The document is a solicitation from Orange County, Florida for cleaning services for air quality control towers at the Eastern Regional Water Supply Facility. The county is seeking a contractor to clean 10 towers twice annually (in March and September) using specialized chemical cleaning processes. The cleaning involves removing calcium buildup from plastic media inside towers that are used to remove hydrogen sulfide gas from water treatment systems. Vendors interested in responding must contact Michelle Fort by email no later than 5:00 PM Eastern time on Monday, August 7, 2025. Currently, Yave Yire Enterprises, Inc. is identified as the only known vendor meeting the county's requirements.
The solicitation includes detailed technical and safety requirements for the contractor, including possessing DOT hazardous materials transportation permits, OSHA Confined Space Certification, and providing safety data sheets for chemicals. The cleaning process involves a precise 10-step procedure using a 2% sulfuric acid solution, with specific instructions for coordinating with county staff, taking treatment systems offline, recirculating cleaning solutions, and inspecting tower packings. Contractors must use chemical-resistant pumps, wear protective equipment, and follow strict safety protocols. The document emphasizes the technical complexity of cleaning these specialized water treatment infrastructure components and the importance of maintaining their performance and integrity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Cleaning_Air_Quality_Control_Towers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Y25-06-SS
Orange County, Florida is interested in procuring services for the Cleaning Air Quality Control Towers. To date, research within the industry has indicated to the County that Yave Yire Enterprises, Inc. located at 2156 Sunset Terrace Drive, Orlando, FL 32825, is the only vendor that fulfils this requirement.
Minimum requirements are listed below:
OVERVIEW
Orange County Utilities is responsible for maintaining air quality control towers at the Eastern Regional Water Supply Facility 9100 Curry Ford Road Orlando, FL 32825. A contractor will clean all 10 towers at this location twice a year—once in March and once in September.
BACKGROUND
The facility uses a system to clean drinking water by removing hydrogen sulfide gas.
The process is as follows:
• Water is sprayed from the top of special towers while air is blown in from the bottom.
• This process removes hydrogen sulfide from the water and pushes it into the air.
• That air is then cleaned in separate towers (air quality control towers), where water with a high pH (11.0–11.5) is used to pull the hydrogen sulfide out of the air.
• Sodium hydroxide is added to raise the water’s pH, which helps trap the gas.
However, this process causes calcium to build up on plastic media inside the towers. If not cleaned, the buildup can reduce performance or even damage the system. The towers contain thousands of small plastic balls to help with air-water contact and mist eliminators to prevent corrosive mist from escaping.
I. STAFFING & EQUIPMENT REQUIREMENTS
A. The Contractor shall furnish all chemicals, materials, and labor necessary to perform the services as described herein.
B. The Contractor shall comply with Department of Transportation’s (DOT) transportation of hazardous materials permit for transporting of chemicals.
C. The Contractor shall possess Occupational Safety and Health Administration
(OSHA) Confined Space Certification.
D. The Contractor shall also provide the applicable Safety Data Sheets (SDS) at the time of each delivery for the duration of the contract.
E. The Contractor shall assigned employees trained in handling or exposure to chemicals, understanding the contents of the Safety Data Sheets (SDS), proper use of protective equipment, and the appropriate actions to take in case of exposure.
F. The Contractor shall furnish a Safety Data Sheet (SDS) and hazardous warning labels upon request for all chemicals transported and delivered.
G. The Contractor shall provide Certificate of Analysis for chemicals used to perform services.
H. The Contractor shall ensure that all employees are clean, neat, wear issue uniforms that are protective clothing. The employees shall conduct themselves in a professional, business-like manner.
I. The Contractor shall be required to perform services work in areas that are approximately twenty (20) feet above ground level.
J. The Contractor shall provide instrumentation for confined space entry requirements permit. The Contractor shall provide proof of confined space entry requirement permit.
K. The Contractor shall have chemical resistance pump to transfer acids to air quality control towers.
L. The Contractor shall prepare a volume of cleaning solutions in vessel to its normal liquid level. A 2% acid solution of 38% sulfuric acid shall be used when performing services.
M. All services required hereunder shall be performed by the Contractor and all personnel engaged in performing the services shall be fully qualified and, if required, authorized, licensed or permitted under state and local law to perform such services.
N. The Contractor shall conform to all Federal, State, City, and Orange County standards and regulations during the duration of the contract.
II. SAFETY
A. The Contractor shall provide and ensure that all personnel providing services under this contract are in compliance with applicable laws, standards, and health and safety requirements of the industry to include by not limited to: Occupational Safety and Health Act (OSHA).
B. The Contractor shall immediately notify to the County Representative the issues which may affect the safety of Orange County personnel or the public.
C. The Contractor shall provide and ensure the wearing of necessary protective clothing, masks, eye protection, hearing protection, etc. as required by any applicable laws, regulations, ordinances, and/or manufacturer’s instructions.
D. All equipment used in the performance of these services shall be properly maintained. Any equipment deemed faulty, inoperable, unsafe or improper for its intended purpose shall be promptly moved from the County’s premises.
E. The Contractor shall immediately notify the County Representative of any chemical spills over one (1) gallon, equipment failures, injuries that occur while performing services. The Contractor will be the responsibility of damages to Orange County facilities and property resulting from services performed.
III. CLEANING SERVICE SCHEDULE
A. The Contract shall schedule services for the first week of March and September;
however, this schedule may be subject to change based on the needs of the County.
B. The Contractor shall notify the County Section Manager in writing at least ten (10) days in advance if services cannot be provided or if there are any changes affecting the performance of services.
IV. CLEANING AIR QUALITY CONTROL TOWERS
A. INSPECTION
The Contractor shall inspect the air quality control tower packing on both scrubber and mist eliminator prior to cleaning and after cleaning to ensure cleaning was successful. The Contractor shall open the vessel hatches and remove one media ball for sample and inspection. Upon removal, the Contractor shall contact the assigned Orange County staff and they will contact the Section Manager
B. CLEANING
The Contractor shall perform the following steps:
1. The Contractor shall coordinate with Orange County staff to taking all treatment systems offline and then return to service in order to perform cleaning services.
2. Open the sump drain and discharge its contents to the lift station.
3. While the hatch is open for mist eliminators’ inspection, activate the valve in mist eliminator cleaning system and the reinstall hatch back on.
4. Close the sump drain valve and fill the sump with the cleaning solution, which may be prepared separately or directly in the vessel.
5. Start the cleaning pump and recirculate the solution through the vessel for two
(2) to three (3) hours.
6. Stop recirculating pump, drain sump and inspect the packing. If packing still needs cleaning, repeat the procedure.
7. If the packing is clean, close off mist eliminator cleaning system and reinstall hatch.
8. Restart the procedure with mixing acid solution to clean bottom pack.
Recirculate solution for three (3) to four (4) hours.
9. Stop recirculating pump, drain sump and inspect packing. If packing still needs cleaning, repeat the procedure
10. If the packing is clean, close off drain and fill with clean water. The unit is ready for startup.
Any vendor meeting all of the County’s minimal requirements is invited to contact Michelle Fort by email at Michelle.Fort@ocfl.net no later than by 5:00 PM (Eastern time), Monday, August 7, 2025.
mailto:Michelle.Fort@ocfl.net