ZJX-1404273-Drawings-Final.pdf
PDF 10 MB Posted
- Solicitation number
- 697DCK-21-R-00432
About this file
This document announces a federal solicitation for replacement of air handling units at a Federal Aviation Administration facility in Florida. The Federal Aviation Administration, Boston Enroute Construction Office, is seeking offers to replace three air handling units at the Jacksonville Air Route Traffic Control Center in Hilliard, Florida under Solicitation Number 697DCK-21-R-00432. This is a small business set-aside with a NAICS code of 238220 and size standard of $16.5 million. Offerors must be registered in the System for Award Management to be eligible. Proposals are due by the date specified in the Request for Offer, which along with specifications, drawings and wage rates, is provided in PDF format. The estimated price range for this requirement is $750,000 to $1,000,000. Payment and performance bonds are required.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment0002.pdf | ||
| 697DCK-21-R-00432amendment0001.pdf | ||
| RFO697DCK21R00432.pdf | ||
| wagerates.pdf | ||
| ZJX-1404273-Specifications-Final.pdf | ||
| COVID-19 Contractual Requirement 21-3-17.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
SCHEDULE ON M603.
MONITORING STATION. SEE
PROVIDE AND INSTALL NEW AIR
M603.
DAMPER AND ACTUATOR. SEE
PROVIDE AND INSTALL NEW
FILTER RACKS.
PRESSURE SWITCHES FOR
REQUIRED.
REMAIN UNLESS SPLICE IS
BACK TO CONTROL PANEL TO
WIRE FREEZESTAT. WIRING
PROVIDE AND INSTALL NEW 4-
M603
ACTUATOR. SEE SCHEDULE ON
CHILLED WATER VALVE AND
TEMPERATURE SENSOR
RECONNECT DDC WIRES
AFTER INSTALLATION
PROTECTION CONTRACTOR.
AND REINSTALLED BY FIRE
DETECTOR TO BE REMOVED
EXISTING DUCT SMOKE
M603. REPLACE WIRING.
DAMPER AND ACTUATOR. SEE
RECONNECT DDC WIRES.
PROTECTION CONTRACTOR.
AND REINSTALLED BY FIRE
TEMPERATURE SENSOR
SERPENTINE TYPE
PROVIDE AND INSTALL NEW AIR
CURRENT SENSOR
REPLACE WIRING AND
EXISTING VFD TO BE REUSED,
SEE SCHEDULE ON M603.
DAMPER AND ACTUATOR.
REPLACE EXISTING
ENGINEERING SERVICES
ENROUTE/FSS
ARTCC
AIRFLOW DIAGRAM AHU 510/515
HVAC REPLACEMENT
POWER SERVICE BUILDING
FLJACKSONVILLE CENTERHILLIARD
LW
MC
PROJECT ENGINEER MGR: ENROUTE/FSS ENGR CTR
05/04/2021 1404273
ZJX-1404273-M601
z jx -1
-m
.d g n
THIS DRAWING PRODUCED ON ASO REGION MICROSTATION SYSTEM
ATO - TECHNICAL OPERATIONS EASTERN SERVICE AREA
C O
N S
T R
U
IO
/2
:4
:0
A
M P lo tt e d b y
V
-C
E
G -E
D
B
F
H
8 7 6 5 4 3 2 1
12345678
REVDRAWING NO
DATE JCN
APPROVED BY
ISSUED BY
CHECKED
DRAWN
DESIGNED
SUBMITTED BY
REVIEWED BY
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV
DATE
APPROVED
DESCRIPTION JCN
REDLINE
APVD
TI
XX-05
TI
XX-04
RA
TLL1
AO
GND
X1
NO
COM
NC
DI
RET
RETAI
GRN WHT
TS1
DPS2
NO C
PDI-1
RETDIDI RET
CNO
DPS1
BAG-FILTERPRE-FILTER
3 SaDpr
SaDpr4
480 VAC
L2L3 L1
R1
DO
PWR
SIG
A NO
CHS
CHR
AB
RETDI
SD1
S3
S1
-5
SaSmkDet
SaFan
AH510_MOD3
AI RET
WHTGRN
TS2
SaTmp
STARTER2 RaSmk SaSmk
SaFanCmd
ChwVlvCmd
AH510_MOD4
AH510_MOD3AH510_MOD3
PreFilDifPr BagFilDifPr
MaTmp
RaDprPos
AH510_MOD4
RaSmkDet
AHU510_MOD3
AHU510LlmtAlmStsDI
AFS-1
SA
AH510_MOD6
AirFlw A I a p rF k
AI
RaDprFbk
NO MSTP
VFD
SaDprFbk
X
2 1 3
OA
MIN
OA
ECO
3200 CFM MAX
34 X 14
20000 CFM MAX
34 X 74 c o rF k rC m a rC m
SaFanSts
O C
AIR HANDLING UNIT #510 & 515
LOCATION: POWER SERVICE BUILDING 2ND FLOOR
IS
CD-510D
CD-510A
CD-510B
N.O.
N.C.
CD-510D
CD-510C
AHU-515,
AHU-510. ADJUST NAMES FOR
POINT NAMES SHOWN ARE FOR
CD-510A
zjx-1404273-m601
2021-07-21T15:12:42-0400
ROBERT L BELTON
2021-07-26T10:08:39-0400
MICHAEL T L COX
AIRFLOW DIAGRAM AHU 520
ZJX-1404273-M602
DPS2
NO C
CNO
DPS1
NC
N.O.
RA
EXISTING
CD-520B
RETCOM
NO DI
OA N.C.
CD-520A
Existing
SET @ 38^
BAG-FILTERPRE-FILTER
GRN
TS2
WHT
TLL1
AFMS
RaSmkDet
RaDprCmd
OaDprCmd
MaTmp
PreFilDifPr BagFilDifPr
AH520_MOD3AH520_MOD3
AH520_MOD4
AH520_MOD3
OaAirFlw
AH515_MOD6
OaDprFbk
RaDprFbk
AIR HANDLING UNIT #520
RMMECH
FLOOR NDLOCATION: POWER SERVICE BUILDING 2
24 X 30
10000 CFM MAX
PWR
SIG
R S
ABNO
CHR
CHS
GRN WHT
TS1
RETAI
DO
R1
SA
L3 L2 L1
480 VAC
ChwVlvCmd
SaTmp
RaSmk VFD
SaFanCmd
AH520_MOD5
SaFanSts
LlmtAlmSts
NO MSTP
SD1
SaSmkDet
O C
2 LoLmt
:2 lo tt e
ON M603. REPLACE WIRING
DAMPER. SEE SCHEDULE
NEW ACTUATOR AND
PROVIDE AND INSTALL
WIRING
FILTER RACKS. REUSE EXISTING
PRESSURE SWITCHES FOR
ON M603.
DAMPER. SEE SCHEDULE
NEW ACTUATOR AND
SEE SCHEDULE ON M603.
AIR MONITORING STATION.
TEMPERATURE SENSOR.
NEW SERPENTINE TYPE
TO DDCP.
FREEZESTAT LIMIT ALARM WIRING
CONTROLS CONTRACTOR TO ADD
UNLESS SPLICE IS REQUIRED.
TO CONTROL PANEL TO REMAIN
WIRE FREEZESTAT. WIRING BACK
PROVIDE AND INSTALL NEW 4-
BE REPLACED
TEMPERATURE SENSOR TO
AND ALL WIRING
REPLACE CURRENT SENSOR
PROVIDE AND INSTALL NEW VFD.
SEE SCHEDULE ON M603
VALVE AND ACTUATOR.
NEW CHILLED WATER
RECONNECT DDC WIRES
PROTECTION CONTRACTOR.
AND REINSTALLED BY FIRE
INSTALLATION RECONNECT DDC WIRES
PROTECTION CONTRACTOR. AFTER
BE REMOVED AND REINSTALLED BY FIRE
EXISTING DUCT SMOKE DETECTOR TO
zjx-1404273-m602
2021-07-21T15:23:33-0400
ROBERT L BELTON
2021-07-26T10:07:40-0400
MICHAEL T L COX
MECHANICAL SCHEDULES
ZJX-1404273-M603
:3 lo tt e zjx-1404273-m603
2021-07-21T15:12:14-0400
ROBERT L BELTON
2021-07-26T10:06:47-0400
MICHAEL T L COX
THEY ARE NOT INCLUDED IN CONTRACT WORK.
SEQUENCES ARE HERE FOR REFERENCE ONLY.
SEQUENCE OF OPERATIONS
ZJX-1404273-M604
MODULATION OF CD-520A.
VALUE WILL BE 500 CFM AND BE MAINTAINED AT ALL TIMES VIA THE AFMS BY THE
POSITIONS. AHU 520 DOES NOT HAVE MINIMUM OA DAMPERS. THE MINIMUM OA
EXCEEDS 70°F, THE DAMPERS SHALL BE RETURNED TO THEIR NORMAL
AIR ENTHALPY EXCEEDS THE SETPOINT OR THE OUTDOOR AIR TEMPERATURE
POINT, WHICH IS ADJUSTABLE AND INITIALLY SET AT 48°F. WHEN THE OUTDOOR
ECONOMIZER MODE IF THE MIXED AIR TEMPERATURE DROPS BELOW ITS SET
SENSOR (TS-2). THE MIXED AIR TEMPERATURE SENSOR (TS-1) SHALL DISABLE
TEMPERATURE SET POINT AS SENSED BY THE SUPPLY AIR TEMPERATURE
SEQUENCE WITH THE COOLING (CV-520) VALVES TO MAINTAIN THE SUPPLY AIR
520A) AND RETURN AIR DAMPERS (CD-520B), SHALL BE MODULATED IN
BELOW THE SETPOINT (INITIALLY SET AT 20), THE OUTSIDE AIR DAMPERS (CD-
ECONOMIZER CYCLE BY THE DDCS. AS THE OUTSIDE AIR ENTHALPY DROPS
SHALL BE SENSED TO PROVIDE INPUT DATA FOR ENTHALPY CONTROL OF
THE RETURN AIR AND OUTSIDE AIR TEMPERATURE AND RELATIVE HUMIDITY
ECONOMIZER MODE:
MAINTAIN A SUPPLY AIR TEMPERATURE SETPOINT OF 52"F (ADJ).
ECONOMIZER DAMPERS (IF ECONOMIZER SEQUENCE IS PERFORMED) TO
THE UNIT. THE BMS WILL MODULATE THE UNIT CHILLED WATER VALVE OR
THE BMS WILL CONSTANTLY MONITOR THE SUPPLY AIR TEMPERATURE FROM
SUPPLY AIR TEMPERATURE CONTROL:
BACNET INTERFACE) FOR MONITORING PURPOSES ONLY.
ALSO MONITOR THE POWER CONSUMPTION OF THE DRIVE (AV:6, THROUGH THE
THIS ALARM UPON RECEIVING A FAULT CONDITION FROM THE VFD. THE BMS WILL
BACNET INTERFACE) FOR TROUBLESHOOTING PURPOSES AND WILL DISPLAY
MONITOR THE FAULT CODE GENERATED BY THE DRIVE (AV:51, THROUGH THE
UNIT'S SUPPLY FAN SPEED WILL NOT BE CONTROLLED. THE BMS WILL ALSO
IF THE FAN IS BYPASSING THE VFD, AN ALARM WILL BE GENERATED AND THE
NOT MATCH THE FEEDBACK SIGNAL RECEIVED, AN ALARM WILL BE GENERATED.
