Y27-131-RC_SOW_-_Stormwater_Maintenance_-_Ponds.pdf

PDF 521 KB Posted

Attached to
Orange County Maintenance of County Owned Stormwater Ponds
Solicitation number
Y27-131
Issued by
Orange County, Orlando City, Florida

About this file

This Scope of Work document outlines the requirements for Orange County, Florida's maintenance contract for county-owned stormwater ponds. The contract encompasses all labor, materials, services, equipment, and ancillary costs necessary to remove and dispose of sediment, vegetation, material, and debris from designated stormwater ponds, as well as repairs to inlets, outlets, slopes, and banks, along with erosion control measures, sodding, pipe jetting, and cleaning. Work shall be performed during standard hours of 6:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise authorized, with non-standard hours available for evening, weekend, holiday, and emergency work. The contract requires the contractor to maintain an on-site foreman with minimum three years' experience operating heavy equipment and laborers with minimum one year's relevant experience; all personnel must pass background checks, drug screening, and obtain Orange County photo identification. The sealed bid submission deadline is 4:00 p.m. EST on Tuesday, December 29, 2026, with an estimated project cost of $1,090,000.00, and responses must be submitted electronically through the OpenGov e-Procurement Platform only.

The contract is structured with Category 1 unit prices covering standard stormwater pond maintenance activities and Category 2 rates for emergency work and additional repairs not otherwise covered by Category 1 pricing; payment shall be made upon Service Coordinator acceptance based on actual quantities verified in the field, with invoices due within thirty days of work acceptance and submitted via mail to the Orange County Facilities Management Fiscal Division. The contractor bears full responsibility for all compliance with federal, state, and local environmental laws, including Clean Water Act requirements, Florida Statutes Chapter 403, Environmental Resource Permits, NPDES requirements, OSHA standards, and Water Management District regulations; material disposal must proceed to Orange County or FDEP-permitted facilities with TCLP testing performed on stockpiled excavated material. No specific set-asides are identified in the solicitation; the contractor must maintain adequate resources to perform multiple concurrent projects, provide detailed reporting on work completion and scheduling, and ensure all disturbed areas are restored to original condition, with all associated costs included in the unit prices for maintenance services.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

1. OVERVIEW

Work under this contract consists of providing all labor, materials, services, equipment, maintenance of traffic, permit fees, taxes, tests, mobilization /demobilization, insurance and miscellaneous costs, overhead and profit, that are necessary to remove and dispose of sediment, vegetation, material, and debris from stormwater ponds. Contractor shall be responsible for making repairs to inlet and outlets, slopes and banks, and perform erosion control measures, sodding, pipe jetting and cleaning in designated stormwater ponds. The

Divsion will schedule all maintenance work of selected stormwater ponds.

The scope of work covers stormwater management ponds currently maintained by

Orange County Facilities Management Division. Contractor shall be responsible for maintaining the stormwater ponds on an as-needed basis Table 1 provided is a historical listing of the stormwater ponds for reference. This listing is subject to change. The Contractor shall confirm the addresses of ponds scheduled for maintenance with the Service Coordinator.

Standard Hours: The Contractor shall perform all work during the Division's Standard

Hours of 6:00 a.m. to 6:00 p.m., Monday through Friday, unless otherwise directed or authorized by the Service Coordinator.

Non-Standard Hours: Non-Standard Hours shall apply to all work performed outside the Division's Standard Hours, including evenings, weekends, County-observed holidays, and emergency or urgent work authorized by the Service Coordinator. Unless otherwise directed by the Service Coordinator, all work performed during Non-Standard Hours shall require prior authorization from the Service Coordinator.

ORANGE COUNTY HOLIDAYS

Legal holidays when most County buildings will be closed to the public, are as follows:

1. New Year’s Day

2. Martin Luther King Day

3. Memorial Day

4. Fourth of July

5. Labor Day

6. Thanksgiving Day and the Friday after Thanksgiving Day

7. Christmas Eve and Christmas Day

8. Veterans Day

In addition to Orange County Holidays, the Ninth Judicial Circuit Court and the Clerk of

Court also observe the following:

1. Good Friday

2. Rosh Hashanah

3. Yom Kippur

2. PERSONNEL REQUIREMENTS

A. The Contractor shall be solely responsibility for the actions of its employees and subcontractors (if applicable) for the life of the Contract. New employees hired after contract award shall follow the same requirement for the life of the contract.

B. The Contractor shall assign a lead point of contact or supervisor with whom the Division may consult with regarding contract performance, service requests, project status updates, and other contractual matters throughout the entire contract term. Contact information shall include a valid e-mail address and phone number.

C. Effective communication with the Division staff is essential to the performance of this contract. The Contractor shall ensure that all supervisors and designated points of contact are fluent in English, with the ability to read, write, speak, and understand the language proficiently.

D. All the services required under this contract shall be performed by the Contractor or under Contractor’s supervision. The Contractor shall ensure that all personnel engaged in performing the services are fully qualified and, if required, authorized, licensed or permitted under state and local law to perform such services.

Foreman – Oversees the repair and maintenance work of stormwater ponds.

