YTPM 22-0004 JA Brand Name or Equal - Hangar 3 REDACTED.pdf
PDF 605 KB Posted
- Attached to
- Repair Barrel Roof, Hangar 3 Bldg 7075
- Solicitation number
- FA660626R0005
About this file
This is a Justification and Approval (J&A) document for a sole-source procurement under Other Than Full and Open Competition authority. The 439th Airlift Wing Contracting Flight at Westover Air Reserve Base in Chicopee, Massachusetts intends to award a firm-fixed-price contract in late spring 2026 for the Guardian CB-Hybrid Permanent Horizontal Lifeline Fall Protection System. The acquisition is classified as an Individual J&A with a dollar value under $750,000 and falls under DAFFARS 5302.101 authority citing 10 USC 3204(a)(1) for a sole-source acquisition where only one responsible source can satisfy agency requirements. The program involves replacement of the existing roof and installation of the new fall protection system on Hangar 3 with an estimated Period of Performance of 365 days.
The justification demonstrates that the Guardian CB-Hybrid system was selected based on proven performance, compatibility, and support for operational safety requirements, with brand name components representing approximately 3% of the overall construction project cost. The document notes that Westover ARB has already installed this system on several facility rooftops, and continuing with this system ensures consistent installation practices, eliminates custom engineering needs, and supports uniform system interoperability base-wide. Market research conducted under FAR Part 10 indicated an adequate number of businesses can perform the acquisition, and the Contracting Officer was granted permission for full and open acquisition by the SBA. The subsequent roof repair solicitation will be issued as a competitive Request for Proposal with full and open competition and small business subcontracting requirements, allowing potential suppliers to propose compatible products for consideration. The document was coordinated on February 20, 2026 and approved by the Chief of the Contracting Office on February 24, 2026.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification and Approval (J&A) for Other Than Full and Open Competition
Security Marking (select from the drop-down list)
August 2023 Security Marking (select from the drop-down list) Page 3 of 3August 2023 Security Marking (select from the drop-down list) Page 3 of 3 to determine that the estimated cost to the Government will be fair and reasonable.
VII. Description of the market research conducted and the results, or a statement of the reasons market research was not conducted.
Market research conducted IAW FAR Part 10 indicated there is an adequate number of businesses who can perform this acquisition. Contracting Officer was granted permission for full and open acquisition by the SBA.
VIII. Any other facts supporting the use of Other Than Full and Open Competition.
IAW FAR (RFO) 11.204(a)(1) The particular brand name, product, or feature is essential to the Government’s requirements, and market research indicates other companies’ similar products, or products lacking the particular feature, do not meet, or cannot be modified to meet the agency’s needs.
IX. List of any sources that expressed, in writing, an interest in the acquisition.
N/A new acquisition
X. A statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisitions for the supplies or services required.
The solicitation for the roof repair project will be a competitive Request for Proposal (RFP) project is being offered as a Full and Open Competition with Subcontracting to Small Businesses. The brand name components represent a small portion, approximately 3% of the overall construction project that is being completed. Potential suppliers may have the opportunity to propose compatible products for consideration.
XI. Certification by the Contracting Officer.
As evidenced by my signature above, I certify that this justification is accurate and complete to the best of my knowledge and belief.
XII. Certification by the technical/requirements personnel.
As evidenced by my (our) signature(s) above, I (we) certify that any supporting data contained herein, which is my (our) responsibility, is both accurate and complete.