GENERATED AND THE UNIT WILL BE DISABLED. IF THE SPEED COMMAND DOES
BE DISABLED. IF A VFD FAULT CONDITION OCCURS, AN ALARM WILL BE
NOT MATCH THE COMMAND, AN ALARM WILL BE GENERATED AND THE UNIT WILL
CONDITION, FAN SPEED, AND FAN BYPASS STATUS. IF THE FAN STATUS DOES
WILL BE GENERATED. THE BMS WILL MONITOR FAN STATUS, FAN FAULT
IF THE SPACE TEMPERATURE RISES 5"F ABOVE SETPOINT, A HIGH TEMP ALARM
TO MAINTAIN THE SPACE TEMPERATURE WITHIN CRITICAL SWITCHGEAR ROOM B.
SETPOINT OF 72"F (ADJ). THIS UNIT WILL WORK IN CONJUNCTION WITH CRAC-1
THE BMS WILL MODULATE THE SUPPLY FAN TO MAINTAIN A SPACE TEMPERATURE
SUPPLY FAN VFD CONTROL:
SEQUENCE OF OPERATIONS AHU-520:
POSITION.
MINIMUM OUTSIDE DAMPERS SHALL BE MAINTAINED IN THE 100%(ADJ) OPEN
THE OUTSIDE AIR DAMPERS ARE OPERATING IN THE ECONOMIZER CYCLE, THE
POINT FOR AHU 510 AND 515 SHALL BE INITIALLY SET AT 3200 CFM (ADJ). WHEN
OUTSIDE AIRFLOW STATIONS (AFMS-1, 3). THE MINIMUM OUTSIDE AIR CFM SET
MODULATED TO MAINTAIN MINIMUM OUTSIDE AIR CFM, AS SENSED BY THE
POSITIONS. THE MINIMUM OUTSIDE AIR DAMPERS (CD-510D,515D) SHALL BE
EXCEEDS 70°F, THE DAMPERS SHALL BE RETURNED TO THEIR NORMAL
AIR ENTHALPY EXCEEDS THE SETPOINT OR THE OUTDOOR AIR TEMPERATURE
POINT, WHICH IS ADJUSTABLE AND INITIALLY SET AT 48°F. WHEN THE OUTDOOR
ECONOMIZER MODE IF THE MIXED AIR TEMPERATURE DROPS BELOW ITS SET
SENSOR (TS-2). THE MIXED AIR TEMPERATURE SENSOR (TS-1) SHALL DISABLE
AIR TEMPERATURE SET POINT AS SENSED BY THE SUPPLY AIR TEMPERATURE
SEQUENCE WITH THE COOLING (CV-510,515) VALVES TO MAINTAIN THE SUPPLY
510A,515A) AND RETURN AIR DAMPERS (CD-510B,515B,), SHALL BE MODULATED IN
BELOW THE SETPOINT (INITIALLY SET AT 20), THE OUTSIDE AIR DAMPERS (CD-
ECONOMIZER CYCLE BY THE DDCS. AS THE OUTSIDE AIR ENTHALPY DROPS
SHALL BE SENSED TO PROVIDE INPUT DATA FOR ENTHALPY CONTROL OF
THE RETURN AIR AND OUTSIDE AIR TEMPERATURE AND RELATIVE HUMIDITY
ECONOMIZER MODE: 12.
CLOSED.
ACTIVE FOR AS LONG AS THE CONTACTS ON THE HYDROGEN SENSOR ARE
NOTIFIED, THE BMS WILL GENERATE AN ALARM. THIS ALARM WILL REMAIN
HYDROGEN PANEL WILL NOTIFY THE BMS OF AN ALARM CONDITION. WHEN
ALARM PANEL. WHEN THE HYDROGEN LEVEL RISES ABOVE 50% LEL, THE
THE BMS WILL MONITOR A SET OF ALARM CONTACTS LOCATED ON A HYDROGEN
HYDROGEN MONITORING:
WORKING FAN TO 100%.
(ADJ), THE BMS WILL GENERATE AN ALARM AND WILL SET THE SPEED OF THE
FAN STATUS DOES NOT MATCH THE COMMAND AFTER A 5 MINUTE INTERVAL
ENDSWITCH WILL MAKE AND THE FANS WILL THEN RAMP UP TO SPEED. IF THE
RUN AT 50% SPEED. WHEN THE ISOLATION DAMPER OPENS, THE DAMPER
THE FAN'S ISOLATION DAMPERS. THE BMS WILL THEN ENABLE BOTH FANS TO
RUN CONTINUOUSLY. WHEN THE FANS ARE ENABLED, THE BMS WILL FIRST OPEN
EXHAUST FANS EF-1 & EF-2 WILL SERVE BATTERY ROOM 101. THESE UNIT'S WILL
EF-1, EF-2:
OF THE WORKING FAN TO 100%.
INTERVAL (ADJ), THE BMS WILL GENERATE AN ALARM AND WILL SET THE SPEED
IF THE FAN STATUS DOES NOT MATCH THE COMMAND AFTER A 5 MINUTE
DAMPER END SWITCH WILL MAKE AND THE FANS WILL THEN RAMP UP TO SPEED.
DURING TESTING & BALANCING). WHEN THE ISOLATION DAMPER OPENS, THE
AND SUPPLY 850 CFM PER FAN (CFM SPEED SETPOINT TO BE DETERMINED
ISOLATION DAMPER. THE BMS WILL THEN ENABLE BOTH SUPPLY FANS TO RUN
IF ONE OF THE UNIT'S IS RUNNING, THEN THE BMS WILL OPEN THE SUPPLY
(ADJ), THE BMS WILL FIRST CONFIRM EITHER AHU-510 OR AHU-515 ARE RUNNING.
FED FROM AHU-510 & AHU-515. IF THE SPACE TEMPERATURE RISES ABOVE 77"F
TEMPERATURE WITHIN THE SPACE. THE SUPPLY FANS WILL HAVE SUPPLY AIR
WILL SERVE BATTERY ROOM 101. THE BMS WILL MONITOR THE SPACE
SUPPLY FANS SF-1 & SF-2
SEQUENCE OF OPERATIONS SF-1, SF-2:
DISABLE THE UNIT.
UNIT. IF THESE CONTACTS TRIP, THE BMS WILL GENERATE AN ALARM AND
THE BMS WILL MONITOR A SET OF GENERAL ALARM CONTACTS LOCATED ON THE
THE COMMAND, THE BMS WILL DISABLE THE PUMP AND GENERATE AN ALARM.
THE BMS WILL MONITOR THE STATUS OF CHP-5. IF THE STATUS DOES NOT MATCH
THAT THE PUMP HAS BEEN STARTED.
CRAC UNIT CHILLED WATER PUMP CHP-5 AND WILL GENERATE A NOTIFICATION
TEMPERATURE RISES 5"F (ADJ) ABOVE SETPOINT, THE BMS WILL ENABLE THE
SETPOINT TO BE 52"F (ADJ). IF THE UNIT IS RUNNING AND THE UNIT'S SUPPLY AIR
SUPPLY AIR TEMPERATURE SETPOINT. INITIAL SUPPLY AIR TEMPERATURE
THE BMS WILL MONITOR THE UNIT'S FAN SPEED, SUPPLY AIR TEMPERATURE, &
SPACE TEMPERATURE SETPOINT.
(ADJ). THIS UNIT WILL WORK IN CONJUNCTION WITH AHU-520 TO MAINTAIN THE
CONTROL ITSELF TO MAINTAIN A SPACE TEMPERATURE SETPOINT OF 72"F
THE UNIT WILL BE PROVIDED WITH ITS OWN SET OF CONTROLS AND WILL
THE BMS WILL COMMUNICATE WITH THE CRAC UNIT VIA A BACNET/LP INTERFACE.
CRAC-1:
SEQUENCE OF OPERATIONS AHU-510 & AHU-515:
ALARM WILL BE GENERATED.
STATIC PRESSURE RISES ABOVE 0.05" W.C. OR FALLS BELOW -0.05" W.C., AN
MAINTAIN A SLIGHTLY POSITIVE BUILDING STATIC PRESSURE. IF THE BUILDING
SWITCHGEAR ROOM 109. THE BMS WILL MODULATE THE RELIEF DAMPERS TO
THE BMS WILL MONITOR THE BUILDING PRESSURE WITHIN THE CRITICAL
RELIEF DAMPERS:11.
FLOW STATION.
AIR AT ALL TIMES. OUTDOOR AIR FLOW WILL BE MEASURED BY OUTDOOR AIR
THE OUTDOOR AIR DAMPER WILL MODULATE TO MAINTAIN 3200 CFM OF OUTSIDE
UNIT DAMPER CONTROL: 10.
SUPPLY AIR DAMPER: CLOSED E.
RETURN AIR DAMPER: OPEN D.
OUTDOOR AIR DAMPER: CLOSED C.
COOLING COIL CONTROL VALVE: CLOSED B.
SUPPLY FAN START/STOP: OFF A.
DEVICES SHALL FAIL IN THE MANNER, AS FOLLOWS:
UPON LOSS OF CONTROL SIGNAL OR ELECTRICAL POWER, THE CONTROL
FAILURE MODE:9.
DIFFERENTIAL PRESSURE ACROSS THE FILTERS.
DIFFERENCE INDICATOR LOCATED AT THE FILTERS SHALL INDICATE THE
ADJUSTABLE LIMIT, AN ALARM SIGNAL WILL BE SENT TO THE DDCS. PRESSURE
THE PRE-FILTER AND FINAL FILTERS. WHEN THE PRESSURE EXCEEDS AN
DIFFERENTIAL PRESSURE SWITCHES SHALL MONITOR THE PRESSURE DROP AT
DIRTY FILTER ALARM: 8.
ALARM SIGNAL SHALL BE SENT TO THE DDCS.
IF THE SUPPLY AIR TEMPERATURE RISES ABOVE 80°F, A HIGH-TEMPERATURE
SUPPLY AIR ALARM 7.
BE RETURNED TO OPERATION.
AND THE FIRE ALARM SYSTEM HAS BEEN RESET, THE AIR HANDLING UNIT SHALL
STOP THE SUPPLY FAN. WHEN THE FIRE ALARM CONDITION HAS BEEN CLEARED,
ALARM SYSTEM SHALL ACTIVATE AN ADDRESSABLE CONTROL DEVICE (ACD) TO
UPON RECEIVING AN ALARM SIGNAL FROM DUCT SMOKE DETECTOR, THE FIRE
FIRE ALARM SHUTDOWN:6.
CONDITION.
FREEZESTAT MUST BE MANUALLY RESET AT THE DEVICE AND OWS AFTER A TRIP
CHW VALVE AND GENERATE AN ALARM AT THE OPERATOR'S WORKSTATION. THE
CLOSE THROUGH A HARDWIRED INTERLOCK. THE DDCS SHALL FULLY OPEN THE
DDCS SHALL STOP THE SUPPLY FAN AND THE OUTDOOR AIR DAMPER WILL
FOR A TRIP SET POINT OF 38°F (ADJUSTABLE). ON A FREEZE CONDITION, THE
THE LOW TEMPERATURE THERMOSTAT (FREEZESTAT) IS MANUALLY ADJUSTED
FREEZESTAT: 5.
AND AN ALARM SHALL SOUND AT THE DDCS AND OWS.