Requires a minimum three (3) years’ experience with operating excavators and related machinery for stormwater ponds maintenance and repairs including, but not limited to, front-end loaders, dozers, graders, excavators and other pieces of heavy equipment. Must be currently licenses and permitted to operate all heavy machinery to be use in contract fulfillment as required by State and County laws. Must be experienced with all types of work required under this contract including but not limited to excavating of sediments, grading, trench work, digging around utilities, pipe fitting, inlet and outlet repairs, and the repair of asphalt and concrete structures.

Must be able to make decisions on behalf of the Contractor.

Laborer – Works under the direction of the Foreman. Assists with the maintenance and repairs of stormwater ponds and related structures. Requires a minimum one (1) year experience performing similar work as detailed in this contract. Must possess current licenses or certifications for machinery if expected to operate machinery in the fulfillment of contract related work. Resume must be submitted with bid package.

E. The Division reserves the right to require the Contractor to immediately remove and replace any supervisor or other contract personnel who, in the Division’s sole judgment, fail to perform the required services in accordance with the terms, conditions, specifications, or performance standards of this Contract, or whose conduct, performance, or actions are determined to be unsatisfactory or detrimental to the County's interests. The Contractor shall provide a qualified replacement within a timeframe acceptable to the Division at no additional cost.

F. The Contractor shall comply with all applicable Federal, State, and local environmental laws, regulations, permits, and guidance, including but not limited to the Clean Water Act, Florida Statutes Chapter 403, applicable Florida Administrative

Code provisions, Environmental Resource Permits (ERP), National Pollutant

Discharge Elimination System (NPDES) requirements, OSHA standards, and all applicable Water Management District regulations. Compliance shall be maintained throughout the contract term regardless of whether specifically identified herein. The

Contractor shall be solely responsible for all fines, penalties, citations, damages, costs, or other liabilities resulting from its, its subcontractors', or its employees' failure to comply with applicable laws, regulations, or the requirements of this Contract.

G. Repeated or material violations may be deemed a material breach of the Contract and may result in suspension of the Work, withholding of payment, termination for cause, or any other remedy available under the Contract or applicable law.

H. Smoking of any kind, including but not limited to cigarettes, cigars, pipes, electronic cigarettes (e-cigarettes), and vaping devices, is strictly prohibited on all Orange

County-owned or -leased property, including buildings, grounds, parking areas, and

County vehicles, in accordance with Orange County policies. This prohibition applies to all Contractor personnel, subcontractors, and visitors. Violations may result in removal from the premises and may be subject to contract deductions or other remedies as determined by the Division.

I. All personnel working under this contract shall conduct themselves in a professional and businesslike manner. At no time shall any individual engage in behavior— whether verbal, physical, or written—that could be reasonably construed as obscene, harassing, or offensive. Any such conduct will be grounds for immediate removal from County property and may result in further action, including removal from the contract.

3. PERFORMANCE REQUIREMENTS

The Contractor shall conform to all Federal, State, and Orange County standards and regulations during the performance of this contract, including but not limited to:

• Florida Department of Transportation (F.D.O.T.)

• Florida Department of Environmental Protection (FDEP)

• St. Johns River Water Management

• Southwest Water Management

• Orange County Environmental Protection Division

• Orange County Codes

• Occupational Safety and Health Act (OSHA)

• National Institute for Occupational Safety & Health (NIOSH)

Florida Department of Transportation (FDOT) Standard Specification sections that are applicable to this Contract includes but is not limited to the following:

Section 104, Prevention, Control and Abatement of Erosion and Water Pollution

Section 120, Excavation and Embankment

Section 160, Stabilizing

Section 162, Prepared Soil Layer

Section 570, Performance Turf

Section 981, Turf Materials

Section 985 Geotextile Fabrics

Section 987 Prepared Soil Layer Material

Contractor may access the FDOT Standard Specifications through the Specification

Library at following website.

http://www.dot.state.fl.us/programmanagement/Implemented/SpecBooks/default.shtm

The Contractor shall comply with all applicable Federal, State, and local environmental laws, regulations, permits, and guidance, including but not limited to the Clean Water

Act, Florida Statutes Chapter 403, applicable Florida Administrative Code provisions, Environmental Resource Permits (ERP), National Pollutant Discharge Elimination

System (NPDES) requirements, OSHA standards, and all applicable Water Management

District regulations. Compliance shall be maintained throughout the contract term regardless of whether specifically identified herein.

A. The Contractor shall not subcontract the primary scope of work under this Contract without the prior written approval of the Service Coordinator.

B. The Contractor shall be solely responsible for the payment of all fines, penalties, citations, or other costs resulting from its failure, or the failure of its subcontractors or personnel, to comply with applicable laws, regulations, codes, or Contract requirements.

C. The Contractor, upon request by the Division, shall remove all Contractor’s personnel and subcontractors from County property and from providing service under this contract who are deemed careless, incompetent, insubordinate, reasonably objectionable, or whose performance is deemed inadequate or unsatisfactory as http://www.dot.state.fl.us/programmanagement/Implemented/SpecBooks/default.shtm determined by the Division.

D. The Contractor shall perform work in such a manner to prevent interruption and interference with the proper execution of Orange County business and provide the least inconvenience to building occupants and visitors.

E. The Contract Administrator may schedule periodic meetings to review contract terms, performance, and other contractual related matters. The Contractor shall attend all meetings as requested by the Contract Administrator, with no additional compensation provided for such attendance.

