work will be performed outside these hours without prior approval of the COR. If the Contractor intends to work other than normal work hours, the Contractor must notify the COR at least 24 hours in advance, or 48 hours prior to night, weekend, or holiday work. Off work hours are12:00 am to 5:00 am. The Contractor shall notify the FAA if personnel will not report to the job site on a normal work day so that the COR and FAA staff can plan accordingly.

I. FAA Maintenance Moratoriums: Unless allowed otherwise by the FAA, no work shall be scheduled or take place during the week of and weekends preceding and following the Thanksgiving, Christmas, and New Years holidays. Only emergency work to restore critical services to the Facility will be considered and a moratorium waiver must be submitted and approved. The moratorium period will not be counted against the contract construction duration of the project. Verify exact dates with COR and include moratorium dates in Contractor’s Construction Schedule.

J. The Contractor’s foreman or superintendent, or another responsible individual temporarily assigned to act as the foreman or superintendent, must be present on site at all times whenever work is being done, even if the only work being performed is by a subcontractor or is a delivery.

K. Contractor's use of premises: The Contractor must allow the Government complete access to all portions of the work site at any time.

L. Staging and parking: No parking or material storage will be allowed within 20 feet of any exterior fence. The Contractor’s staging area is limited to the area designated by the COR. This will be reviewed and agreed on prior to site mobilization. The Contractor is responsible for providing temporary security fencing of their staging area if desired.

M. Vehicle engines of parked vehicles must not be left idling near air intakes for longer than ten minutes for gasoline engines or two minutes for diesel engines.

N. Special Tool Restrictions: Powder-driven fasteners, tools, and devices are not allowed on facility property. Not including vehicle engines, fuel (including natural gas, propane, gasoline, or diesel) powered tools and devices are only allowed with prior approval and scheduling with the COR. At least 48-hours’ notice must be given prior to any proposed use of fuel-powered tools or devices. This restriction includes fuel-powered pumps, generators, welders, and air compressors, including those mounted on vehicles but with their own engines.

O. Outages: The Contractor must request in writing and coordinate any mechanical, water, sewer, or electrical outage at least five working days in advance with the COR. Outages must be kept to a minimum. Outages could require the Contractor to work during other than normal hours at no additional cost to the Government.

Only the FAA will turn off, lock out, and tag out systems, not the Contractor, including to facility equipment, valves, and breakers. The FAA will lock out and tag out systems, and the Contractor may add their lock out and tag out on top of the FAA’s. The Contractor shall positively verify de-energization before working on individual systems.

P. The Contractor must provide safety cones, barricades, and flag off exclusion areas, such as overhead work or around openings. Refer to Sections 01 35 29 Health, Safety and Emergency Response Procedures.

WORK RESTRICTIONS 01 14 00 - 4

Q. Testing: The Contractor must notify the COR in writing at least three working days in advance of any testing.

1.4 SUPPLEMENTARY REQUIREMENTS

A. Damage to the Site: Damage caused by the Contractor's activities to existing facility paving, lawns, curbs, sidewalks, utilities, or buildings must be repaired or replaced by the Contractor.

After the Notice to Proceed and prior to the start of construction, the Contractor and COR must conduct joint inspections of the existing areas affected by the construction. Existing site damage/defects in these areas must be noted by the Contractor in writing and photographed and will be used as the basis for determination of any damages caused by the Contractor's operations.

B. Photography Permit: Photography is allowed on site only by permit from the facility, as obtained by the COR. Photographs are generally restricted to documenting the work and progress and should not show any FAA employees or employees’ automobile/vehicle license plates. Photographs from the facility are for official Government use only and cannot be used on Contractor promotional material or without the expressed written consent from the FAA.

C. The following items are strictly prohibited on the faculty:

1. Any unsafe act.

2. Explosives.

3. Guns or weapons.

4. Pets or animals.

5. Blocking facility driveways or entrances (see drawings).

6. Allowing fumes or odors from the work to enter the facility (see Article 1.2.F. below).

7. Working on energized electrical circuits.

8. Fires or burning.

9. Use of forklifts, man-lifts, loaders or other self-propelled equipment unless equipped with a fire extinguisher.

10. Dripping or leaking vehicles or equipment.

11. Refueling of vehicles or equipment while hot.

12. Bringing any material of health, safety or environmental concern on site without

Material Safety Data Sheets (MSDSs) being readily available on the work site, and without spill containment materials in place and ready to catch spills, including while fueling or servicing vehicles or equipment.

13. Open flame, torching, or other welding without a fire watch, fire extinguisher, and daily hot-work permit from the COR.