CONTINUES TO DROP TO 40°F, THE FAN AT EACH AHU SHALL BE DEACTIVATED
SHALL BE MODULATED TO THE OPEN POSITION. IF THE MIXED AIR TEMPERATURE
SHALL BE MODULATED TO THE CLOSED POSITION AND THE RETURN AIR DAMPER
WHEN MIXED AIR TEMPERATURE REACHES 45°F, THE OUTSIDE AIR DAMPER
MIXED AIR SHUTDOWN:3.
SCHEDULE WITH OUTSIDE AIR TEMPERATURE.
MAINTAIN A SUPPLY AIR TEMPERATURE FROM 55F TO 65F BASED ON A RESET
ECONOMIZER DAMPERS (IF ECONOMIZER SEQUENCE IS PERFORMED) TO
THE UNIT. THE BMS WILL MODULATE THE UNIT CHILLED WATER VALVE OR
THE BMS WILL CONSTANTLY MONITOR THE SUPPLY AIR TEMPERATURE FROM
SUPPLY AIR TEMPERATURE CONTROL: 2.
(AV:6, THROUGH THE BACNET INTERFACE) FOR MONITORING PURPOSES ONLY.
VFD. THE BMS WILL ALSO MONITOR THE POWER CONSUMPTION OF THE DRIVE
AND WILL DISPLAY THIS ALARM UPON RECEIVING A FAULT CONDITION FROM THE
(AV:51, THROUGH THE BACNET INTERFACE) FOR TROUBLESHOOTING PURPOSES
THE BMS WILL ALSO MONITOR THE FAULT CODE GENERATED BY THE DRIVE
GENERATED AND THE UNIT'S SUPPLY FAN SPEED WILL NOT BE CONTROLLED.
BE GENERATED. IF THE FAN IS BYPASSING THE VFD, AN ALARM WILL BE
COMMAND DOES NOT MATCH THE FEEDBACK SIGNAL RECEIVED, AN ALARM WILL
ALARM WILL BE GENERATED AND THE UNIT WILL BE DISABLED. IF THE SPEED
AND THE UNIT WILL BE DISABLED. IF A VFD FAULT CONDITION OCCURS, AN
FAN STATUS DOES NOT MATCH THE COMMAND, AN ALARM WILL BE GENERATED
STATUS, FAN FAULT CONDITION, FAN SPEED, AND FAN BYPASS STATUS. IF THE
BETWEEN A MINIMUM OF 18HZ (ADJ) TO 60HZ (ADJ). THE BMS WILL MONITOR FAN
TEMPERATURE SETPOINT OF 72 F (ADJ). SUPPLY FAN SHALL MODULATE
ENABLED, THE BMS WILL MODULATE THE UNIT SUPPLY FAN TO MAINTAIN A SPACE
LEAD UNIT WILL BE ROTATED ON A WEEKLY BASIS TO EQUALIZE RUNTIME. WHEN
AHU-510 & AHU-515 WILL OPERATE IN A LEAD/STANDBY CONFIGURATION. THE
SUPPLY FAN VFD CONTROL: 1.
:5 lo tt e zjx-1404273-m604
2021-07-21T15:27:15-0400
ROBERT L BELTON
2021-07-26T10:05:37-0400
MICHAEL T L COX
ROOF LINE
8'-5"
10'-0"
5'-0"
SECOND FLOOR
FLOOR
SECOND
8'-11
LINE
ROOF
4'-101/2"
FL
MC 05/04/2021 1404273
ZJX-1404273-A101
ARCHITECTURAL ELEVATIONS
JACKSONVILLE CENTERHILLIARD
-a
-a lo tt e
4' 7'5' 6' 1
7' 5' 4'1 6'
B' A' A C'B D E
SHEET NOTES:
DEMOLITION OF EXISTING LOUVER CAN BEGIN.
M603 FOR LOUVER SCHEDULE. NEW LOUVER MUST BE ON SITE BEFORE
ACCORDING TO MANUFACTURER RECOMMENDATION. SEE DRAWING
PROVIDE NEW MIAMI-DADE HURRICANE RATED LOUVER AND INSTALL
APPROVED BY COR BEFORE WORK CAN BEGIN.
OF EXISTING WALL. NEW COVERING MUST BE SUBMITTED AND
WEATHER TIGHT, MATCH EXISTING MATERIAL GAUGE AND MATCH FINISH
PROVIDE NEW WALL COVERING. PERMANENT COVERING MUST BE
INSTALLED.
TO BE REINSTALLED AFTER ALL NEW AIR HANDLERS HAVE BEEN
BE PROTECTED AND STORED OUT OF WEATHER WHILE REMOVED. PANEL
COR FOR APPROVAL PRIOR TO START OF WORK. EXISTING PANEL MUST
WITHSTANDING HURRICANE-FORCE WINDS. SUBMIT ON COVERING TO
IS REMOVED. TEMPORARY COVERING MUST BE CAPABLE OF
UNITS. PROVIDE TEMPORARY WEATHER TIGHT COVERING WHILE PANEL
EXISTING. REMOVE 10'-0" X 10'-0" PANEL TO BRING IN NEW AIR HANDLING
PANEL DETAILS AND LOCATION SHOWN FOR REFERENCE ONLY. PANEL IS 1
L
1/8" = 1'-0" SCALE:
WEST ELEVATION1
A101 1/8" = 1'-0" SCALE:
EAST ELEVATION2
A101
NORTH ELEVATION4
SOUTH ELEVATION3
UPS FLOOR
SCALE: 1/8" = 1'-0"
8' 16'08' zjx-1404273-a101
2021-07-21T15:32:41-0400
ROBERT L BELTON
2021-07-26T09:47:19-0400
MICHAEL T L COX
ZJX-1404273-D101
MECHANICAL DEMOLITION
-d
A'
C'
4'6' 5'7' 1
B'
-d lo tt e
SHEET NOTES
POWER SERVICE BLDG
WING
CONTROL
ADMIN
AUTO
KEY PLAN
DEMOLITION OF EXISTING LOUVER.
NEW LOUVER MUST BE APPROVED AND ON SITE PRIOR TO START OF
WORK. SEE A101 FOR PANEL LOCATION.
SUBMIT ON COVERING TO COR FOR APPROVAL PRIOR TO STARTING
EXISTING PANEL TO BE PROTECTED AND STORED OUT OF THE WEATHER.
TEMPORARY WEATHER TIGHT COVERING WHILE PANEL IS REMOVED.
HANDLING UNITS. PANELS MUST ONLY BE REMOVED ONCE. PROVIDE
REMOVE EXISTING 8'-10"x10'-0" PANEL TO BRING IN AND REMOVE AIR
THE OPENING. FALL PROTECTION REQUIRED.
FLOOR DAMPERS MUST BE REMOVED FROM SECOND FLOOR SIDE OF
PENETRATIONS IN SUPPLY AND RETURN DUCT MUST BE DEMOLISHED.
AND IS A CLASS A SYSTEM. CONCRETE FIRE DAMPERS AT ALL FLOOR
WITH FAA COR, WORK MUST DE DONE BY EST CERTIFIED CONTRACTOR
FIRE ALARM CONDUIT/WIRES ASSOCIATED WITH THEM. COORDINATE
DEMOLISH EXISTING DUCT SMOKE DETECTORS, FIRE DAMPER, AND ALL
EMPLOYEES MAY OPERATE BREAKERS.
SERVICE AND ISOLATE IT ELECTRICALLY AND MECHANICALLY. ONLY FAA
PRIOR TO REMOVAL OF ANY AHU, THE FAA SHALL TAKE UNIT OUT OF
DEMOLISH ALL CONDENSATE DRAIN PIPING.
FOR NOTES ON COVERING.
USED TO TRANSPORT MATERIALS IN OR OUT OF THE BUILDING. SEE A101
OUTSIDE AIR OPENINGS MUST BE COVERED WHEN NOT ACTIVELY BEING
WALL. SEE E601 FOR PANEL LOCATION.
VACATED BY CONDUIT DEMOLITION. SEAL MUST MATCH FIRE RATING OF
NOTES ON DRAWINGS A101 AND M101. SEAL ANY PENETRATIONS
BACK TO PANEL. REMOVE LOUVERS/DAMPERS AND REPAIR WALLS PER
REMOVE EF-507 AND F-531; REMOVE WIRING AND CONDUIT FROM FANS
DEMOLISH EXISTING LOUVERS.
VISUALLY INSPECTED BY COR.
INSULATION CANNOT BEGIN UNTIL PIPE IS PRESSURE TESTED AND
TEMPORARILY INSULATED UNTIL PERMANENTLY INSULATED. PERMANENT
WATER PIPING IN MECHANICAL ROOM. ANY EXPOSED PIPE MUST BE
ISOLATION VALVE. REMOVE PIPING INSULATION ON ALL OTHER CHILLED
REMOVE PIPING BACK TO ISOLATION VALVES, USE BLIND FLANGE ON
DEMOLITION. MOTORS TO BE TURNED OVER TO FAA COR.
REMOVED, FOR USE AS SPARE PARTS FOR AHU 515 DURING AHU 510'S
RETAIN THE MOTOR, FAN, BELTS FROM AHU 510 WHILE IT IS BEING
NEXT UNIT.