F. The Contractor shall notify the Service Coordinator immediately upon completion of each Delivery Order. Work shall not be considered complete until inspected and accepted by the Service Coordinator or Division. Acceptance by the Division does not relieve the Contractor of responsibility for defective work discovered after acceptance.

G. In the event of non-performance or unsatisfactory performance by the Contractor, or employees of (including subcontractors), the Service Coordinator shall have the right to exercise one or a combination of the following options:

1. Notify the Contractor of non-performance/unsatisfactory performance and allow

Contractor to correct such item of non-performance/unsatisfactory performance within a twenty-four (24) hour timeframe. Although the timeframe for making corrections may occur outside of the Contractor’s normal working hours, the

Contractor shall not receive any further compensation.

2. The Contract Administrator may request the Contractor remove any Supervisor or employee if it is a personnel related issue.

3. Assess liquidated damages in accordance with Article III, Administrative Data.

4. Cancel all or a portion of the delivery order. When a partially completed

Delivery Order is cancelled, the Contractor will only be paid for the satisfactory work performed there under.

5. The Division reserves the right to correct any item of non-performance/ unsatisfactory performance by any means it deems necessary to ensure the effective operation of the County's facilities. Costs incurred by the Division for the correction using Division employees shall be deducted from payments owed to the Contractor. If no payment is owed to the Contractor, the Contractor shall reimburse the Division for cost incurred within thirty (30) days of notification from the Division of total cost incurred.

H. The Service Coordinator will notify the Procurement Division of the unsatisfactory performance and or deficiencies in service that remain unresolved or reoccurring.

The Procurement Division, may after appropriate notice, take necessary actions to address unsatisfactory performance up to and including termination of this contract by default.

I. If the Contractor utilizes any specialized software platform to manage, monitor, or support the services provided under this Contract, the Contractor shall provide the

Contract Administrator and/or designated Service Coordinator with appropriate access to the platform for the duration of the Contract.

County access shall, at a minimum, permit viewing of work orders, service status, scheduling information, available reports, and supporting documentation necessary for contract administration, performance monitoring, and verification of services performed. Such access shall be provided at no additional cost to the County unless otherwise specified in the Contract.

4. COORDINATION OF WORK AND RESPONSE TIME

A. All work will be under the supervision of the designated Service Coordinator, depending on stormwater pond location.

B. The Contractor shall adhere to the following response times unless mutually agreed between the Division and Contractor in writing.

C. Prior to commencing work under each Delivery Order, the Contractor must conduct a site walkthrough with the Service Coordinator or designated Division representative, unless waived in writing by the Service Coordinator. During the walkthrough, the Contractor shall identify and document existing site conditions, including but not limited to access routes, utilities, structures, fencing, sidewalks, pavement, landscaping, stormwater facilities, and any other improvements that may be affected by the requested work.

EMERGENCY RESPONSE

In the event of an emergency, Contractor shall respond by visiting the worksite within four (4) hours of notification to determine the extent of the required service/repair.

Contractor shall submit quote for all services to be provided within twenty-four (24) hours of arriving at the worksite.

NON-EMERGENCY RESPONSE

Contractor shall respond to request for quotation by visiting the worksite to assess conditions within forty-eight (48) hours or two (2) business days after notification by the Service Coordinator.

The Contractor shall provide a detailed written quote within seventy two (72) hours of visiting worksite or three (3) business days from e-mail or phone notification.

The time of performance for each Delivery Order will be ten (10) calendar days from delivery order date unless otherwise negotiated between the Division and the

Contractor and documented on the Delivery Order; all timeframe for work completion shall be provided in the number of calendar days, documented on quotes provided by the Contractor and included on each Delivery Order. Contractor’s failure to adhere to these time frames may result in adverse actions by the Divsion.

D. The Contractor shall submit the following reports to the Service Coordinator for approval prior to commencing work under each individual delivery order:

a. Maintenance of Traffic Plan with approved MOT Permit (if applicable)

b. Schedule of Work according to the number of days quoted.

E. Multiple Concurrent Projects: The multiple concurrent project capability is considered a minimum requirement in the consideration of award of a contract for this solicitation. At any given time during the contract term, the Contractor shall have adequate resources to perform more than one Division project at the same time.

F. A Delivery Order will be issued for each project. The Delivery Order will contain a Start Date and Completion Date that will be mutually agreed to between the

Division and the Contractor prior to project start date. Specialty equipment and any work covered under “Additional Work and Repairs”, or Category 2 line items, of the schedule shall be approved prior to use and noted on Delivery Order. Contractors shall not begin any work under this contract without a delivery order.

G. Change Orders: Additional work, labor, and specialty equipment shall be approved prior to use and issued on County Change Order per ARTICLE 11 - CHANGES IN

THE WORK.

H. The Service Coordinator will be entitled at all times to be advised, at his/ her request, as to the status and details of the work being completed by the Contractor in a format he/she requires. The Contractor shall always maintain communication and coordination with the Service Coordinator. Either party may request and be granted a conference upon request in a timely manner during the performance of a delivery order. Upon the Division’s request, the Contractor shall inform the Service

Coordinator daily as to the locations to be worked and the areas completed on the previous day.

