This document is a Scope of Work for a state and local contract opportunity from the Youth Challenge Academy, Hilo (YCA Hilo) in Hawaii. The project involves locating and removing an abandoned 600-foot fence, as well as clearing and mulching approximately 0.45 acres of vegetated land containing various types of trees and shrubs. The contractor will be responsible for cutting down trees to the stump, applying approved pesticides/herbicides, and properly disposing of all materials and debris. The estimated quantities include 100 large trees, 15 coconut palm trees, 10 areca palm clumps, 5 mountain apple trees, and 2 jacaranda trees. All work must be completed before May 1, 2022, and the contractor must follow all applicable federal, state, and local laws and regulations.

The contract also includes special environmental conditions, such as the inadvertent discovery of Native Hawaiian cultural items or the presence of a hawk in the vicinity, which would require the contractor to cease work and contact the appropriate parties. The contractor must be licensed in the appropriate trades, submit proof of valid licensure, and use Davis-Bacon wages for the project. The contractor is responsible for field verifying the dimensions and location of the project area, and no substitutions are allowed for the disposal of the fence remnants. The project manager may allow the green waste generated from mulching to be retained on-site, subject to approval.

View the file

Other files

File Type Posted
H SPEC PROVConst ACT 52 and 68 Rev.doc DOC document
DD Form 1532 Instructions.pdf PDF
Approved Herbicide List.pdf PDF
HIePRO GoodsServices Offer Form YCA Hilo VegandFence Removal.doc DOC document
G Special notice to bidders Rev.doc DOC document
K1 GC Table of Contents.doc DOC document
103D-1 General Conditions.pdf PDF
K2 GCONDITION rev.doc DOC document
Inadvertent Discovery SOPs from ICRMP.pdf PDF
YCA HILO Vegetation Removal 2022 v1.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

YCA HILO OLD FENCE, TREE, AND VEGETATION REMOVAL

1.0 Scope of Work

The project is located at the Youth Challenge Academy, Hilo (YCA Hilo), BLDG 621A Address:

1046 Leilani St, Hilo, HI 96720

The Contractor shall provide all labor, tools, equipment, and materials required to perform all work related to locating an abandoned 600 ft long fence and its remnants, then removing all materials associated with this fence; materials include (but are not limited to) concrete, metal posts, metal mesh, metal wiring, etc. Materials and debris are to be disposed in a legal manner.

Contractor shall then provide all labor, tools, equipment, and materials required to perform all work related to Clearing and Mulching to Ground approximately .45 acres of vegetated land (~100 trees and shrubs) as shown on the map attachment on HIePRO. Trees in this area include, but are not limited to, Gunpowder trees, Bing-A-Bing trees, Melochia trees, Lauhala trees, saplings, Coconut palms, Areca palm clumps, Mountain apple trees, and Jacaranda trees.

Contractor shall cut all trees within this area down to the stump and not disturb the ground. No trees, roots, or stumps shall be uprooted or excavated; any mud ruts or minor machinery tracks must be filled with mulch and tamped down as needed after the service has been rendered.

After trees are cut down to the stump, the Contractor shall apply only pesticides (herbicides) approved for use on Hawaii Army National Guard (HIARNG) facilities; this list can be found on the HIARNG State Pesticide Use List (SPUL). Acceptable products for use at HIARNG facilities include: Garlon (Element) 3A, Garlon (Element) 4, Garlon 4 Ultra (GF-1529). All pesticides (herbicides) will be applied in accordance as per the pesticide (herbicide) label as required by the Federal, Fungicide, Insecticide, Rodenticide Act (FIFRA). Any deviation from approved for use herbicides must first be approved by the HIARNG Pest Management Coordinator (PMC). All pesticides (herbicides) applied must be reported daily on DD Form 1532-1. All pesticide applicators and applications are required to follow all state and federal pesticide laws.

Topography of the property must not be changed at all. Contractor is responsible for Field Verification of the dimensions and location of the area described in this project.

All work for this job must be completed before May 1, 2022, regardless of HIARNG ENV forced stoppages.

1.1 Estimated Quantities for this Project

Reconnaissance of the area to find the abandoned fence Removal of fence remains Hauling and landfill fees Trees requiring cutting down to the stump:

100 large trees 15 Coconut Palm Trees 10 Areca Palm Clumps 5 Mountain Apple Trees 2 Jacaranda Trees All equipment and accessories required to complete project

1.2 Estimated Area of Clearing

All shrubbery and vegetation over a 20,000 sqft (0.454 ac) stretch bordering the property line. It is estimated that there are 80-100 small trees in this area; contractor is responsible for verifying quantities before submitting a bid.

Everything required for hauling and properly/legally disposing of concrete, metal, and vegetation must be included in the bid price. In lieu of hauling and disposal, the Project Manager (Jim Barbour) may allow Green Waste generated from mulching. This will need to be approved prior to the Notice to Proceed. There will be no substituting disposal of fence remnants.

2.0 Drawings

Please review the Drawings and Maps provided in the HIePRO Solicitation.

The area considered in this project is comprised of the inside the Red borders.

3.0 Special Conditions

All work shall comply with all applicable federal, state, and County of Hawaii laws, rules, codes, ordinances, and regulations.

The Contractor shall schedule their work to ensure that the area is secure at the end of each work-day.

Contractor is informed that existing above-ground and below-ground lines such as electrical equipment, conduits and panels, and all other subgrade fixtures are their responsibility. Any damage that results from the clearing of this area is to be fixed by the Contractor at their cost.

It is recommended that Contractor contacts One-Call before starting any digging or site work Contractor shall be licensed in all appropriate trades required to perform the work and shall submit proof of valid licensure by the State of Hawaii and HCE Compliant.

Davis-Bacon Wages must be used by contractor and subcontractor(s).

Working hours for this project are between 7 a.m. and 3:30 p.m. Requests to work outside of these hours shall be submitted in writing no less than 1 week in advance. There is no guarantee that such requests will be approved.

Clean excavated material, free of debris, shall be disposed of in accordance with all local, state, and federal laws.

4.0 Special ENV Conditions

In the event that the inadvertent discovery of Native Hawaiian cultural items occur, all activity in the area will cease and the area will be secured. Such items include, but are not limited to:

• Discovery of known or likely human remains

• Unmarked graves

• Pre-contact or historical artifacts

• Archaeological features

• Paleontological remains

If any Cultural Material is discovered in the course of completing this project, the contractor must contact the Project Manager and the Cultural Resource Specialist (Kekapala Dye). Contractor must then provide the general location, information, and what activity may have resulted in the discovery. Coordination can be made on where and when activities can resume. Further guidance can be found in the HIePRO Solicitation Attachments (HIARNG Inadvertent discovery Standard Operating Procedure)

If a hawk lands in the vicinity of the job, then all work on the job would cease until the hawk leaves on its own accord.

5.0 Warranty

Warranty Period: Standard Warranty of the approved Pesticide/Herbicide.