MUST BE INSTALLED, TESTED AND APPROVED PRIOR TO DEMOLITION OF
TIME. SUGGESTED SEQUENCE IS 510, 515, AND THEN 520. NEW UNIT
AHU'S AND ALL ASSOCIATED DUCTWORK MUST BE DEMOLISHED ONE AT A
EF
W/ FD AT SLAB
72X30 DN
24X30
3" CWS/R
AHU
36X18
515C
CD
MECHANICAL ROOM
(TYP OF 2)
34X48 DN
FIRE DAMPER AT
FLOOR SLAB (TYP)
510C
2" CWR
2" CWS
INTAKE OPENING
1500 CFM MAX
24X24 CONTROL DAMPER
30X72 DN
72X30
3" CWR
3" CWS
STAIRWELL
SCALE: 3/16" = 1'-0"
8' 12'4'04'
MECHANICAL DEMOLITION PLAN
1500 CFM
DAMPER AND HOOD,
16X16 BACKDRAFT
zjx-1404273-d101
2021-07-21T15:31:26-0400
ROBERT L BELTON
2021-07-26T10:03:52-0400
MICHAEL T L COX
ELECTRICAL SYMBOLS
CM
ZJX-1404273-E001
-e lo tt e
GENERAL LEGEND ELECTRICAL LEGEND GENERAL NOTES
TERMINAL_BOX/BOARD/BLOCK
STANDARD ABBREVIATIONS
COR CONTRACTING OFFICER'S REPRESENTATIVE
DDC DIRECT DIGITAL CONTROL
VFD VARIABLE FREQUENCY DRIVE
BREAK LINES
ELEVATION SYMBOL
A012
DETAIL TITLE REFERENCE
SECTION TITLE REFERENCE
DETAIL NUMBER
A010
SECTION IS DRAWN
SHEET ON WHICH
SECTION CUT
NORTH ARROW
DETAIL REFERENCE
MATCH LINE SYMBOL
COLUMN LINE GRID DESIGNATION
ABOVE OR BEYOND
OUTLINE OF OBJECT
CONTRACTOR, UON
DEMOLITION BY
SECTION DESIGNATION
IS DRAWN OR SCHEDULED
SHEET ON WHICH DETAIL
DETAIL DESIGNATION
DETAIL IS DRAWN
SECTION IS CUT
ROOM NAME & NUMBER
EXISTING WORK, UON
NEW WORK, UON
ELEVATION SYMBOL (PLANS)
GRAPHIC SCALE
04' 4' 8'
SCALE: 1/4" = 1'-0"
EQUIPMENT ROOM
FLOOR_EL._10.50'__
ELEVATION REFERENCE
PARTIAL SECTION CUT
_E1
ELEVATION SHOWN
DARKENED ARROW INDICATES
ELEVATION IS DRAWN
ELEVATION DESIGNATION
DESIGNATION
INTERIOR ELEVATION
ELEVATION NUMBER
A AMPERE
AC
AF AMPERE_FRAME
AMM
ANN
AP
AWG AMERICAN_WIRE_GAGE
BC
CB CIRCUIT_BREAKER
CCTV CLOSED_CIRCUIT_TELEVISION
CKT CIRCUIT
CLF CURRENT_LIMITING_FUSE
CO
COMM
CPC CRITICAL_POWER_CENTER
CPU CENTRAL_PROCESSING_UNIT
CR
CS
CT
DB DIRECT_BURIAL
DC
DI DIGITAL_INPUT
DISC
D_PNL DISTRIBUTION_PANEL
DM
DO DIGITAL_OUTPUT
DPDT
DPST
ECP
EDAM
EH
EHC ELECTRIC_HEATING_COIL
ERMS ENVIRONMENTAL_REMOTE_MONITORING_SYSTEM
EMT
FA
FDR
FLA
FLUOR
FO
FOT FIBER_OPTIC_TERMINAL
FV
HOA
HPS
BAT_CHGR
AT
AIC
ELECTRICAL_METALLIC_TUBING
ELECTRIC_HEATER,_ELECTRONIC_HUMIDIFIER
ENGINE_CONTROL_PANEL
ELECTRICAL_DATA_ACQUISITION_AND_MONITORING
DOUBLE_POLE_DOUBLE_THROW
DOUBLE_POLE_SINGLE_THROW
ATS
CONDUIT_ONLY
CONTROL_RELAY
FAN_COOLED
FEEDER
FULL_LOAD_AMPERES
FLUORESCENT
FIBER_OPTIC
FULL_VOLTAGE
HAND-OFF-AUTOMATIC
HIGH_PRESSURE_SODIUM
HERTZ
DIRECT_CURRENT
COMMUNICATIONS
CONDUIT
CURRENT_TRANSFORMER,_CABLE_TRAY
CONTROL_SWITCH
DEMAND_METER
DISCONNECT
BARE_COPPER
BATTERY CHARGER
AMPERE_TRIP
ANNUNCIATOR_POINT
AUTOMATIC_TRANSFER_SWITCH
ANNUNCIATOR
AMMETER
ANALOG_OUTPUT
AMPERE_INTERRUPTING_CAPACITY
ALTERNATING_CURRENT
GROUND
GA GAGE
GAL GALVANIZED
DIA DIAMETER
EXT
EXIST EXISTING
EXTERIOR
CBS CENTRAL BATTERY SYSTEM
JB
KA
KCMIL
KV KILOVOLT
KVA KILOVOLT_AMPERES
KVAR KILOVOLT_AMPERES-REACTIVE
KW KILOWATT
KWH KILOWATT_HOUR
JUNCTION_BOXJ
K
THOUSAND_CIRCULAR_MILLS
KILO_AMPERES
LTG
LV LOW_VOLTAGE
MCC
MCP MOTOR_CIRCUIT_PROTECTOR
MDT MAIN_DISTRIBUTION_TERMINAL
MG MOTOR_GENERATOR
MH MANHOLE
MLO
N NEUTRAL
OVHD
P POLE
PCMS
PCS
PF
RFI
RGS
RMS
SCC
SCP
SP
SRG
STGP
STP
SW
SWBD
SWGR
TB
TC
TD
TERM
VA
WM
XFMR
Y-D
Z
W
Y
MOTOR_CONTROL_CENTER
MAIN_LUGS_ONLY
LIGHTING
OVERHEAD
POWER_CONTROL_MONITORING_SYSTEM
POWER_CONDITIONING_SYSTEM
POWER_FACTOR
NEMA
UONU
POS
PH PHASE
PNL PANEL
POSITIVE,_POSITION
RECEPTACLE
RADIO_FREQUENCY_INTERFERENCE
RIGID_GALVANIZED_STEEL
SECURITY_CONTROL_CENTERS
SYSTEM_CONTROL_PANEL
SINGLE_POINT/SINGLE_POLE
SIGNAL_REFERENCE_GRID
SIGNAL_TRANSPORT_GROUND_PLANE
SHIELDED_TWISTED_PAIR
SWITCH
SWITCHBOARD
SWITCHGEAR
TRANSDUCER
TRIP_COIL
TIME_DELAY
TERMINAL
UNLESS_OTHERWISE_NOTED
VOLT/VOLTAGE
VOLT-AMPERE
WATT/WIRE
WATTMETER
TRANSFORMER
Y WYE
WYE-DELTA
IMPEDANCE
REC
MCB MAIN_CIRCUIT_BREAKER
ROOF_MEAN_SQUARE
INCAND
ISMS
I INCANDESCENT
INTEGRATED SECURITY MANAGEMENT SYSTEM
AA AIR_COOLED
MANUFACTURER'S ASSOCIATION
NATIONAL ELECTRICAL
SM_
DP-1
WHEN THERE ARE MORE THAN 3 IN A CONDUIT
CROSS MARKS DENOTE NUMBER OF WIRES
INDICATED WITH BLANK COVER PLATE (UON)
JUNCTION BOX- WALL MOUNTED AT HEIGHT
CONDUIT DOWN
CONDUIT UP
RAISED FLOOR WITH BLANK COVER PLATE (UON)
JUNCTION BOX ABOVE CEILING OR BELOW
CENTER OF DEVICE UON
MOUNTING HEIGHTS SHOWN WITH SYMBOL TO
BREAKERS.
SEPARATED BY COMAS INDICATE MULTIPLE POLE
CIRCUIT LOCATION IN THE PANEL. NUMBERS
PANEL DESIGNATION AND NUMBER INDICATE THE
HOMERUN TO PANELBOARD. LETTERS INDICATE
+90"
J
RMC RIGID METALLIC CONDUIT
LIMIT OF DEMOLITION
WIRES PLUS 1#12 GROUND, UON
BRANCH CIRCUIT- EXPOSED, 3/4" C, WITH 3#12
2#12 WIRES PLUS 1#12 GROUND, UON.
FLEXIBLE METALLIC CONDUIT EXPOSED WITH
VFD VARIABLE FREQUENCY DRIVE
ELECTRICAL PANELBOARD
MANUAL MOTOR STARTER SWITCH
WHICH CASE, FAA STANDARDS SHALL GOVERN.
FOLLOWED, EXCEPT WHEN FAA STANDARDS ARE MORE STRINGENT, IN
LATEST EDITION OF THE NATIONAL ELECTRICAL CODE SHALL BE
MANNER IN ACCORDANCE WITH THE PLANS AND SPECIFICATIONS. THE
ALL CONSTRUCTION SHALL BE DONE IN A NEAT AND WORKMEN LIKE 15.
NOT ACCEPTABLE IN ANY APPLICATION.
FITTINGS, SUITABLE FOR USE AND LOCATION. SCREW-TYPE FITTINGS ARE
CONDUIT MINIMUM SIZE SHALL BE 3/4". USE COMPATIBLE CONDUIT 14.
FINISHED FLOOR, UNLESS OTHERWISE INDICATED.
INDICATED HEIGHTS ARE FROM CENTER OF BOX, OR EQUIPMENT, TO THE 13.
DEEP, AND SHALL BE INDEPENDENTLY SUPPORTED.
ALL BOXES SHALL NOT BE LESS THAN 4 INCHES SQUARE, 2 1/8 INCHES 12.
CONFORM WITH STRUCTURAL CONDITIONS.
EQUIPMENTS. EXACT ROUTING SHALL BE DETERMINED AT JOB SITE TO
ONLY TO INDICATE CONNECTIONS BETWEEN DEVICES AND/OR
ROUTE OF CONDUITS SHOWN IN LAYOUT IS SCHEMATIC AND INTENDED 11.
EDITION OF THE NATIONAL ELECTRICAL CODE (NEC) AND FAA-STD-019F.
ALL EQUIPMENT SHALL BE GROUNDED ACCORDING TO THE LATEST 10.
NEMA STANDARDS.
ALL EQUIPMENT SHALL BE NEW AND APPROVED ACCORDING TO ANSI AND 9.
GROUND CONDUCTOR.
I.E., EACH OVERCURRENT DEVICE SHALL HAVE ITS OWN SEPARATE
SHARED/COMMON GROUNDING CONDUCTORS SHALL NOT BE PERMITTED, 8.
RESPECTIVE FEEDER OR PHASE CONDUCTOR SIZES.
CONDUCTOR. NEUTRAL CONDUCTOR SIZES SHALL NOT BE LESS THAN THE
OVERCURRENT DEVICE SHALL HAVE ITS OWN SEPARATE NEUTRAL
SHARED/COMMON NEUTRALS SHALL NOT BE PERMITTED, I.E., EACH 7.
COLOR CODING AS INDICATED IN PROJECT SPECIFICATIONS.
SMALLER; STRANDED COPPER CONDUCTOR FOR LARGER THAN 10AWG.
OTHERWISE SPECIFIED. USE SOLID COPPER CONDUCTOR FOR 10AWG AND
SMALLER THAN 12AWG, INSTALLED IN METALLIC RACEWAYS, UNLESS
ALL WIRING SHALL CONSIST OF INSULATED COPPER CONDUCTORS, NOT 6.
ACCORDANCE WITH UL STANDARDS.
WALLS. MATERIALS & METHODS EMPLOYED IN FIRESTOPPING SHALL BE IN
FIRESTOP CONDUIT PENETRATIONS THROUGH FLOORS AND FIRE RATED 5.
"B" - BUILDING SERVICE
"E" - ESSENTIAL
"C" - CRITICALBUS DESIGNATION:
ROOM NUMBER
PANEL DESIGNATION
C-1051-A
EXISTING POWER PANELS ARE DESIGNATED AS FOLLOWS:4.
COORDINATED IN ADVANCE WITH THE COR.
PERMANENT,TEMPORARY OR PARTIAL ELECTRICAL OUTAGES SHALL BE
ANY CIRCUIT BREAKER AT ANY TIME. WORK REQUIRING
CONTRACTOR SHALL NOT OPEN (DE-ENERGIZE) OR CLOSE (ENERGIZE)
ONLY FAA PERSONNEL MAY OPERATE CIRCUIT BREAKERS. THE 3.
MAY CAUSE ACCIDENTS AND/OR LOSS OF LIFE.
CONTROL CENTER (ARTCC) AND UNAUTHORIZED ELECTRICAL OUTAGES
SERVICE). THIS FACILITY IS AN OPERATIONAL AIR ROUTE TRAFFIC
ELECTRICAL POWER SYSTEMS (BUILDING, ESSENTIAL AND CRITICAL
EXTREME CAUTION MUST BE PRACTICED WHEN WORKING ON ANY OF THE 2.
PRODUCT FOR THE GOVERNMENT.
WITH ALL PROJECT REQUIREMENTS TO PRODUCE AN ACCEPTABLE
HERE WITH SITE CONDITIONS, EQUIPMENT AND MATERIAL SUPPLIERS AND
CONTRACTOR TO VERIFY AND CONFIRM ALL INFORMATION PROVIDED
DURING THE CONSTRUCTION PROCESS. IT IS THE RESPONSIBILITY OF THE
INTENDED TO SHOW ALL POSSIBLE CONDITIONS TO BE ENCOUNTERED
THESE CONTRACT DRAWINGS ARE SCHEMATIC IN NATURE AND ARE NOT 1.