I. It is the Contractor's responsibility to visit the worksites prior to starting operations on any assigned project to ascertain site conditions. The Contractor shall submit the following information for each project:

• Quote detailing the project requirements

• Breakdown of work to be completed per the contract line items

J. Project schedule and action plan with time frame in the number of calendar days for project completion. The Contractor shall consult with the Service Coordinator prior to any schedule variance. The notification shall occur no later than the day before the day of the scheduled variance and requires Division approval and acceptance.

K. The Contractor shall coordinate with the Service Coordinator to verify work has been completed in accordance with this Scope of Work.

L. Unless otherwise specified in the applicable Delivery Order, the Contractor shall complete all work within ten (10) calendar days from the date the Delivery Order is issued. For each Delivery Order, the Contractor should provide a proposed completion schedule expressed in calendar days or estimated completion date as part of the quotation. Upon acceptance by the Division, the agreed-upon performance period shall be incorporated into the Delivery Order.

M. Time is of the essence for all work performed under this Contract. The Contractor shall diligently prosecute the work to completion within the time specified in the applicable Delivery Order.

N. Any request for an extension of the completion time shall be submitted in writing to the Division prior to the scheduled completion date and must include documentation supporting the reason for the delay. No extension shall be valid unless approved in writing by the Division or other authorized written modification. The Contractor shall promptly notify the Division in writing of any circumstance that may delay performance and shall take all reasonable actions to mitigate such delay.

5. TRAVEL AND PARKING

A. The Contractor shall be responsible for all travel and per diem costs associated with traveling to and from the County facilities. Travel time, fuel, and truck charges shall not be included in any quote or invoice and shall not be compensated by the Division under any circumstances. Billable time shall begin upon the

Contractor’s arrival at the specific job site where work is to be performed, not upon arrival at the general facility or campus.

B. The Division or Service Coordinator will identify available parking locations for

Contractor’s personnel. If parking fees apply, the cost shall be the sole responsibility of the Contractor. The Division shall not be responsible for any damage to the Contractor’s or subcontractor’s vehicles while parked on Orange

County property. Any towing fees or related expenses incurred while the

Contractor is on County property shall be the responsibility of the Contractor.

C. All Contractor and subcontractor vehicles shall be clearly identified with the

Contractor’s or subcontractor’s logo or name, and all signage must be visible and professionally displayed.

6. QUOTATION AND ESTIMATE REQUIREMENTS

Notwithstanding any provision of this Contract to the contrary, including any references to “quotes,” “quotations,” “estimates,” or similar pre-pricing requirements, this provision shall control. To the extent that any portion of this Contract conflicts with or imposes procedures inconsistent with this provision, this provision shall govern and supersede all such requirements.

The County may issue Delivery Orders under this Contract based on, but not limited to, any of the following, at the County’s sole discretion:

1. A verbal agreement confirming scope and anticipated quantities;

2. A written exchange, such as email, confirming scope and estimated quantities; or

3. A formal written quote, when specifically requested by the County.

The County further reserves the exclusive right to establish a standard practice requiring written quotations for certain types of work or work under specified conditions. Such parameters shall be communicated by the County’s representative to the Contractor in writing (e.g., work exceeding $X.00, or work performed at designated facilities requiring written quotations). The County may, at its sole discretion, waive any request for a formal written quote. Any such waiver shall not relieve the Contractor of any performance obligations or contractual duties under this Contract.

Prior to commencing work or accepting a Delivery Order or any Change Order to a delivery order, the Contractor is responsible to:

1. Confirm its understanding of the scope, and

2. Verify the accuracy of the estimated quantities or estimated hours stated in the

County’s official written order.

The Contractor’s commencement of work under a duly executed Delivery Order or

Change Order shall constitute the Contractor’s acknowledgment and agreement to confirmed scope, estimated quantities or hours; and all terms associated with the Delivery

Order and master agreement. Adjustments between estimated and actual quantities or hours shall require coordination between the County and the Contractor and must be memorialized through a County issued Change Order. Variances arising from the

Contractor’s failure to adequately review or assess the Delivery Order shall not justify issuance of a Change Order or additional compensation.

7. CONTRACTOR USE OF PREMISES

A. The Contractor shall conduct all work in a manner that minimizes disruption and inconvenience to the public, adjacent property owners, and County operations. The

Contractor shall coordinate all site access, work areas, and traffic impacts with the

Division’s Service Coordinator prior to commencing work. The access point(s) for each pond shall be approved by the Service Coordinator.

B. When required, the Contractor shall furnish, install, maintain, and remove all

Temporary Traffic Control (TTC), including all personnel, signs, barricades, warning devices, and equipment necessary to safely perform the Work. All Temporary Traffic

Control shall be provided at the Contractor's expense and shall comply with the latest editions of the Florida Department of Transportation (FDOT) Standard Plans, Index

102 Series (Temporary Traffic Control), the FDOT Design Manual (FDM), the

Manual on Uniform Traffic Control Devices (MUTCD), and all applicable federal, state, and local laws, regulations, and permitting requirements.

C. The project shall be fenced off from public access during non-working hours using temporary fencing. No open areas shall be left open during Holidays or Holiday weekends. When pedestrian traffic is impeded by work operations; barricades, restrictive tape, or other restraints shall be used to keep pedestrians from the work site.

D. The Contractor shall not be held responsible for the removal and installation of existing fencing around stormwater ponds. However, Contractor shall coordinate with the Service Coordinator to determine the extent and timing of the removal.