14. Performing any work on site without properly providing warning signs, safety cones, barricades and flagging off exclusion areas, such as for overhead work or around openings.

15. Performing any work on site without proper personal protective clothing and equipment, such as hard hats, safety glasses, hearing protection, high visibility vests, gloves, protective boots, et cetera.

WORK RESTRICTIONS 01 14 00 - 5

16. Performing any work on electrical or mechanical systems before positively verifying that the facility has de-energized and locked it out.

17. Use of any tools or equipment without proper inspection before use, including at least daily inspections of equipment.

18. Use of any tools, equipment, or vehicles unless trained, experienced, and certified (if applicable), and authorized by the Contractor, including to operate man-lifts or forklifts.

19. Use of any electrical equipment or extension cords in wet conditions or if not in good condition, properly maintained, grounded, and with ground fault circuit interruption (GFCI) protection.

D. Prevention of Transference of Construction Noise, Dust and Odors: All areas outside the project work areas in the facility will remain occupied and operational (24 hours a day 7 days a week) throughout the entire period of performance of construction. The Contractor is to establish, to the satisfaction of the COR, and maintain provisions to prevent the transference of construction noise, dust and odors from construction areas and activities to the occupied areas of the facility. Such provisions ought to include sealing of existing and new openings in walls, floors and ceilings within the work areas, negative air system, et cetera. The Contractor is to submit to the COR for FAA review and approval proposed methodology for preventing transference.

E. Contractor’s Responsibility for Testing: All testing identified in these documents and/or otherwise required for implementation and completion of the project is the responsibility of the Contractor at no additional cost to the Government.

F. HPSB: Applicable portions of the FAA’s High Performance Standards for Buildings (HPSB) Criteria have been incorporated into the project’s design and documents. These include specifications of certain products based on compliance with local availability and/or recycled content, special procedures for collecting and disposing of construction waste according to local and federal laws and regulations.

G. Controls: Contractor shall subcontract with Jacksonville local vendor of FAA’s controls contractor, Schneider, for controls on this project.

H. Security Systems and Components: Contractor shall subcontract with FAA’s national Security

Systems Design and Integration (SSDI) Contractor Johnson Controls, Inc. (JCI) for all security system and component work, including temporary relocation or removal of existing security components required to complete the work.

I. Salvage Items: Existing fire protection system, controllers, actuators, and other items designated on the drawings to be removed and not incorporated back into the work are to be protected and turned over to the COR.

WORK RESTRICTIONS 01 14 00 - 6

PART 2 - PRODUCTS

2.1 MATERIALS

A. Materials shall be in accordance with the requirements of the individual sections of these specifications.

2.3 MATERIALS CONTAINING ASBESTOS

A. Materials or products used on this project are to be asbestos free.

2.4 LEAD FREE PAINT, PLUMBING AND FLASHING MATERIALS

A. Only lead free paint, plumbing and flashing materials may be used on this project.

2.5 BUY AMERICAN ACT

A. Provide only equipment and materials of United States manufacture on this project.

PART 3 - EXECUTION

3.1 FIELD MEASUREMENTS

A. Contractor, Installer and sub-contractors are responsible for making complete field measurements. Check all dimensions at the job site for components requiring fit to surrounding conditions. Check shop drawings and indicate the actual dimension available at all locations.

3.2 JOB SAFETY PROGRAM REQUIREMENTS

A. All on-site work under this Contract shall be performed in compliance with the requirements of all Federal and State Occupational Safety and Health laws and regulations as they apply to construction site activity.

1. Comply with applicable Occupational Safety and Health Standard (29 CFR 1910 and 1926) promulgated pursuant to authority of the Occupational Safety and Health Act of 1970.

2. Comply with any other applicable Federal, State, or local regulations governing workplace safety to the extent that they do not conflict with other clauses of this contract. If a conflict exists between sections of this Contract, the more stringent requirement takes precedence.

3. Take all other proper precautions to protect the safety and health of the Contractor’s employees, Federal Aviation Administration employees, and the public. Provide and maintain barricades, guard rails, covered walkways, lighting devices and other protective devices necessary to warn and protect the workmen and general public from hazards at the construction site.

4. See Section 01 35 29 “OSHA Safety Requirements” for further details.

3.3 FIRE PROTECTION

A. Maintain fire extinguishers at construction site in sufficient number to adequately protect the structures during construction. Provide at least one fire extinguisher at each construction office.