WALL SPACE
CONCEALED IN OR ABOVE CEILING OR
SAME AS BRANCH CIRCUIT - EXCEPT
EL._89'-6"
FIN_FLR
C-C zjx-1404273-e001
2021-07-21T15:31:51-0400
ROBERT L BELTON
2021-07-26T10:01:58-0400
MICHAEL T L COX
ELECTRICAL DEMOLITION
ZJX-1404273-E101
lo tt e
POWER PANELS)
OF FIRST FLOOR. (LOCATION
FOR A DETAIL SECTIONAL
REFER TO SHEET E102
MECHANICAL ROOM - ELECTRICAL DEMOLITION
E102
DPE CKT 13, 15, 17
1"C-3#8 & 1#10 GND
#4 BC (TYP)
DPE CKT 8, 10, 12
DPD CKT 13, 15, 17
ALL TIMES. REFER TO DRAWING F101 AND F102.
THE EXISTING FIRE ALARM SYSTEM MUST REMAIN IN OPERATIONAL CONDITION AT7
CONDUIT, AND WIRING BACK TO SOURCE. REFER TO E601 FOR PANEL SCHEDULE.
DEMOLISH EXHAUST FAN EF-507, F-531 AND ASSOCIATED DISCONNECT SWITCH,6
WITH COR.
EXISTING POWER PANELS FOR AHU UNITS TO REMAIN. COORDINATE SHUTDOWN5
TO BUILDING STEEL.
DEMOLISH EXISTING GROUNDING AND BONDING CONNECTIONS FROM AHU HOUSING 4
DEMOLISH EXISTING CONDUIT AND WIRING FROM VFD OUTPUT TO AHU FAN MOTOR.3
CONNECTIONS BETWEEN ELECTRICAL EQUIPMENT.
ROUTE OF CONDUITS SHOWN ARE ILLUSTRATIVE AND INTENDED ONLY TO INDICATE2
TO SOURCE TO REMAIN FOR NEW WORK.
520 TO REMAIN. EXISTING WIRING BACK TO SOURCE AND EXISTING CONDUIT BACK
EXISTING VARIABLE FREQUENCY DRIVE W/ BYPASS PANEL FOR AHU-510, 515, AND1
zjx-1404273-e101
2021-07-21T15:32:20-0400
ROBERT L BELTON
2021-07-26T09:58:18-0400
MICHAEL T L COX
ELECTRICAL NEW WORK
ZJX-1404273-E102
NEW COVER
SWITCH
TRANSFER
MANUAL
PLN (E/G-5 CP)
ENGINE CONTROL
lo tt e
7 10
4 5
GND IN 1" RGS,
3 #6 AWG & 1 #10
DPE-8,10,12
NEW COVER
DPD-13,15,17
6 3
45 1
6 3
DPE-13,15,17
DPF
MCC E#6
MCC E#5
DPE
DPD
GLB1
GTA
GLB
(E /G
IN
KATOLIGHT ROOM
(E /G -6
E102 SCALE: 3/16" = 1'-0"
MECHANICAL ROOM - ELECTRICAL NEW WORK
E102 SCALE: 3/16" = 1'-0"
KATOLIGHT ROOM - 110
PVC SCH 40 1#2".
THIS THIS GROUNDING CONDUCTOR MUST BE ENCLOSED IN A ELECTRICAL
THE NATIONAL ELECTRICAL CODE (NEC) AND FAA STANDARD FAA-STD-019F
PROVIDE AND INSTALL GROUNDING ACCORDING TO THE LATEST EDITION OF
REPRESENTATIVE SPECIALIST.
VFD CONFIGURATION AND START-UP MUST BE ACCOMPLISHED BY A FACTORY
ON DRAWING E601.
MANUFACTURE, TYPE, AND AIC RATINGS, AS PER PANELBOARD SCHEDULES
PROVIDE NEW CIRCUIT BREAKER TO MATCH EXISTING PANELBOARD
WILL BE USED.
CONTRACTOR SHALL ADVISE FAA COR WHICH METHOD OF CONDUIT SUPPORT
UNISTRUT MOUNTS AND CONDUIT LINES ACCORDINGLY.
IF NECESSARY ADJUST VFD IN ORDER TO KEEP NEC CLEARANCES. ADJUSTED
REFER TO SHEET E601 FOR PANEL SCHEDULE INFORMATION OF EACH AHU.
PERFORM INSULATION RESISTANCE TEST ON ALL NEW CIRCUITS PROVIDED.
ABOVE 8' AFF TRANSITION CONDUIT TO RGS.
POWER CONDUIT TO BE IN RGS WHEN BELOW 8' ABOVE FINISHED FLOOR (AFF).
RESPECTIVE VFD.
USE EXISTING CONDUIT AND CONDUCTORS FROM THE SOURCE PANEL TO
MOUNTING SUPPORTS AS NEEDED.
USE EXISTING VARIABLE FREQUENCY DRIVE WITH BYPASS PANEL. MODIFY
THE AHU.
PROVIDE AND ROUTE NEW CONDUIT AND CONDUCTORS FROM THE VFD TO
GND IN 1" RGS
3 #6 AWG & 1 #10
GND IN 1" RGS
3 #8 AWG & 1 #10
zjx-1404273-e102
2021-07-21T15:28:32-0400
ROBERT L BELTON
2021-07-26T10:28:29-0400
MICHAEL T L COX
ELECTRICAL SCHEDULES
ZJX-1404273-E601
SPACE
SPARE
SECURITY LIGHTS
E/G-6 MCC
DAYTANK UNIT
E/G-5 MCC
DAYTANK UNIT
CHARGER 4DCB
E/G-6
JACKET WATER
HEATER
30kVA TRANSFORMER
E/G-5
JACKET WATER
HEATER
CHARGER 4DCA
AIR COMPRESSOR
PUMP P-23
AHU-510
UH-561 B & C
SURFACE MOUNTED
AHU-515
EF-581B
MAIN: MLO AT BOTTOM
FEEDER FROM MCC-C
A C
33 34
29 30
27 28
41 42
39 40
LOADLOAD
PANEL SCHEDULE
AHU-520
CKT
NO.
PHASE
BKR
SIZE
PANEL DPEPANEL DPD
FEEDER FROM MCC-A
A CB
LOAD LOAD
GTA & MANUAL
TRANSFER SWITCH
TVSS
PANEL GLB VIA
TRANSFER SWITCH
GTA & MANUAL
30kVA TRANSFORMER
PANEL GLB VIA
CRAC-1
CHARGER
BATTERY
5DCA
5DCB
BATTERY
CHARGER
(FOR REFERENCE ONLY) (FOR REFERENCE ONLY)
PANEL GLB
FEEDER FROM DPD
LOAD LOAD
(FOR REFERENCE ONLY)
SECURITY LIGHTS (3)
EXIT LIGHTS (6)
WATER COOLER RECPT.
FP&L RELAY
CRITICAL XFMR SUMP PUMP
SUMP PUMP EMH-H
SEC LIGHTS (MECH ROOM)
RECPT (6) ROOM 110
VIKING FIRE ALARM SYST
RECPT (6) MECH ROOM
EF-507
SUMP PUMP EWH-G
EF-510
RECPT (6) MECH ROOM
EF-509
FIRE ALARM CKT NOTIFIER
SECURITY LIGHTS (3)
SEC LIGHT(1-400W,2-150W)
RECPT (7) ROOM 110
RECPT (9) ROOM 109
RECPT (8) ROOM 109
PANEL GLB1
PANEL GLB
LOADLOAD
APMS CABINET
POWER BLDG DDCP-1
POWER BLDG DDCP-2
FUEL OIL FILTER
PCMS RECPT
EF-581A DAMPER MOTOR
SEC CAM DAYCARE POLE
DROP LIGHTS PCMS ROOM
LIGHTS
BLANK
APMS SERVER RECEPT
SECURITY ACP 4A
SECURITY EXP 4A
SECURITY SWITCH 5
FEEDER FROM GLB
(FOR REFERENCE ONLY)
EF-508 A&B HEATER
ROOM 107&108
:1 lo tt e
DEMOLISH THE EXISTING CIRCUIT AND RE-LABEL CIRCUIT BREAKER AS SPARE.
BREAKERS.
EXISTING PANELBOARDS ARE GE A-SERIES PANELBOARDS WITH THED HI-BREAK CIRCUIT
MANUFACTURER TYPE AND AIC RATINGS.
SCHEDULE, TO FEED NEW AHU 520. BREAKER SHALL MATCH EXISTING PANELBOARD
PROVIDE NEW CIRCUIT BREAKER, 30 AMP RATING AS INDICATED ON PANELBOARD
MATCH EXISTING PANELBOARD MANUFACTURER TYPE AND AIC RATINGS.
PROVIDE NEW CIRCUIT BREAKER, 60 AMP RATING TO FEED NEW AHU 515. BREAKER SHALL
MANUFACTURER TYPE AND AIC RATINGS.
SCHEDULE, TO FEED NEW AHU 510. BREAKER SHALL MATCH EXISTING PANELBOARD
PROVIDE NEW CIRCUIT BREAKER, 60 AMP RATING AS INDICATED ON PANELBOARD
ZJX-1404273-E601
2021-07-21T15:28:06-0400
ROBERT L BELTON
2021-07-26T10:27:53-0400
MICHAEL T L COX
FIRE ALARM
DETECTOR
SMOKE
SMOKE DETECTOR
FIRE ALARM SMOKE DETECTOR
FIRE ALARM DEMOLITION PLAN
ZJX-1404273-F101
-f
-f lo tt e
GENERAL NOTES
CONTRACTOR SHALL BE EST CERTIFIED. (EDWARD SYSTEM TECH).5.
WITH THE MAIN WORK SCHEDULE/ORDER TO MINIMIZE THE DOWNTIME.
CONTRACTOR SHALL COORDINATE THE WORK OF THE FIRE ALARM SYSTEMS4.
EACH AHU, DURING THE VFD REPLACEMENT.
DISCONNECT OR BYPASS THE ASSOCIATED DUCT SMOKE DETECTOR FOR
AT ALL TIMES CONTRACTOR SHALL COORDINATE WITH FAA/COR/ESU TO
THE EXISTING FIRE ALARM SYSTEM MUST REMAIN IN OPERATIONAL CONDITION3.
ALL FIRE CONDUIT MUST BE FACTORY RED.
THE CONTRACTOR SHALL VERIFY AND LABEL EACH FIRE WIRE AND CONDUIT. 2.
INDICATE CONNECTIONS BETWEEN ELECTRICAL DEVICES AND EQUIPMENT.
ROUTE OF CONDUITS SHOWN ARE ILLUSTRATIVE AND INTENDED ONLY TO 1.
SHEET NOTES
MECHANICAL ROOM - FIRE ALARM DEMOLITION
AHU 1
LOOP
AHUAHU
AHUAHU
EXISTING CONDUIT PENETRATION THROUGH-WALL FROM EG ROOM 110.5
CREATE NEW SPLICES.
REMOVE FIRE ALARM WIRE WITH INTENTION TO RE-USE. DO NOT CUT AND 4
DEMOLISH EXISTING FIRE ALARM CONDUIT WHIP TO VFD.3
DEMOLISH EXISTING FIRE ALARM CONDUIT THAT PERIMETERS AHU.2
AHU-510, 515, AND 520.
