Y22-764.pdf
PDF 2 MB Posted
- Attached to
- Parks Dr. Phillips/Orange County Public Schools (OCPS) Future Middle School Joint Ballfield Park
- Solicitation number
- Y22-764
- Issued by
- Orange County, Orlando City, Florida
About this file
This document is an Invitation for Bids (IFB) No. Y22-764-FH issued by Orange County, Florida, in collaboration with Orange County Public Schools (OCPS), for the Parks Dr. Phillips Future Middle School Joint Ballfield Park project. The project involves constructing four ballfields, a concessions/storage/restroom building, storm drainage, parking, and an entrance road on a six-acre site located at 10496 Bissell Street, Orlando, FL. The total estimated project cost is $8,000,000. Sealed bids are due by 4:00 PM on February 10, 2022, to be submitted electronically through the OpenGov Procurement Portal. A non-mandatory virtual pre-bid conference was held on January 20, 2022, and the project is expected to be substantially completed within 210 consecutive calendar days from the official Notice to Proceed.
The bid requires compliance with Minority/Women Owned Business Enterprise (M/WBE) requirements, with an overall goal of 20% participation of the contract value for M/WBE subcontractors and suppliers. Bidders must provide documentation of good faith efforts to meet these goals, including workforce diversity targets of 18% minority and 6% women employees. The project will be awarded to the lowest responsive and responsible bidder, with the County reserving the right to reject any and all bids. Performance and payment bonds will be required, and the contractor must provide comprehensive insurance coverage, including builders' risk, general liability, and workers' compensation. Funding appears to be from county and potentially school district sources, with the project aimed at creating a joint-use ballfield park facility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Y22-764_Drawings.pdf | ||
| Y22-764_Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
i
IFB NO. Y22-764-FH ISSUED: January 10, 2022
INVITATION FOR BIDS
FOR
PARKS DR. PHILLIPS/ORANGE COUNTY PUBLIC SCHOOLS (OCPS) FUTURE
MIDDLE SCHOOL JOINT BALLFIELD PARK
In an effort to help promote social distancing measures during the COVID-19 Public Health Emergency, electronic submissions will be accepted by the County.
Firms are strongly encouraged to submit responses electronically. Firms will not be permitted to fax or email offers.
To maintain a secured sealed process electronic submissions may be made through the OpenGov Procurement Portal only at:
https://secure.procurenow.com/portal/orangecountyfl or Mail or Hand Deliver
ORIGINAL BID FORM (MARKED “ORIGINAL”), ONE (1) COMPLETE COPY AND
ONE (1) ELECTRONIC COPY ON USB DRIVE
BY 4:00 PM – February 10, 2022
To:
ORANGE COUNTY, FLORIDA
INTERNAL OPERATIONS CENTRE II
PROCUREMENT DIVISION
400 E. SOUTH STREET- 2nd FLOOR
ORLANDO, FLORIDA 32801
A Non-Mandatory Virtual Pre-Bid Conference will be held on January 20, 2022, at 10:00
AM.
NON-MANDATORY PRE-PROPOSAL CONFERENCE MEETING LINK
https://ocfl.webex.com/ocfl/j.php?MTID=me491a558c6e31f62a23eaae02d9bcdf7
Meeting number: 2464 784 7820 Password: Go2Meeting
More ways to join:
Join by video system Dial 24647847820@ocfl.webex.com You can also dial 173.243.2.68 and enter your meeting number.
Join by phone 1-408-792-6300 Call-in number (US/Canada) Access code: 2464 784 7820
Interested bidders are encouraged to attend.
https://secure.procurenow.com/portal/orangecountyfl https://ocfl.webex.com/ocfl/j.php?MTID=me491a558c6e31f62a23eaae02d9bcdf7 ii
NOTICE TO BIDDERS/OFFERORS
Effective August 11, 2020, the Board of County Commissioners approved a change to the M/WBE Ordinance, removing the sliding scale from all construction formal solicitation opportunities. All bidders, for construction and professional services formal solicitations, are required to successfully demonstrate Good Faith Effort, or they shall be deemed non-responsive by the Procurement Manager.
If you have any questions regarding this change, please submit them to the assigned Contracting Agent identified in the Invitation for Bids document.
To ensure that your bid is responsive, you are urged to request clarification or guidance on any issues involving this solicitation before submission of your response. Your point-of-contact for this solicitation is Rolando Melo at (407) 836- 5644 or at Rolando.Melo@ocfl.net.