Provide at least one fire extinguisher for welders or other trades using open flames in the execution

WORK RESTRICTIONS 01 14 00 - 7

of their work. Maintain “Fire Watch” personnel, with fire extinguisher in hand, during all welding/cutting or other open flame operations on, within, or near existing facility.

B. Maintain the telephone number of the local fire department. Keep number posted conspicuously near telephone.

3.4 DISRUPTION TO SERVICES

A. Construction/Demolition shall in no way interfere with Air Traffic Control Operations. The loss or shut down of existing FAA air traffic control equipment or associated support equipment for any amount of time will jeopardize safety of the flying public and may result in criminal charges against the contractor. Extreme care shall be exercised so as not to cause any interference or interruption of service from this facility.

B. Disruption to existing utilities, piping, or electrical services must be held to a minimum. Carefully plan work in a manner that such disruptions are coordinated with the COR. All operations which require shut down of some portion of the facilities operation shall be in compliance with other Sections of Division 01.

C. Maintain storm sewers and sanitary sewers in service at all times. In the event that it becomes necessary to disrupt one of the utilities, provide temporary service around the construction or otherwise construct the structure in a manner that the flow is not curtailed.

3.5 ENVIRONMENTAL PROTECTION AND POLLUTION CONTROL

A. The Contractor shall perform all work necessary to implement and accomplish a program to prevent environmental pollution during or as a result of construction performed under this contract.

B. Take necessary precautions to prevent contamination of soil or atmosphere by the discharge of noxious substances resulting from construction operations. Provide equipment and personnel and perform emergency measures necessary to contain any spillage. If contamination of the soil does occur, excavate contaminated soil and dispose of at an off-site location in accordance with applicable Federal, State and local regulations. Fill resulting excavations with suitable backfill and compact to the density of the surrounding undisturbed soil.

C. Take measures to prevent dispersal of pollutants into the atmosphere. Do not dump or otherwise discharge noxious, volatile or harmful fluids into drains or sewers.

3.6 HANDLING OF HAZARDOUS MATERIALS

A. Hazardous material which has been identified and requires removal, encapsulation or other protection shall be performed only by qualified, independent asbestos and/or lead base paint abatement contractor(s) as part of this Contract. Disposal of hazardous material resulting from this work shall be in accordance with applicable Federal, State and local regulations.

WORK RESTRICTIONS 01 14 00 - 8

3.7 WEATHER PROTECTION

A. Structure: Provide and maintain weather protection with tarpaulins or polyethylene film supported on and secured to temporary framework and scaffolding to protect all parts of the structure and contents from damage by the elements.

B. Wall Openings: Install, maintain and subsequently remove, temporary weather closures, at exterior walls, parapets, columns and roof construction, as required. These closures shall be installed at the conclusion of each working period affecting the wall openings and shall be maintained in weather- tight condition until work is resumed and completed. The temporary weather closures shall be subject to approval and direction of the COR.

3.8 SLEEVES AND EQUIPMENT BASE

A. Furnish and install temporary watertight closures for sleeve openings below grade. Such closures shall remain in place until pipe installation in sleeves is completed and made watertight.

B. Coordinate the sizes, locations, and installation of all sleeves and equipment bases in a time and manner to avoid any hindrance to work of other trades. In the event that sleeves, inserts, and any imbedded items are to be placed in concrete, form required openings in the Work. Any subsequent related cutting and patching will be the responsibility of the Contractor.

3.9 BLASTING

A. No blasting will be permitted at this site.

3.10 ORDER OF PRECEDENCE

A. Coordinate work in a manner to avoid conflicts or interference between trades. Lay out work in advance of installation to ascertain location of various systems and arrangement of ductwork, piping, conduit, equipment and the like. Coordinate work and take action as necessary to avoid conflicts between the work of various trades. Establish the exact locations of equipment based on actual dimensions of the items furnished.

3.11 INITIAL MAINTENANCE

A. Maintain equipment until the project is turned over to the FAA. Ensure that mechanical equipment is properly greased, oiled, or otherwise cared for as recommended by the manufacturer. Do not operate air handling equipment unless filters are in place and are clean. Change filters operating air handling equipment weekly during construction/operations.

END OF SECTION 01 14 00

SITE ACCESS CONSTRUCTION LIMITS 01 14 13 - 1

SECTION 01 14 13 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK

HOURS

A. Existing facility operations - Construction/demolition shall in no way interfere with Air Traffic Control

Operations. The ARTCC is a 24-hour, seven day a week facility. Extreme care shall be exercised so as not to cause any interference or interruption of service from this facility. Controller functions are vital to the safety of the flying public. It is absolutely mandatory that the contractor protect FAA personnel and existing FAA communication, electrical and mechanical equipment both inside and outside buildings from damage caused by impact, water, debris, dust or odor. The contractor shall have the overall responsibility for the performance and enforcement of all forms of protection within the ARTCC premises against any damages due to work performed under this contract. Any damages incurred, as a result of construction activity during the performance of this contract will be repaired/replaced immediately by the contractor at no cost to the FAA.