DEMOLISH EXISTING SUPPLY AND RETURN DUCT SMOKE DETECTORS FOR 1
FIRE ALARM LOOP
zjx-1404273-f101
2021-07-21T15:27:42-0400
ROBERT L BELTON
2021-07-26T10:26:16-0400
MICHAEL T L COX
ZJX-1404273-F102
FIRE ALARM INSTALLATION PLAN
-f
-f lo tt e
GENERAL NOTES:
MECHANICAL ROOM - NEW WORK, FIRE ALARM SYSTEM
CONTRACTOR SHALL BE EST CERTIFIED. (EDWARD SYSTEM TECH).5.
WITH THE MAIN WORK SCHEDULE/ORDER TO MINIMIZE THE DOWNTIME.
CONTRACTOR SHALL COORDINATE THE WORK OF THE FIRE ALARM SYSTEMS4.
EACH AHU, DURING THE VFD REPLACEMENT.
DISCONNECT OR BYPASS THE ASSOCIATED DUCT SMOKE DETECTOR FOR
AT ALL TIMES CONTRACTOR SHALL COORDINATE WITH FAA/COR/ESU TO
THE EXISTING FIRE ALARM SYSTEM MUST REMAIN IN OPERATIONAL CONDITION 3.
ALL FIRE CONDUIT MUST BE COLOR FACTORY RED.
THE CONTRACTOR SHALL VERIFY AND LABEL EACH FIRE WIRE AND CONDUIT. 2.
INDICATE CONNECTIONS BETWEEN ELECTRICAL DEVICES AND EQUIPMENT.
ROUTE OF CONDUITS SHOWN ARE ILLUSTRATIVE AND INTENDED ONLY TO 1.
AHU AND MUST NOT INTERFERE WITH ANY ACCESS DOORS OR CONTROLS.
NEW CONDUIT FOR FIRE ALARM SYSTEM MUST BE ROUTED TO FIT EACH NEW 5
THIS SECTION OF CONDUIT MUST BE CEILING HEIGHT TO NOT BLOCK PATHWAY.4
PROVIDE NEW FIRE ALARM CONDUIT WHIPS TO NEW VFD.3
PERIMETERS EACH AHU.
PROVIDE AND ROUTE FIRE ALARM WIRING AND 3/4 " EMT CONDUIT THAT 2
PROVIDE NEW DUCT SMOKE DETECTORS FOR AHU 510, 515, AND 520.1
zjx-1404273-f102
2021-07-21T15:33:04-0400
ROBERT L BELTON
2021-07-26T10:25:40-0400
MICHAEL T L COX
COVER SHEET AND LOCATION MAP
ZJX-1404273-G001
-g lo tt e
LOCATION MAP
NOT TO SCALE
LOCATION
PROJECT
GEORGIA
FLORIDA
IV
NASSAU
RIVER
5A
AIA
T 23
CALLAHAN
DUVAL
HILLIARD
FOLKSTON
NASSAU
JACKSONVILLE
INTERNATIONAL
AIRPORT
I 9
T OF TRANSPO
T A
IC
OF
STATES
IT
TM
EN
AVIA
LAR
TRAT
SI
NI
ZJX/ARTCC - HILLARD, FLORIDA
SCALES SHOWN FOR 22X34 SHEETS ADJUST SCALES FOR OTHER SIZES
zjx-1404273-g001
2021-07-21T15:26:23-0400
ROBERT L BELTON
2021-07-26T10:25:04-0400
MICHAEL T L COX
DRAWING INDEX AND GENERAL NOTES
ZJX-1404273-G002
lo tt e
GENERAL NOTES DRAWING LIST
DESCRIPTIONDATEREV.DRAWING NO.
ARE SPECIFIC FOR THE AIR TRAFFIC OPERATIONS.
GROUNDING, SPLICING, TERMINATION, BONDING, AND INSTALLATION OF THE ELECTRICAL SYSTEMS THAT
SET BY THIS STANDARD. THE FAA'S ELECTRICAL STANDARDS INCLUDE SPECIFIC REQUIREMENTS FOR
COPY OF THE FAA'S STANDARDS FOR ELECTRICAL WORK AND SHALL COMPLY WITH ALL THE REQUIREMENTS
SMACNA, THE NATIONAL INSULATION STANDARD, AND FAA ORDERS. THE CONTRACTOR SHALL OBTAIN A
AND ARE NOT LIMITED TO THE LATEST EDITIONS OF THE INTERNATIONAL BUILDING CODE, NFPA, ASHRAE, CODES, STANDARDS, AND REGULATIONS. APPLICABLE CODES AND STANDARDS FOR THIS PROJECT INCLUDE
AS A MINIMUM, THE CONTRACTOR SHALL COMPLY WITH ALL FEDERAL, STATE, AND LOCAL LAWS, 11.
CONSTRUCTION PHASE OF THIS PROJECT.
TO MEET ALL FAA ORDERS, FEDERAL, STATES, AND LOCAL CODES AND ORDINANCES DURING THE
APPLICABLE CODES AND STANDARDS OF THE INDUSTRY. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY
THE CONTRACTOR OF THIS PROJECT SHALL BE QUALIFIED AND FULLY KNOWLEDGEABLE OF THE 10.
WITH THE PLANS AND SPECIFICATIONS.
ALL CONSTRUCTION SHALL BE DONE IN A NEAT AND WORKMANLIKE MANNER IN ACCORDANCE 9.
DRAWINGS.
COR SHALL STOP WORK ACTIVITIES IF FIELD WORK DEVIATES FROM THE APPROVED COORDINATION
APPROVED BY THE COR PRIOR TO INSTALLATION AND SHALL USE THESE TO DICTATE THE FIELD WORK. THE
ACTUAL FIELD CONDITIONS. THE CONTRACTOR SHALL ENSURE THE COORDINATION DRAWINGS ARE
COORDINATION DRAWINGS ANY DEVIATION FROM THE DESIGN TO FIT THE NEW INSTALLATION TO THE
THE NEW EQUIPMENT AND COMPONENTS WITHIN THE SPACE AND THE BUILDING ELEMENTS. INDICATE IN THE
COORDINATION DRAWINGS SHALL INDICATE DIMENSIONS, DISTANCES, AND ELEVATIONS THAT RELATE TO
THE CONTRACTOR SHALL SUBMIT COORDINATION DRAWINGS FOR THE APPROVAL OF THE COR. 9.
SITE ONCE APPROVED BY THE COR AND AT NO ADDITIONAL COST TO THE FAA.
OR MODIFY EQUIPMENT LOCATIONS AND ROUTING OF UTILITIES TO FIT THE CONDITIONS ENCOUNTERED ON
THE CONTRACTOR SHALL BE RESPONSIBLE TO FIELD VERIFY THE EXACT CONDITIONS ON SITE TO ADJUST, 8.
COORDINATED WITH THE COR AT LEAST 10 DAYS IN ADVANCE.
WORK REQUIRING PERMANENT, TEMPORARY, OR PARTIAL ELECTRICAL/WATER OUTAGES MUST BE 7.
(DE-ENERGIZE) OR CLOSE (ENERGIZE) ANY CIRCUIT BREAKER AT ANY TIME.
ONLY FAA PERSONNEL MAY OPERATE CIRCUIT BREAKERS, THE CONTRACTOR SHALL NOT OPEN 6.
COORDINATED WITH THE COR AT LEAST 10 DAYS IN ADVANCE.
WORK REQUIRING PERMANENT, TEMPORARY OR PARTIAL ELECTRICAL / WATER OUTAGES MUST BE 5.
VALVE AT ANY TIME.
ONLY FAA PERSONNEL MAY OPERATE VALVES. THE CONTRACTOR SHALL NOT OPEN OR CLOSE ANY 4.
OR ENERGIZE ANY CIRCUIT BREAKER AT ANY TIME.
ONLY FAA PERSONNEL MAY OPERATE CIRCUIT BREAKERS. THE CONTRACTOR SHALL NOT DE-ENERGIZE 3.
AND/OR LOSS OF LIFE.
CONTROL CENTER (ARTCC) AND UNAUTHORIZED OUTAGES OF UTILITY SERVICES MAY CAUSE ACCIDENTS
(ELECTRICAL, MECHANICAL, OR PLUMBING). THIS FACILITY IS AN OPERATIONAL AIR ROUTE TRAFFIC
EXTREME CAUTION MUST BE PRACTICED WHEN WORKING ON ANY OF THE BUILDING UTILITIES 2.
SITE CONDITIONS, EQUIPMENT AND MATERIAL SUPPLIERS.
RESPONSIBILITY OF THE CONTRACTOR TO VERIFY AND CONFIRM ALL INFORMATION PROVIDED HERE WITH
POSSIBLE CONDITIONS TO BE ENCOUNTERED DURING THE CONSTRUCTION PROCESS. IT IS THE
THESE CONTRACT DRAWINGS ARE SCHEMATIC IN NATURE AND ARE NOT INTENDED TO SHOW ALL 1.
ZJX-1404273-F102
ZJX-1404273-F101
ZJX-1404273-E601
ZJX-1404273-E102
ZJX-1404273-E101
ZJX-1404273-E001
ZJX-1404273-M604
ZJX-1404273-M603
ZJX-1404273-M602
ZJX-1404273-M601
ZJX-1404273-M502
ZJX-1404273-M501
ZJX-1404273-M302
ZJX-1404273-M301
ZJX-1404273-M101
ZJX-1404273-A101
ZJX-1404273-D101
ZJX-1404273-G004
ZJX-1404273-G003
ZJX-1404273-G002
ZJX-1404273-G001
FIRE ALARM INSTALLATION PLAN
FIRE ALARM DEMOLITION PLAN
ELECTRICAL SCHEDULES
ELECTRICAL NEW WORK
ELECTRICAL DEMOLITION
ELECTRICAL SYMBOLS
SEQUENCE OF OPERATIONS
MECHANICAL SCHEDULES
AIRFLOW DIAGRAM AHU 520
AIRFLOW DIAGRAM AHU 510/515
CHILLED WATER SYSTEM DETAILS
MECHANICAL DETAILS
SECTION HVAC
SECTION VIEW
MECHANICAL FLOOR PLAN
ARCHITECTURAL ELEVATIONS
MECHANICAL DEMOLITION
CONSTRUCTION STAGING PLAN
ABBREVIATIONS AND LEGENDS
DRAWING INDEX AND GENERAL NOTES
COVER SHEET AND LOCATION MAP
05/04/2021 zjx-1404273-g002
2021-07-21T15:25:49-0400
ROBERT L BELTON
2021-07-26T10:23:46-0400
MICHAEL T L COX
ABBREVIATIONS AND LEGENDS
ZJX-1404273-G003
lo tt e
STANDARD ABBREVIATIONS
CONSTRUCTION SEQUENCE
BREAK LINES
ELEVATION SYMBOL
DETAIL TITLE REFERENCE
SECTION TITLE REFERENCE
DETAIL NUMBER
SECTION CUT
ELEVATION REFERENCE
NORTH ARROW
PARTIAL SECTION CUT
MATCH LINE SYMBOL
COLUMN LINE GRID DESIGNATION
ROOM NAME & NUMBER
EXISTING WORK, UON
NEW WORK, UON
ELEVATION SYMBOL (PLANS)
GRAPHIC SCALE
ELEVATION DESIGNATION
FLOOR EL. 10.50'
GATE VALVE
GLOBE VALVE
BALL VALVE
GLV
BV
GV
CHECK VALVE
UNION
PRESSURE REDUCING VALVE
CV
PRV
EXISTING WORK TO BE REMOVED
EXISTING WORK TO REMAIN
NEW WORK
GENERAL LEGEND
SECTION IS DRAWN
ABOVE OR BEYOND
OUTLINE OF OBJECT
CONTRACTOR, UON
DEMOLITION BY
IS DRAWN OR SCHEDULED
SHEET ON WHICH DETAIL
ELEVATION IS DRAWN
MECHANICAL LEGEND
CHILLED WATER SUPPLY
CHILLED WATER RETURN
FLUID FLOW DIRECTION
CWS
CWR
MOTOR OPERATED CONTROL VALVE
STRAINER WITH BLOWDOWN VALVE
IDENTIFYING NUMBER
EQUIPMENT DESIGNATION SYMBOL
SUPPLY AIRSA
RETURN AIRRA
4' 8'04'
ENERGY VALVE
ELECTRIC MOTOR ACTUATOR
EV
SM_
DP-1
3 IN A CONDUIT
CROSS MARKS DENOTE NUMBER OF WIRES WHEN THERE ARE MORE THAN
PLATE (UON)
JUNCTION BOX- WALL MOUNTED AT HEIGHT INDICATED WITH BLANK COVER
CONDUIT DOWN
CONDUIT UP
PLATE (UON)
JUNCTION BOX ABOVE CEILING OR BELOW RAISED FLOOR WITH BLANK COVER
MOUNTING HEIGHTS SHOWN WITH SYMBOL TO CENTER OF DEVICE UON
SEPARATED BY COMAS INDICATE MULTIPLE POLE BREAKERS.