E. The Contractor shall immediately notify the Service Coordinator of any hazardous condition or obstruction affecting vehicular or pedestrian traffic that is observed or created during the performance of the Work. The Contractor shall take all reasonable measures to protect the public and secure the area until the condition is corrected.

F. The Contractor shall, at its sole expense and to the Division's satisfaction, promptly repair, restore, or replace any damaged property or utility to its original or better condition. Such property includes, but is not limited to, buildings, roadways, sidewalks, landscaping, stormwater facilities, sanitary sewer systems, water mains and services, gas lines, electrical systems, communication and fiber-optic lines, traffic signalization, signage, fences, irrigation systems, and any other public or private utilities, infrastructure, or structures encountered during the performance of the Work.

Repair or replacement of damaged property shall not relieve the Contractor of any other obligations or liabilities under this Contract or applicable law.

G. Contractor shall restore all areas damaged during the performance of the maintenance work to their original condition. All ruts shall be filled, areas where sod has been damaged shall be re-sod with like material, and disturbed areas shall be re-graded and re-sod at the Contractor’s expense.

H. The Contractor shall keep the work site free from accumulations of waste materials, rubbish and debris at the work site as well as all tools, construction equipment and machinery, and surplus materials, and shall always leave the work site clean and safe.

All applicable Florida Department of Environmental Protection's regulations shall be always followed.

I. The Contractor shall immediately contain and report any spill or release of fuel, oil, hydraulic fluid, chemicals, or other hazardous substances. Cleanup shall be performed at the Contractor's expense.

J. The Contractor shall restore to their original condition those portions of the work site, not designated for alteration by contract documents such as staging and stockpile areas. This shall include returning the area to the proper grade and slope as well as replacing sod, etc. prior to project completion.

K. Contractor shall coordinate with the Service Coordinator to ensure that all shoreline clearing activity is permitted and meets Water Management District Environmental

Resource Permit (ERP) requirements, where applicable. The Contractor shall be responsible for meeting all permit requirements in performing the maintenance of all stormwater ponds.

8. QUALITY CONTROL

A. Contractor shall be responsible for the implementation and tracking of all quality control measures through performance under this contract.

B. The Contractor shall provide competent, suitable and qualified personnel to perform the work as required by this Scope. The Contractor shall always maintain good discipline and order at the work site.

C. The lack of inspections by the Division or any error or omission in these specifications shall not relieve the Contractor of its obligation to perform services in accordance with this Contract.

D. The Contractor shall supervise and direct the work efficiently with due care, skill and attendance. The Contractor shall be responsible to ensure that the finished work complies accurately with the applicable specifications, County standards and all written orders.

E. The Contractor shall immediately notify the Service Coordinator of any unforeseen problems in the assigned project. Communication may be verbal, however, any communication that will change the project’s scope of work or cause a change is project cost shall be followed up in writing. The Contractor shall provide a revised quote including details of the unforeseen problems and cost changes within twenty-four (24) hours of verbal communication. The Contractor’s failure to comply with these requirements may result in non-payment in whole or partially for any additional work.

9. UNDERGROUND OR OVERHEAD UTILITIES

It shall be the Contractor’s responsibility to determine the location, character and depth of any existing utilities and to assist the utility companies, by every means possible, to determine said locations. Extreme caution shall be exercised to eliminate any possibility of any damage to utilities resulting from Contractor’s activities.

During the period of this contract the Contractor shall coordinate all utility relocations and adjustments necessary for project.

A. The Contractor shall cooperate with owners of any underground or overhead utilities in the removal and rearrangement operations, in order that these operations may progress in a reasonable manner and that service rendered by these parties will not be interrupted.

B. Excavators shall comply with current Florida Statutes regarding notification of existing gas and oil pipeline company owners prior to excavating. Evidence of such notice shall be furnished to the Service Coordinator prior to excavating.

C. The Contractor shall be responsible for locating of utilities prior to starting operations.

D. The Contractor shall notify the Service Coordinator of any damages (irrigation, utilities, etc.) and shall repair damages immediately. The Contractor shall be responsible for these areas for a period of six (6) months after acceptance of the project and shall be required to correct any damages related to such repairs. No additional compensation shall be provided to the Contractor for locates or repairs to damages as specified above.

Costs associated with these activities shall be included in the unit prices for services under the line items designated for Stormwater Pond Maintenance, or Category 1, of this

10. SEDIMENTATION AND EROSION CONTROL

The Contractor shall furnish all labor, materials, equipment (including excavator and dump trucks), and incidentals necessary to perform all installation, maintenance, removal and area cleanup related to sedimentation control work as specified herein.

A. The Contractor shall implement Best Management Practices (BMPs) for sedimentation, erosion, and pollution control to prevent violation of State Water

Quality Standards as outlined in the Florida Department of Transportation Standard

Specifications for Road and Bridge Construction and shall produce the results required Florida Department of Environmental Protection (DEP) and by the rules of the Orange County Environmental Protection Division. Contractor shall obtain the most recent version of all applicable publications.

B. Turbidity barriers shall be installed at existing stormwater control structures and at all locations where the possibility of transferring suspended solids into the receiving water body exists. Turbidity shall not be increased more than 29 Nephelometric

Turbidity Units (NTUs) in the receiving water body (62-302.530, F.A.C.). The

Contractor shall perform testing as needed to ensure increases in turbidity do not exceed 29 NTUs.