Any work or activity that may impact the National Airspace System (NAS), such as work on critical equipment or circuits, will require coordination with the Contracting Officer Representative (COR).

The COR will prepare and submit a work or activity specific “Risk Assessment” for the facility’s review and approval. This process may take one week to complete. Typically, this type of work or activity is performed from midnight to 05:00AM and/or on weekends.

B. Construction limits and access

1. Construction limits - The contractor shall confine operations, activities, storage of materials and employee parking within the designated areas, as indicated on the construction staging plan, or as designated by the COR. Additional space the contractor deems necessary shall be obtained off site, at no additional cost to the Government.

2. Access - Access route for the contractor, subcontractors, employees, deliveries, etc., shall be through the main gate, or as designated by the COR. Access to all, parking areas, and loading dock shall be kept unobstructed. If temporary access obstruction is unavoidable, the contractor shall advise the COR immediately. Vehicles transporting materials shall not be loaded beyond the capacity prescribed by federal, state, or local laws. Obstruction of existing roadways, driveways, to the ARTCC is strictly prohibited.

3. Damage to site - Damage to existing paving, lawns, curbs, sidewalks, and utilities caused by the contractor's activities shall be repaired immediately. Any damage to the building, interior or exterior, that are a result of the contractor’s activities shall be repaired. The contractor shall pay all costs of repairs. After notice to proceed and prior to the commencement of construction, the contractor and COR shall conduct joint inspections of the existing areas affected by the construction. Existing damage or defects shall be noted and will be used as the basis for determination of damages caused by the contractor's operations.

4. The Contractors’ employees may use the Cafeteria if properly badged/escorted.

SITE ACCESS CONSTRUCTION LIMITS 01 14 13 - 2

C. Inspection of site by contractor - It is strongly urged that the contractor carefully examine the premises to determine the extent of work and the conditions under which it must be done.

D. Government use and access to premises - The Government reserves the right to enter the construction area at any time for work inspection and for the operation of the facility.

E. Work hours - All work hours, shifts, and overtime work shall be coordinated with the COR. Before commencing construction, furnish to the COR a statement of hours per day and days per week to normally be worked and approximate number of persons on the job for a normal work shift.

F. Security requirements

1. Personnel List - Contractor shall provide the COR with a list of contractor personnel who require access to the ARTCC. The list shall be submitted immediately after contract award. The list shall be kept current during the project and shall include the following:

Full name, including middle initial Name of Employer Dates Anticipated On-Site Federal or State issued photo ID

2. Security Investigation and Identification - Contractor's personnel may be subject to security investigation by FAA. The contractor shall promptly complete all security forms provided by the CO. Contractor's personnel shall report to the FAA security guard at entrance to the facility and submit proper identification when signing in to obtain an FAA badge which will be worn on an outside garment, above the waist and below the neck, facing forwards, at all times while on the ARTCC premises. This badge shall be returned daily to the security guard when leaving the premises, unless otherwise noted.

3. Vehicle Identification - Vehicle identification tags will be issued for contractor and contractor's employees' vehicles that require access into the ARTCC site. The identification tags shall be displayed in the windshield of the vehicle at all times when the vehicle is on the site. The contractor shall be responsible for the collection and return of all vehicle tags that are no longer required.

4. Escort Requirement - Contractor is responsible to provide an escort for his employees. This will required a security background investigation by the FAA. Contractor's personnel shall not violate any security regulations pertaining to the ARTCC facility. Violators may be removed from the premises with the right to reenter revocable. Contractor's day-to-day work schedules in the classified areas shall be so arranged to allow for minimum escort.

5. Right to Search - Current procedures at FAA facilities include the "right to search." If in the judgment of the FAA a cause to search a vehicle or the person of personnel exists, such search will be made.

6. Replacement of Lost Identification - The FAA will provide personnel badges and vehicle identification tags as described above. It is the contractor's responsibility to return these badges and tags daily and upon completion of the project. The contractor shall be liable to pay for any FAA badge or tag not returned or replaced at the completion of the work. The payment for lost I.D. will be $25.00 for each tag or badge not returned or replaced, except for temporary badges.