NUMBER INDICATE THE CIRCUIT LOCATION IN THE PANEL. NUMBERS
HOMERUN TO PANELBOARD. LETTERS INDICATE PANEL DESIGNATION AND
OR WALL SPACE
SAME AS BRANCH CIRCUIT - EXCEPT CONCEALED IN OR ABOVE CEILING
+90"
UON
BRANCH CIRCUIT- EXPOSED, 3/4" C, WITH 3#12 WIRES PLUS 1#12 GROUND,
GROUND, UON.
FLEXIBLE METALLIC CONDUIT EXPOSED WITH 2#12 WIRES PLUS 1#12
VARIABLE FREQUENCY DRIVE
ELECTRICAL PANELBOARD
MANUAL MOTOR STARTER SWITCH
ELECTRICAL LEGEND
4'
X001
X001
POINT OF CONNECTION - NEW TO EXISTING
POINT OF TERMINATION OF DEMOLITION
TURNING VANE
CONNECTION
FLEX DUCT
F-531
507 AND REPAIR WALL OPENINGS ORIGINALLY USED WITH EF-19.
CONDUCTORSDEMOLISH EF-507 AND F-531 AND ASSOCIATED 18.
REINSTALL SECOND FLOOR REMOVABLE PANEL17.
INSTALL NEW RESINOUS FLOORING IN SECOND FLOOR 16.
CLEAN FLOORS15.
DAYS FOLLOWING REPAIRS.
UNIT WILL BE REQUIRED TO OPERATE FOR 5 CONSECUTIVE
DURATION OF THE PROVING PERIOD WILL BE RESET AND THE
PERIOD. IN THE EVENT OF EQUIPMENT FAILURE THE
PROVING AHU-520 STARTUP AND BEGINNING OF 5-DAY 14.
AND CONTROLS
SENSORS, INSTALL NEW AHU-520 INCLUDING ALL DUCTWORK, 13.
EQUIPMENT PAD.INSTALL EPOXY RESIN COATING TO AHU-520 12.
DUCTWORKDEMOLISH EXISTING AHU-520 AND ASSOCIATED 11.
PRIOR TO BEGINNING WORK ON AHU-520
A-SIDE COORDINATE BUILDING POWER SUPPLY CUTOVER TO 10.
NOR AHU-510/510 PROVING PERIODS.
WILL NOT OCCUR CONCURRENTLY WITH AHU-510/515 WORK
CONSECUTIVE DAYS FOLLOWING REPAIRS. AHU-520 WORK
RESET AND THE UNIT WILL BE REQUIRED TO OPERATE FOR 5
FAILURE THE DURATION OF THE PROVING PERIOD WILL
PERIOD. IN THE EVENT OF EQUIPMENT MALFUNCTION OR
PROVING AHU-515 STARTUP AND BEGINNING OF 5-DAY 9.
SENSORS, INSTALL NEW AHU-515 INCLUDING ALL DUCTWORK, 8.
EQUIPMENT PADINSTALL EPOXY RESIN COATING TO AHU-515 7.
DUCTWORKDEMOLISH EXISTING AHU-515 AND ASSOCIATED 6.
NOR AHU-510/510 PROVING PERIODS.
WILL NOT OCCUR CONCURRENTLY WITH AHU-510/515 WORK
CONSECUTIVE DAYS FOLLOWING REPAIRS. AHU-520 WORK
RESET AND THE UNIT WILL BE REQUIRED TO OPERATE FOR 5
FAILURE THE DURATION OF THE PROVING PERIOD WILL BE
PERIOD. IN THE EVENT OF EQUIPMENT MALFUNCTION OR
PROVING AHU-510 STARTUP AND BEGINNING OF 5-DAY 5.
SENSORS, INSTALL NEW AHU-510 INCLUDING ALL DUCTWORK, 4.
EQUIPMENT PADINSTALL EPOXY RESIN COATING TO AHU-510 3.
DUCTWORKDEMOLISH EXISTING AHU-510 AND ASSOCIATED 2.
REMOVE SECOND FLOOR EXTERIOR REMOVABLE PANEL1.
POUNDS PER SQUARE INCHPSI
PRESSURE SENSORPS
PRESSURE REDUCING VALVEPRV
POINT OF CONNECTIONPOC
PRESSURE INDICATORPI
PHASEPH
OUTSIDE DIAMETEROD
OUTSIDE AIROA
NOT TO SCALENTS
NATIONAL PIPE THREADNPT
NOMINALNOM
NORMALLY OPENNO
NOT IN CONTRACTNIC
NORMALLY CLOSEDNC
MANUAL MOTOR PROTECTION MMP
MINIMUMMIN
MANUFACTURERMFG
MOTOR CONTROL CENTERMCC
1000 BTU PER HOURMBH
MAXIMUMMAX
MANUAL AIR VENT MAV
LEAVING WATER TEMPERATURELWT
POUNDSLBS
LEAVING AIR TEMPERATURELAT
KILOWATTSKW
KILOVOLT AMPEREKVA
JUNCTION BOXJB
INVERTINV
INCHIN
INSIDE DIAMETERID
HERTZHZ
HUMIDITY SENSORHS
HOURHR
HORSE POWERHP
HORIZONTALHORIZ
GATE VALVEGV
GALLONS PER MINUTEGPM
GROUNDGND
GROUND FAULT INTERRUPTERGFI
GALVANIZEDGALV
GAUGEGA
FEETFT
FEET PER MINUTEFPM
FLOW METER/SENSORFM
FLANGEFLG
FINISHED FLOOR ELEVATIONFFE
FIRE/SMOKE DAMPERFD/SD
FIRE DAMPER OR FLOOR DRAINFD
FLOW CONTROL VALVEFCV
ENTERING WATER TEMPERATUREEWT
ENERGY VALVEEV
ELECTRICAL METAL TUBINGEMT
ELECTRIC/ELECTRICALELEC
ELEVATIONELEV
EXHAUST FANEF
ENTERING AIR TEMPERATUREEAT
DP SENSORDPS
DIFFERENTIAL PRESSURE TRANSMITTERDPT
DIFFERENTIAL PRESSURE INDICATORDPI
DIFFERENTIAL PRESSUREDP
DIGITAL OUTPUTDO
DOWNDN
DISCONNECTDISC
DIAMETERDIA
DIRECT DIGITAL CONTROLDDC
DIRECT CURRENTDC
DOUBLEDBL
DRY BULB TEMPERATUREDB
DRAIND
CHILLED WATER SUPPLYCWS
CHILLED WATER RETURNCWR
CHILLED WATERCW
CONDENSING UNITCU
CONTRACT STARTS HERECSH
TECHNICAL REPRESENTATIVE
CONTRACTING OFFICERSCOR
CONTINUOUSCONT
CONDENSATECOND
CONCRETECONC
COLUMNCOL
CLEAN OUTCO
CENTER LINECL
CIRCUITCKT
CIRCULATINGCIRC
CAST IN PLACECIP
CUBIC FEET PER MINUTECFM
CONDENSATE DRAINCD
COOLING COILCC
BALL VALVEBV
BTU PER HOURBTUH
BRITISH THERMAL UNITBTU
BOTTOMBOTT
BOTTOM OF PIPEBOP
BOTTOM OF DUCTBOD
BREAKERBKR
BUTTERFLY VALVEBFV
BLIND FLANGEBF
AMERICAN WIRE GAUGEAWG
APPROXIMATELYAPROX
ANALOG OUTPUTAO
AIR HANDLING UNIT AHU
AIR FLOW METER/SENSORAFM
ABOVE FINISHED FLOOR AFF
ACCESS DOORAD
ALTERNATING CURRENTAC
AMPA
TRANSFORMERXFMR
TRANSFERXFER
WITHOUTW/O
WATER COLUMNWC
WET BULB TEMPERATUREWB
WITHW/
WATTSW
VERTICALVERT
VOLUME DAMPERVD
VOLTSV
UNLESS NOTED OTHERWISEUNO
TYPICALTYP
TEMPERATURE TRANSMITTERTT
TEMPERATURE SENSORTS
TOP OF PIPETOP
TOP OF DUCTTOD
TEMPERATURE INDICATORTI
TEMPERATURETEMP
THERMOSTATT
STRUCTURESTR
STANDARDSTD
SPECIFICATIONSSPEC
SUPPLY FANSF
SCHEDULESCH
SUPPLY AIRSA
REVOLUTIONS PER MINUTERPM
RIGID GALVANIZED STEELRGS
REVISION OR REVERSEREV
REQUIREDREQ'D
REINFORCINGREINF
REGISTERREG
RECEPTACLEREC
RETURN AIRRA
RADIUSR
SYMBOL ABBREVIATION DESCRIPTION
zjx-1404273-g003
2021-07-21T15:25:14-0400
ROBERT L BELTON
2021-07-26T10:22:49-0400
MICHAEL T L COX
STAGING AREA
CONTRACTOR'S
PARKING AREA
PERSONNEL
CONTRACTOR'S
VISITOR PARKING
ENTRANCE
GUARDHOUSE
ZJX-1404273-G004
UP
lo tt e
GENERAL NOTES:
E.1 CONTRACTOR TO PROVIDE PORTABLE TOILETS
CONSTRUCTION TOILET FACILITIESE.
BY COR IN WRITING, A MINIMUM OF 10 WORKING DAYS BEFORE THE PERFORMANCE OF THE WORK.
ALLOWED ONLY AT PREARRANGED TIMES APPROVED BY COR. SCHEDULE, COORDINATE AND HAVE APPROVAL
D.6 CONCRETE SAWING, CORE DRILLING, CONCRETE DEMOLITION AND ANCHOR DRILLING SHALL BE
CONDITIONS AT THE CONCLUSION OF THE PROJECT.