PART A
mailto:Fabio.Henao@ocfl.net iii
TABLE OF CONTENTS
PART DESCRIPTION PAGE
A INVITATION FOR BIDS A
B NOTICE B
C INSTRUCTIONS TO BIDDER
1. GENERAL C-1
2. PREPARATION AND SUBMISSION OF BIDS C-1
3. MINORITY/WOMEN OWNED BUSINESS ENTERPRISE C-4
4. BID PREFERENCE FOR REGISTERED SERVICE-DISABLED
VETERANS (SDV) C-11
5. BID ERRORS C-11
6. DEVIATIONS C-11
7. SUBSTITUTE MATERIAL AND EQUIPMENT C-12
8. REQUESTED INFORMATION/DESCRIPTIVE LITERATURE C-12
9. AWARD OF CONTRACT/REJECTION OF BIDS C-12
10. POSTING OF RECOMMENDED AWARD C-13
11. CONTRACT DOCUMENTS C-14
12. MODIFICATION/ALTERATION OF SOLICITATION C-14
13. LAWS AND REGULATIONS C-14
14. REQUIRED DISCLOSURE C-14
15. EXECUTION OF WRITTEN AGREEMENT C-15
16. LICENSING REQUIREMENTS C-15
17. SECURITY FORFEITURE C-16
18. PERFORMANCE BOND AND PAYMENT BOND C-16
19. QUALIFICATIONS OF SURETY COMPANIES C-16
20. TRENCH SAFETY ACT C-17
21. DRUG FREE WORKPLACE C-17
22. BID TABULATION AND RECOMMENDED AWARD C-17
23. INDEMNIFICATION FOR TORT ACTIONS C-17
24. OCCUPATIONAL SAFETY AND HEALTH ACT (O.S.H.A.) C-18
25. PUBLIC ENTITY CRIME STATEMENT C-18
26. SUBCONTRACTOR/SUPPLIER INFORMATION C-18
27. SUBCONTRACTOR’S PAST PERFORMANCE C-18
28. REFERENCES C-19
29. BID & RELATED COSTS C-19
30. SOLICITATION CANCELLATIONS C-19
31. LICENSES/PERMITS/FEES C-19
32. BID ACCEPTANCE PERIOD C-20
33. EQUAL OPPORTUNITY C-20
34. ETHICS COMPLIANCE C-21
35. TOBACCO FREE CAMPUS C-21
36. VERIFICATION OF EMPLOYMENT STATUS C-22
37. PROPRIETARY INFORMATION C-22
iv
38. DEBARMENT, SUSPENSION, INELIGIBILITY AND VOLUNTARY
EXCLUSION C-24
39. FLORIDA CONVICTED/SUSPENDED/DISCRIMINATORY
COMPLAINTS C-24
PART DESCRIPTION PAGE
D BID FORM
OFFICIAL BID FORM D-1
NON-COLLUSION AFFIDAVIT ATTACHMENT A
REQUIRED DISCLOSURE ATTACHMENT B
M/WBE REQUIREMENTS ATTACHMENT C
COMPLIANCE WITH TRENCH SAFETY ACT ATTACHMENT D
REFERENCES ATTACHMENT E
PROJECT EXPENDITURE REPORT ATTACHMENT F
RELATIONSHIP DISCLOSURE FORM ATTACHMENT G
E-VERIFICATION CERTIFICATION ATTACHMENT H
BID BOND EXHIBIT 1
E CONSTRUCTION CONTRACT
CONTRACT FORM E-1
PERFORMANCE BOND E-7
PAYMENT BOND E-10
RELEASE OF LIEN E-14
CHANGE ORDER FORM E-16
CONSENT OF SURETY/INCREASE OF PENALTY FORM E-17
DRUG-FREE WORKPLACE FORM E-19
F GENERAL CONDITIONS
ARTICLE 1 - CONTRACT F-1
ARTICLE 2 - DEFINITIONS F-1
ARTICLE 3 - ASSIGNMENT OF CONTRACT F-3
ARTICLE 4 - QUALIFICATIONS OF SUBCONTRACTORS
AND SUPPLIERS F-4
ARTICLE 5 - STARTING THE WORK F-4
ARTICLE 6 - INTERPRETATION AND INTENT OF THE
CONSTRUCTION DOCUMENTS F-4
ARTICLE 7 - REFERENCE POINTS F-5
ARTICLE 8 - BONDS AND INSURANCE AND INDEMNIFICATION F-6
ARTICLE 9 - CONTRACTOR'S RESPONSIBILITIES F-12
ARTICLE 10 - WORK BY OTHERS F-18
ARTICLE 11 - PROJECT OWNER'S STATUS
DURING CONSTRUCTION F-21
ARTICLE 12 - CHANGES IN THE WORK F-21
ARTICLE 13 - CHANGE OF CONTRACT AMOUNT/CONTRACT TIME F-22
ARTICLE 14 - CONDITION OF MATERIALS & PACKAGING F-28
ARTICLE 15 - ASBESTOS FREE MATERIALS F-28
ARTICLE 16 - WARRANTY/ACCEPTANCE OF DEFECTIVE WORK F-29
v
ARTICLE 17 – DELAYS AND EXTENSION OF TIME F-31