SITE ACCESS CONSTRUCTION LIMITS 01 14 13 - 3

7. Physical Security - At the end of each workday, the contractor shall secure all construction areas by closing and locking all doors and gates. The contractor is responsible for the security of the staging area and shall provide the required measures at no additional expense to the government.

END OF SECTION 01 14 13

COORDINATION AND TESTING 01 14 16 - 1

SECTION 01 14 16 COORDINATION AND TESTING

A. Project Coordination - It shall be the duty of the Contractor to prepare a detailed schedule of work and work layout to resolve conflicts and to assure coordination of the work by different trades.

B. Daily Project Scope and Schedule - A detailed daily project scope and schedule must be reviewed with the FAA COR daily. Usually, the daily scope and schedule meeting is held early morning. Hot work permits, utility lockouts, and fire alarm disabling are issued daily and shall be requested at this meeting.

C. Weekly Meeting - Coordination between the COR and Contractor shall take place weekly at the site. Ad Hoc meetings will be scheduled if requested by either the COR or Contractor. The subjects to be discussed at the progress meetings shall include, but are not limited to, the following:

1. Safety concerns/Issues

2. Progress of Work

3. Previous meeting action items/issues

4. Field problems

5. Material and Equipment delivery status

6. Submittal status/schedules

7. Two Week Look-Ahead Schedule

8. Review of changes, and potential effects on the schedule

9. Construction schedule revisions

10. Schedule Revisions

11. Other current business

The following persons will be expected to attend meetings; FAA COR, Prime Contractor Superintendent, Project Manager and Project Manager/Superintendents for other major trades.

D. Facility Coordination Meeting – Ad Hoc coordination meetings shall take place between the facility managers, COR and the Contractor’s Project Superintendent.

E. Work Affecting Operational Systems - The contractor shall coordinate all work which has any or may have any impact on any operational system within the facility through the COR in writing 10 days in advance. The contractor shall immediately cease any work that is adversely impacting the operation of the ARTCC and shall immediately repair or restore any portion of the operational system that has been damaged or suffered diminished performance as a result of the contractor's activities.

F. Local permits and Coordination - The Contractor will be responsible for obtaining and payment of all building fees, inspection fees, utility connection charges and any other fees or charges that may be incurred in the performance of this contract.

COORDINATION AND TESTING 01 14 16 - 2

G. Applicable documents - The contractor shall comply with all local city, county, and state construction codes.

1.2 TESTING

A. Contractor's responsibility - Unless otherwise indicated as the responsibility of another identified entity, Contractor shall provide certified testing and inspection agencies, inspections, tests, and other quality-control services specified elsewhere in the Contract Documents and required by authorities having jurisdiction.

1. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Contractor's responsibility, the Contractor shall employ and pay a qualified independent testing agency to perform quality-control services.

2. Where individual Sections specifically indicate that certain inspections, tests, and other quality-control services are the Government's responsibility, the Government will employ and pay a qualified independent testing agency to perform those services.

a. Where the Government has engaged a testing agency for testing and inspecting part of the

Work, and the Contractor is also required to engage an entity for the same or related element, the Contractor shall not employ the entity engaged by the Government, unless agreed to in writing by the Government.

B. Retesting - The Contractor is responsible for retesting where results of inspections, tests, or other quality-control services prove unsatisfactory and indicate noncompliance with Contract Document requirements, regardless of whether the original test was Contractor's responsibility.

1. The cost of retesting construction, revised or replaced by the Contractor, is the Contractor's responsibility where required tests performed on original construction indicated noncompliance with Contract Document requirements.

C. Selection and payment - The contractor shall pay for all testing. The contractor shall select and use a certified and qualified testing laboratory to perform the requirements of this contract. The American Association of Laboratory Accreditation shall certify the testing laboratory.

D. Rejected materials or workmanship - All materials or workmanship or both which have been rejected by the COR by reasons of failure to conform to the requirements of the Contract Documents shall be removed and replaced with new, acceptable materials by the contractor at the contractor's own expense. Contractor shall also pay for testing of new materials that have been installed in place of rejected materials.

1. The testing laboratory will furnish a digital copy directly to the COR covering all of its determinations and conclusions within 14 calendar days of final testing date. Reports will show all data customarily listed by the laboratory in reporting on quantities, qualities, and types of materials, together with their correlation with the project and applicable Specification Section.

END OF SECTION 01 14 16

SUBSTITUTION PROCEDURES 01 25 00 - 1

SECTION 01 25 00 SUBSTITUTION PROCEDURES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary.

Conditions and other…