CONCLUSION OF THE PROJECT WHEN ALL CONSTRUCTION IS COMPLETE. THE STAGING AREA MUST BE RESTORED TO ORIGINAL
D.5 ALL DEBRIS MUST BE REMOVED FROM SITE BY CONTRACTOR. ENTIRE STAGING AREA MUST BE CLEANED AT THE
LOOSE DEBRIS MUST BE SECURED OR DISPOSED DAILY.
AREA. THE AREAS AROUND THE DUMPSTERS MUST BE KEPT CLEAN AND FREE OF EXCESS DEBRIS DURING CONSTRUCTION.
D.4 DUMPSTERS FOR DISPOSAL OF CONSTRUCTION WASTE MUST BE PROVIDED BY THE CONTRACTOR WITHIN THE STAGING
PERFORMANCE OF WORK. CONTRACTOR MUST NOT DIG WITHOUT WRITTEN PERMISSION OF THE COR.
OR PARTIAL OUTAGES MUST BE SCHEDULED AND APPROVED IN WRITING BY COR AT LEAST 10 WORKING DAYS IN ADVANCE OF
ELECTRICAL ROOMS. UNSCHEDULED INTERRUPTIONS SHALL NOT BE TOLERATED. WORK REQUIRING PERMANENT, TEMPORARY, D.3 THE CONTRACTOR MUST USE GREAT CARE AND CAUTION WHILE WORKING WITHIN THE EXISTING MECHANICAL AND
PM TO 6:00 AM OR AS APPROVED BY COR.
OTHER FAA/GOVERNMENT EQUIPMENT. WORK ON CRITICAL EQUIPMENT MUST BE ACCOMPLISHED DURING OFF-HOURS OF 11:00
COR LOCATION OF CRITICAL EQUIPMENT THAT MAY BE AFFECTED BY THE WORK AND PROCEDURES TO PROTECT THIS AND
D.2 FAA HAS AND MAINTAINS EQUIPMENT THAT IS CRITICAL TO ITS OPERATION THROUGHOUT THIS FACILITY. COORDINATE WITH
BE REQUIRED TO BE SCHEDULED DURING OFF-REGULAR HOURS 11:00 P.M. TO 6:00 A.M.
NOTICE IN ADVANCE OF PERFORMANCE OF WORK. WORK ACTIVITIES THAT MAY DISRUPT THE OPERATION OF THE BUILDING MAY
THE BUILDING MUST BE SCHEDULED, COORDINATED AND SUBMITTED FOR APPROVAL TO THE COR WITH A MINIMUM OF 10 DAYS
CONSTRUCTION NOISE MUST BE MINIMIZED BETWEEN 6:00 AM TO 11:00 PM.DEMOLITION AND CONSTRUCTION INSIDE OR OUTSIDE
COORDINATE CONSTRUCTION ACTIVITY SO AS NOT TO INTERFERE WITH FUNCTIONS OF THE ARTCC. DEMOLITION AND
D.1 ARTCC IS A 24 HOUR 7 DAY PER WEEK OPERATING FACILITY. IT WILL BE NECESSARY TO
DEMOLITION AND CONSTRUCTIOND.
TIMES.
C.2 THIS SITE IS A SECURE AREA AND ALL CONSTRUCTION PERSONNEL MUST REMAIN IN THE CONSTRUCTION AREAS AT ALL
PHOTO ID TO SIGN IN. ALL PERSONNEL MUST BE U.S. CITIZENS.
CONSTRUCTION EMPLOYEE MUST CHECK IN AND OUT AT THE MAIN SECURITY GATE AND WILL NEED A GOVERNMENT ISSUED
BADGES WILL BE ISSUED TO EACH INDIVIDUAL. ALL DELIVERIES MUST BE SCHEDULED IN ADVANCE WITH COR. EACH
C.1 A LIST OF CONSTRUCTION PERSONNEL MUST BE PROVIDED TO THE COR AT LEAST 24 HOURS IN ADVANCE. TEMPORARY DAILY
FAA SECURITY REQUIREMENTSC.
CONSTRUCTION MATERIALS.
NEATLY STORED AND PROTECTED AT ALL TIMES. A TEMPORARY CONSTRUCTION FENCE MUST BE INSTALLED SURROUNDING
B.3 STORAGE OF CONSTRUCTION MATERIAL MUST BE LIMITED TO THE CONSTRUCTION STAGING AREA. MATERIALS MUST BE
THE CONTRACTOR.
LOCATION OF THE OFFICE TRAILER WILL BE LIMITED TO THE CONTRACTOR STAGING AREA. ALL UTILITIES MUST BE PROVIDED BY
B.2 CONTRACTOR JOB OFFICE TRAILER, IF DESIRED BY THE CONTRACTOR, WILL BE PROVIDED BY THE CONTRACTOR. THE
PARKING, IF NECESSARY, MUST BE COORDINATED WITH THE COR.
B.1 CONTRACTOR'S PERSONNEL PARKING MUST BE LIMITED TO THE INDICATED CONTRACTOR PARKING AREA. ADDITIONAL
CONTRACTOR STAGINGB.
A.4 CONTRACTOR AND EMPLOYEES MUST BE ESCORTED AT ALL TIMES BY BADGED PERSONNEL.
THE CONSTRUCTION AREAS.
A.3 PROVIDE NECESSARY BARRICADES, LIGHTS, SIGNAGE AND FENCING TO PROTECT, WARN AND DIRECT ALL PERSONS NEAR
FAA SHIFT CHANGES OCCUR FROM 6:30 A.M. TO 8:00 A.M. AND FROM 2:00 P.M. TO 4:00 P.M.
A.2 ALL DELIVERIES SHOULD BE SCHEDULED AT TIMES OTHER THAN THE FAA EMPLOYEE SHIFT CHANES TO AVOID CONGESTION.
A.1 CONTRACTOR'S VEHICLES. PEDESTRIANS AND ALL DELIVERIES TO SITE SHALL BE THROUGH THE GUARDHOUSE.
CONSTRUCTION ACCESSA.
HAS THE SAME GENERAL REQUIREMENTS AND SITE CONDITIONS MAY PRECLUDE THE VARIOUS ALLOWANCES LISTED BELOW.
COORDINATED WITH SITE PERSONNEL (VIA COR): PARTICULARLY IN CONJUNCTION WITH ONGOING PROJECTS. EACH PROJECT
CONTRACTORS PARKING. CONSTRUCTION OFFICES AND THE EXTENT/SIZE OF THE CONSTRUCTION STAGING AREA MUST BE
1 REQUIREMENTS AND ARE NOT INTENDED TO MODIFY OR REPLACE ANY DIVISION 1 REQUIREMENTS. CONSTRUCTION ACCESS, REQUIREMENTS STATED IN "DIVISION 1-GENERAL REQUIREMENT" OF THE SPECIFICATIONS. THESE NOTES PARAPHRASE DIVISION
THE FOLLOWING NOTES AND ACCOMPANYING "CONSTRUCTION STAGING PLAN" GRAPHICALLY REPRESENT MANY OF THE MAJOR
CONSTRUCTION STAGING PLAN NOTES
SHALL NOT BE PERMITTED IN FAA OCCUPIED AREAS UNLESS APPROVED IN WRITING BY COR.
G.2 NO WELDING EQUIPMENT SHALL BE POWERED BY THE FACILITY ELECTRICAL SYSTEM. WELDING
OR CLOSE (ENERGIZE) ANY CIRCUIT BREAKER AT ANY TIME.
IN ADVANCE AND IN WRITING FOR EACH CASE OF BREAKER OPERATION. DO NOT OPEN (DE-ENERGIZE)
PERFORMANCE OF WORK. ONLY FAA PERSONNEL MAY OPERATE CIRCUIT BREAKERS. REQUEST PERMISSION OF FAA
AND HAVE APPROVAL IN WRITING BY COR WITH A MINIMUM OF 10 WORKING DAYS NOTICE IN ADVANCE OF
PREPARATORY WORK MUST BE COMPLETED PRIOR TO SHUTDOWN AND SWITCHOVER. SCHEDULE, COORDINATE
ONLY FAA MAY SHUT OFF MECHANICAL VALVES, COORDINATE SHUTTING OFF VALVES WITH COR.
DURING OFF-HOURS AS INDICATED IN NOTE D.2 THIS SHEET UNDER DEMOLITION AND CONSTRUCTION HOURS.
DRILLING. SHUTDOWNS AND SWITCHOVERS OF MECHANICAL AND ELECTRICAL SYSTEMS SHALL BE ACCOMPLISHED
BUT NOT LIMITED TO, DAMAGE CAUSED BY IMPACT, WATER, DEBRIS AND DUST, INCLUDING CORE
G.1 PROTECT NEW AND EXISTING FAA EQUIPMENT, BOTH INSIDE AND OUTSIDE BUILDING, FROM DAMAGE, INCLUDING
EQUIPMENT PROTECTIONG.
SATISFACTION OF COR.
F.2 DISTURBED LAWNS AND LANDSCAPING MUST BE RESTORED TO ORIGINAL CONDITION TO THE
ORIGINAL CONDITION, INCLUDING STRIPING OF PARKING LOT.
F.1 UPON COMPLETION OF WORK, REPAIR PAVED SURFACES AFFECTED BY THE WORK TO
PARKING LOT AND DRIVEWAY REPAIRF.
SCALE: 1" = 800'
800' 1600'0800'
COUNTY ROAD 108
ASB NCO
PSB
WORK
AREA OF
ZJX
ASPHALT PARKING
zjx-1404273-g004
2021-07-21T15:24:02-0400
ROBERT L BELTON
2021-07-26T10:19:56-0400
MICHAEL T L COX
ZJX-1404273-M101
MECHANICAL FLOOR PLAN
lo tt e
WITH COR.
WITH LEAD FREE PAINT AS SPECIFIED. COORDINATE COLOR SELECTION
STEEL. PREPARE SURFACE AND ENCAPSULATE FIRMLY BONDED PAINT
REMOVE ALL LOOSE FLAKING PAINT FROM CEILING AND SUPPORT
REGARDING REMOVAL OF LEAD BASED AND LEAD CONTAINING PAINT,
ROOM FOR LEAD. IN ACCORDANCE WITH OSHA GUIDELINES
TEST PEELING PAINT ON CEILING AND SUPPORT STEEL OF MECHANICAL
COATING.
PREPARE AND COAT ENTIRE FLOOR WITH TRAFFIC RATED EPOXY
IN MECHANICAL ROOM 201.
PROVIDE INSULATION AND JACKETING FOR ALL CHILLED WATER PIPING
OBSTRUCTION.
COMPLETE REMOVAL OF COOLING COILS FROM AHUS WITHOUT
COORDINATE EQUIPMENT AND PIPING LOCATIONS TO ALLOW FOR
REQUIRED ATTACHMENT MATERIALS.
RECOMMENDED INSTALLATION PROCEDURES INCLUDING ANY
EXISTING WALL PANELS. CONFORM WITH MANUFACTURER'S
MATCH THE MATERIAL GAUGE, COLOR, FINISH, AND PATTERN OF
REPAIR EF-507 AND F-531 OPENINGS WITH INSULATED PANELS TO
DOORS,
PROVIDE NEW CURTAIN STYLE FIRE DAMPERS IN WALL WITH ACCESS
COOLING OF MECHANICAL ROOM.
PROVIDE 12"X24" RETURN GRILL WITH MANUAL DAMPER CONTROL FOR
FOR COOLING OF MECHANICAL ROOM.
PROVIDE 12"X24" SUPPLY REGISTER WITH MANUAL…
This is the start of the file's text. The full file is on GovTribe.