ARTICLE 18 - PAYMENT AND COMPLETION F-32
ARTICLE 19 - SUSPENSION OF WORK AND TERMINATION F-39
ARTICLE 20 - MAINTENANCE AND EXAMINATION OF RECORDS F-41
ARTICLE 21 – MINORITY/WOMEN OWNED BUSINESS ENTERPRISE
REQUIREMENTS AND SMALL BUSINESS PROVISIONS F-43
ARTICLE 22 - FEDERAL REQUIREMENTS F-46
ARTICLE 23 – VERBAL ORDERS F-46
ARTICLE 24 – MISCELLANEOUS F-47
ARTICLE 25 – CONTRACT CLAIMS F-49
ARTICLE 26 – VALUE ENGINEERING F-49
ARTICLE 27 – PATENTS AND ROYALTIES F-54
ARTICLE 28 – OWNER DIRECT PURCHASES F-55
ARTICLE 29 – PUBLIC RECORDS COMPLIANCE (APPLICABLE FOR
SERVICE CONTRACTS) F-55
G SUPPLEMENTAL CONDITIONS / SPECIAL PROVISIONS
NOT USED
H TECHNICAL PROVISIONS (SPECIFICATIONS)
DIVISION 1 – GENERAL REQUIREMENTS
01 01 00 – SUMMARY OF THE WORK
01 02 70 – PAYMENT APPLICATION
01 03 50 – MODIFICATION PROCEDURES
01 04 00 – PROJECT COORDINATION
01 07 00 – ABBREVIATIONS
01 09 50 – REFERENCE STANDARDS AND DEFINITIONS
01 20 00 – PROJECT MEETINGS
01 30 00 – SUBMITTALS
01 41 00 – TESTING LAB SERVICES
01 60 00 – MATERIALS AND EQUIPMENTS
01 63 10 – PRODUCTS SUBSTITUTIONS
01 70 00 – CLOSE OUT
01 74 00 – WARRANTIES AND BONDS
DIVISION 2 – SITE CONSTRUCTION (NOT USED)
DIVISION 3 – CONCRETE
03 30 00 – CAST-IN-PLACE CONCRETE
DIVISION 4 – MASONRY
04 22 00 – CONCRETE UNIT MASONRY
04 23 00 – GLASS UNIT MASONRY
DIVISION 5 – METALS
vi
05 31 00 – STEEL DECK
05 40 00 – STRUCTURAL COLD FORM METAL FRAMING
05 44 00 – COLD FORM METAL TRUSSES
DIVISION 6 – WOOD AND PLASTICS (NOT USED)
DIVISION 7 – THERMAL AND MOISTURE PROTECTION
07 21 00 – THERMAL INSULATION
07 41 13 – STANDING SEAM ROOF PANELS
07 46 46 – FIBER-CEMENT SOFFITS AND CEILINGS
07 62 00 – SHEET METAL FLASHING AND TRIM
07 92 00 – JOINT SEALANTS
DIVISION 8 – DOORS AND WINDOWS
08 11 13 – HOLLOW METAL DOORS AND FRAMES
08 33 23 – OVERHEAD COILING DOORS
08 51 13 – ALUMINUMFRAMED STOREFRONT WINDOWS
08 71 00 – DOOR HARDWARE
08 80 00 – GLAZING
08 91 19 – FIXED LOUVERS
DIVISION 9 – FINISHES
09 29 00 – GYPSUM BOARD
09 30 13 – CERAMIC TILING
09 51 23 – ACOUSTICAL TILE CEILINGS
09 67 23 – RESINOUS FLOORING
09 91 13 – EXTERIOR PAINTING
09 91 23 – INTERIOR PAINITING
DIVISION 10 – SPECIALTIES
10 14 00 – SIGNAGE
10 21 13 – PLASTIC TOILET COMPARTMENTS
10 28 00 – TOILET AND BATH ACCESSORIES
10 44 13 – FIRE EXTINGUISHER CABINETS
10 44 16 – FIRE EXTINGUISHERS
DIVISION 11 – EQUIPMENT (NOT USED)
DIVISION 12 – FURNISHINGS (NOT USED)
DIVISION 13 – SPECIAL CONSTRUCTION (NOT USED)
DIVISION 14 – CONVEYING SYSTEMS (NOT USED)
DIVISION 22 – PLUMBING
vii
22 05 00 – COMMON WORK RESULTS FOR PLUMBING
22 05 29 – HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
22 05 53 – IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 07 00 – PLUMBING INSULATION
22 11 16 – DOMESTIC WATER PIPING
22 11 19 – DOMESTIC WATER PIPING SPECIALTIES
22 11 23 – DOMESTIC WATER PUMPS
22 13 16 – SANITARY WASTE AND VENT PIPING
22 13 19 – SANITARY WASTE PIPING SPECCIALTIES
22 33 00 – ELECTRIC DOMESTIC WATER HEATERS
22 40 00 – PLUMBING FIXTURES