C. Erosion control shall be implemented prior to and during work being performed by the Contractor. Contractor is responsible for providing effective temporary erosion and sedimentation control measures until permanent controls become effective.

1) Temporary sedimentation controls include, but are not limited to, silt dams, traps, barriers, appurtenances at the foot of sloped surfaces which will ensure that sedimentation will be either eliminated or will not result in an increase of more than 29 NTUs in the discharge.

2) Temporary erosion controls include, but are not limited to, grassing, mulching, setting, watering, and reseeding on-site surfaces and providing interceptor ditches at necessary locations to ensure that erosion while performing the work will be eliminated or will not result in an increase of more than 29 NTUs in the discharge.

D. All wetlands areas or water bodies outside the specific limits of this scope of work shall be protected from erosion, sedimentation, scouring, excess turbidity, and dewatering by the Contractor.

E. Where applicable, the selected sedimentation control measures shall be installed landward of upland buffer zones around all protected wetlands. All areas shall be stabilized and vegetated immediately after performing any work to prevent erosion and transport of sediment into the receiving water body, wetlands, or upland buffer zones.

F. Final stabilization of all berms to be with sod.

Costs associated with these activities shall be included in the unit prices for services under the line items designated for Stormwater Pond Maintenance, or Category 1, of this

11. EXCAVATED SEDIMENT, DEBRIS, AND VEGETATION REMOVAL

A. Contractor shall furnish all labor, materials, equipment, tools, supplies, and incidentals required to remove and dispose of sediment, debris, organic soil, exotic and other nuisance vegetation removal and disposal, pipe jetting and cleaning in specified stormwater management ponds as specified herein.

B. Contractor shall use commercial grade mechanical harvesting and excavation equipment to perform all work (long or short boom excavator, jetter vacuum truck, etc.). Contractor shall use equipment that contains non petroleum based fluids while working in storm water ponds. The equipment shall be free of

Hydrilla verticillata and all other vegetation prior to any work. All harvesting and excavation equipment shall be cleaned by the Contractor prior to performing any work. The Division reserves the right to inspection all equipment use to perform work.

C. Contractor shall excavate stormwater management ponds to lines and grades indicated on applicable Record Drawings. If Record Drawings are not available, the Contractor shall remove all organic materials based on the latest standards of the following authorities:

1. Florida Department of Transportation (F.D.O.T.)

2. Florida Department of Environmental Protection (FDEP)

3. St. Johns River Water Management

4. Southwest Water Management

5. Orange County Environmental Protection Division

6. Orange County Codes

D. Excavated material and vegetation shall be temporarily placed and stockpiled in areas agreed upon between the Service Coordinator and Contractor.

Excavated material and vegetation shall be stockpiled for no less than seven days prior to transporting to the disposal facility. Drainage shall be controlled such that the runoff from the stockpile areas is returned to the stormwater pond being maintained and prevent sediment/erosion off-site.

1. Contractor shall be responsible for testing a minimum of one composite sample (from eight discrete locations) per 400 cubic yards from all stockpiled material at each pond using SW-846 EPA Test

Method 1311 - Toxicity Characteristic Leaching Procedure (TCLP) and in accordance with 40 CFR 261.24 for the following metals:

arsenic, barium, cadmium, chromium, lead, mercury, selenium and silver.

a. Composite sampling and analysis shall be performed by a contract laboratory certified by the State of Florida as a subcontractor to the successful bidder. The laboratory shall be experienced in this type of sampling and analysis. Sampling shall be in accordance with the most recent FDEP Standard Operating

Procedures. The contract laboratory shall be approved by the

Divsion.

2. The Contractor shall dispose of drained, excavated material and vegetation in an Orange County or FDEP permitted facility. The disposal facility shall be chosen based on TCLP analytical results and agreed upon by the Contractor and Service Coordinator. If the stockpiled material for a given pond fails TCLP testing, the Division will assume responsibility for the proper disposal of stockpiled material.

E. The Contractor shall remove all exotic vegetation and other nuisance species such that this vegetation shall be no more than 10 percent of total cover of the vegetative community. Removal of vegetation shall include roots and rhizomes of the nuisance vegetation.

F. Contractor shall remove all garbage, soil, and vegetation from inlet and outfall structures or pipes. Excavated sediment, debris and vegetation within the designated pond mechanical means (long or short boom excavator, jetter vacuum truck, etc.) to the required depth as determined by the Service

Coordinator. Any damages created by the Contractor’s operations shall be repaired as specified by the Service Coordinator prior to leaving the jobsite at no cost to The Division.

G. The removal and disposal of any and all debris, sediment and vegetation at a specified location shall be inclusive of loading, hauling and disposal at a landfill, properly permitted facility and other incidentals. The quantity of the material removed from the pond shall be determined by the number of cubic yards of material loaded into dump trucks, verified by the Service Coordinator and hauled to the landfill. Landfill tickets shall be provided by the Contractor to the Service

Coordinator with invoice for reimbursement.

H. Unless otherwise directed by the Service Coordinator, the debris shall not be recycled, re-used, stock-piled, or re-sold by the Contractor.

The unit price per cubic yard to excavate and dispose of sediment, debris and vegetation includes all labor, materials, mechanical equipment, maintenance of traffic, erosion control, and any other incidentals needed to complete the work including the transportation of all cleared/excavated material to closest approved County landfill. Contractor shall provide copies of Disposal Tickets for reimbursement.

12. DISPOSAL OF EXCAVATED MATERIALS

A. Loads shall be taken to a specified landfill or permitted facility by the Florida

Department of Environmental Protection. The County Solid Waste Division shall be contacted and shall have first right of refusal prior to using an alternate facility.

B. Disposal location shall be the closest approved County landfill or mutually agreed upon between Contractor and Service Coordinator in writing prior to disposal of material.

C. The truck driver shall supply a copy of the disposal tickets to the Service

Coordinator after every return trip to the site and then after the final visit to finalize the project.

D. Disposal tickets shall contain at a minimum the following information: date, time, truck number, work site name, verified amount of debris loaded, and driver’s signature. The landfill’s or facility’s disposal ticket number shall be written on the corresponding delivery ticket after every trip so they may be matched to verify invoice accuracy.

E. The disposal tickets shall contain at a minimum the following information: date, time, truck number, work site name, type of debris, verified amount of debris loaded, driver’s signature, and Service Coordinator’s signature.

Contractor will receive reimbursement for loads per the bid proposal form.

No reimbursement for disposal shall be provided without the landfill disposal ticket.

13. DEWATERING OF STORMWATER PONDS (AS-NEEDED)

For all work in the areas with high groundwater levels, dewatering during excavating and backfilling shall be anticipated and may be accomplished by the use of sump pumps and/or other methods such as, sanded well points, and vertical/horizontal suction wells as approved by the Service Coordinator. Contractor shall obtain a Water Use Permit as required by the applicable Water Management District prior to any dewatering activity.

A. Contractor shall prepare a basic plan for any dewatering, including proposed pumping rates and duration as well as the points of discharge. The Contractor shall obtain written approval and acceptance from the County prior to proceeding.

B. For proposed dewatering discharges to the County owned and operated storm system, the Contractor shall obtain a Right of Way Utilization permit from Orange

County Public Works.

C. For dewatering discharges proposed to go off site, other then into the County storm water system, the Contractor shall provide written permission from the property owner and coordinate with Orange County Environmental Protection Division.

Dewatering shall be in accordance with all applicable laws, codes, and requirements according to the PERFORMANCE REQUIREMENTS of this contract.

Dewatering shall be on an “as-needed” basis and shall be negotiated and paid for in accordance with line items under REPAIRS AND ADDITIONAL WORK of this contact and fee schedule.

14. FILL DIRT

Contractor shall provide fill dirt as requested by Service Coordinator. The Division reserves the right to inspect the source of the supply prior to delivery.

A. Material shall be clean fill material without any construction debris with uniform moisture content prior to and during compaction throughout each layer of material.

Use backfill material having placement moisture content within 2% on the dry side of optimum. At the end of each day’s operation, slope the backfill surface in order to permit runoff of rainwater away from the slope face, or provide some other positive drainage. In general, fill material are comprised of mixture approximately

45 percent clean native soil, 40 percent sand, maximum 10 percent muck and maximum 5 percent vegetation (allowable). Material for fill dirt shall conform to

F.D.O.T Specification, Section 987, Prepared Soil Layer Material. Fill material shall be free of vegetation, deleterious material, rock, concrete, metal, wood, plastic, paper, garbage, gravel, trash, etc. and will not be acceptable. The

Divsion reserves the right to request fill dirt certification as-needed from the

Contractor as verification that these requirement are met.

B. Muck, sand, and clay will not be accepted as fill dirt. Loads that contain undesirable material will not be accepted and removal of the material will be the responsibility of the Contractor at no additional cost to the Division.

C. Erosion repairs and berm restoration shall be performed within specified areas as determined by the Service Coordinator. Eroded areas shall be filled with clean fill dirt and returned to the proper grade and compaction; leveling the top edge of the bank to prevent water from running over the edge of the bank with a slight pitch away from the bank to prevent erosion. Quantities for imported clean fill dirt will be verified by the Service Coordinator.

D. Delivery tickets shall be provided by the Contractor to the Service Coordinator at the completion of each project. The total quantity of the erosion repairs shall be determined by the number of cubic yards of imported fill dirt used to complete the work as verified by the Service Coordinator. Berms, slopes and access areas disturbed by the work performed shall be re-sodded using Bahia sod (pegged where needed).

Excavated material deemed to be reusable can be mixed with “clean back fill” as determined by the Service Coordinator.

The cubic yard unit price to furnish and install fill dirt shall be inclusive of labor, materials, erosion control, grading, compaction and any other incidentals needed to complete the work.

15. SEEDING AND SODDING

The Contractor shall be fully responsible for maintaining in good condition all vegetation, e.g. cultivated grass plots, trees, shrubs, etc. around the work area. Where maintained shrubbery or grassed areas shall be removed or destroyed incidental to the construction operation, the Contractor shall, after completion of the work, replace/restore to the original condition, all destroyed or damaged shrubbery or grass. The Contractor shall understand that shrubbery shall be encountered at any given site and shall consider this when submitting a bid for structures.

Grass that shall be removed for the construction shall be replaced at the contract unit price for that particular type of sod.

All disturbed areas are to be graded to within plus or minus one tenth (1/10’) of a foot of the existing elevation and shall be sodded to match existing sod unless otherwise directed by the Service Coordinator. Sod placed adjacent to the road and walkways shall be placed flush with the top of the road surface so as not to cause a drop off or rise of sod dirt to asphalt. The Contractor shall be fully responsible for all disturbed areas outside the designated work area and shall repair/replace at no cost to the Division.

Trees interfering with the construction will be evaluated by the Service Coordinator and trimmed or removed accordingly by the Division.

Sodding

The Contractor shall establish a stand of grass sod in the necessary areas of construction by furnishing and installing sod, fertilizing, watering, and maintaining the sodded areas in accordance with FDOT’s Standard Specifications for Road and

Bridge Construction, Sections 570 and 981, most recent edition, except where authorized by the Service Coordinator.

In established areas, unless otherwise approved by the Service Coordinator, replacement sod shall be of the same type as the existing sod (i.e. replace Bahia sod with Bahia sod).

Every piece of sod shall be pegged if area to be sodded has a slope of three-to-one

(3:1) or greater or at locations where the sod shall slide. A minimum of three (3) pegs for piece of sod shall be used on slopes and other areas as required by the

Service Coordinator.

Thoroughly water the sod immediately after placing. Do not apply more than one inch of water per acre per week for establishment. Use watering equipment that shall prevent damage to the finished sod surface. The contractor shall keep the sod in a moist condition for a period of 30 days or until a firm root system and healthy stand of grass is established, whichever is longer. All cost for ensuring a firm root system and healthy stand of grass is included in the price to purchase and install the sod. Areas determined not to be in compliance with these requirements shall be removed and replaced by the Contractor at no additional cost to the Divsion.

Seeding, Mulching and Soil Preparation

The Contractor shall seed and mulch with Division's approval all areas disturbed by construction which are not designated for sodding in accordance with FDOT’s

Standard Specifications for Road and Bridge Construction, Sections 162, 570 and

987, most recent edition, except where authorized by the Service Coordinator.

Work under this Section shall include the seeding, mulching, fertilizing, and watering necessary to provide routine maintenance of the seeded area until the work is accepted by the Service Coordinator.

The square yard unit price for seeding, sodding, and mulching shall be inclusive of labor, materials, erosion control, grading, compaction and any other incidentals needed to complete the work.

16. TCLP TESTING

When directed by the Service Coordinator, the Contractor shall collect representative sediment samples and obtain Toxicity Characteristic Leaching Procedure (TCLP) laboratory analysis from a laboratory certified by the State of Florida. The Contractor shall provide laboratory reports to the Service Coordinator prior to disposal of the material when required by the County, applicable regulations, or the receiving disposal facility.

The Division reserves the right to require analytical testing of excavated sediment, including but not limited to TCLP testing, prior to transportation or disposal. The

Contractor shall not dispose of material requiring analytical testing until written authorization has been provided by the Service Coordinator.

17. ADDITIONAL WORK AND REPAIRS

All additional work and repair services under this contract must be approved in writing by the Divsion. All services required hereunder shall be performed by the Contractor or under the Contractor’s supervision, and all personnel engaged in performing the services shall be fully qualified and, if required, authorized, licensed or permitted under state and local law to perform such services. Response time and submittals shall be according to the -

COORDINATION OF WORK AND RESPONSE TIME section.

A. Contractor shall perform repairs to inlet/ outlets pipes and surrounding structure including, but not limited to: risers, weirs, asphalt/concreate structures.

B. All repairs shall be according to F.D.O.T. Standard Specification for Roads and

Bridges Construction, FDEP requirements and Orange County Environmental

Protection Division requirements.

It shall the Contactor’s responsible to obtain the most recent standard publications and codes. Any fines levied due to inadequacies or failure to comply with any and all requirements shall be the sole responsibility of the Contractor

C. Contractor shall be required to submit a quote for County approval inclusive of estimated labor hours, materials, equipment and incidentals needed to perform the necessary repair. Unit prices for services under Category One (1) are inclusive of labor, material, and incidentals. Unit prices under Category 1 include, but are not limited to all labor, services, materials, equipment, maintenance of traffic, taxes, tests, mobilization/demobilization, insurance, incidentals and other miscellaneous costs, overhead and profit, that are necessary to successfully complete all work herein. This shall include the completion of any reports for stormwater ponds that are serviced under any line item in this schedule.

Category 2 services shall be performed only when specifically authorized by the

Service Coordinator and shall be used solely for emergency work or additional work not otherwise covered by the Category 1 unit prices. Category 2 services shall not be used to supplement, augment, or duplicate the labor, materials, equipment, or other costs included in any Category 1 unit price. The Division reserves the right to reject any invoice containing Category 2 charges for work determined to be included within the applicable Category 1 unit price.

D. Contractor shall not perform any services without approval in the form of a delivery order.

E. All repairs for line items covered under “Additional Work and Repairs” line items shall be invoiced separately. Payment for repairs and additional work must be billed in accordance with the Scope of Work.

F. A separate service ticket documenting hours worked and a detailed description of work performed shall be completed for each day of work and submitted to the

Division or Service Cooridinator with final invoice for payment for all work requests.