22 47 00 – DRINKING FOUNTAINS AND WATER COOLERS
DIVISION 23 – MECHANICAL
23 05 00 – COMMON WORK RESULTS FOR HVAC
23 05 10 – BASIC MECHANICAL REQUIREMENTS
23 05 29 – HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
23 05 48 – VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 53 – IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 – TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 – HVAC INSULATION
23 09 00 – INSTRUMENTATION AND CONTROL FOR HVAC
23 23 00 – REFRIGERANT PIPING
23 05 00 – COMMON WORK RESULTS FOR HVAC
23 31 13 – METAL DUCTS
23 31 16 – NON METAL DUCTS
23 33 00 – AIR DUCT ACCESSORIES
23 34 23 – HVAC POWER VENTILATORS
23 37 13 – DIFFUSERS, REGISTERS, AND GRILLES
23 63 13 – AIR COOLED CONDENSING UNITS – RESIDENTIAL
23 81 26 – SLIP-SYSTEM AIR-CONDITIONERS (MINI SLIPT)
23 82 18 – AIR HANDLING UNITS - RESIDENTIAL
DIVISION 26 – ELECTRICAL
26 05 00 - COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 - LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 - HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 - RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
26 05 53 - IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 09 23 - LIGHTING CONTROL DEVICES
26 22 00 – LOW-VOLTAGE TRANSFORMERS
26 24 16 - PANELBOARDS
26 27 13 - ELECTRICITY METERING
26 27 26 - WIRING DEVICES
26 28 13 - FUSES
26 28 16 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
viii
26 41 13 - LIGHTNING PROTECTION FOR STRUCTURES
26 43 13 - TRANSIENT VOLTAGE SUPPRESSION FOR LOW-VOLTAGE
ELECTRICAL POWER CIRCUITS
26 51 00 - INTERIOR LIGHTING
26 56 00 - EXTERIOR LIGHTING
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 11 – SECURITY AND FIRE ALARM SYSTEM
DIVISION 31 – EARTHWORK
31 21 10 – SITE CLEARING
31 22 00 – EARTHWORK
31 22 10 – EARTHWORK – UNDERGROUND UTILITIES
31 22 14 – PAVEMENT REMOVAL AND REPLACEMENT
31 22 70 – EROSION AND SEDIMENTATION
31 25 10 – SUBGRADE STABILIZATION
31 25 11 – SOIL CEMENT
31 25 12 – LIMEROCK
31 25 13 – ASPHALT CONCRETE PAVING
31 25 20 – PORTLAND CEMENT CONCRETE PAVING
31 25 80 – CONCRETE CURBS AND WALKS
31 26 66 – POTABLE WATER SYSTEMS
31 27 30 – SANITARY SEWAGE SYSTEMS
31 28 31 – CHAIN LINK FENCING AND GATES
DIVISION 32 – EXTERIOR IMPROVMENTS
32 84 00 – PLANTING IRRIGATION
32 92 00 – TURFS AND GRASSES
32 93 00 – PLANTS
DIVISION 33 – UTILITIES (NOT USED)
END OF TECHNICAL SPECIFCATIONS
INDEX OF DRAWINGS
Drawing Number Drawing Name
G-000 COVER SHEET
C-001 OVERALL EXISTING SITE PLAN
C-002 DETAIL DEMOLITION + EROSION CONTROL PLAN
C-003 DETAIL DEMOLITION + EROSION CONTROL PLAN
C-004 DETAIL DEMOLITION + EROSION CONTROL PLAN
C-005 DETAIL DEMOLITION + EROSION CONTROL PLAN
C-006 DETAIL DEMOLITION + EROSION CONTROL PLAN
C-100 OVERALL SITE DEVELOPMENT PLAN
C-101 GEOMETRY PLAN
C-102 GEOMETRY PLAN
ix
C-103 DETAIL SITE DEVELOPMENT PLAN
C-104 DETAIL SITE DEVELOPMENT PLAN
C-200 OVERALL GRADING + DRAINAGE PLAN
C-201 DETAIL OFF-SITE POND GRADING + DRAINAGE PLAN
C-202 DETAIL GRADING + DRAINAGE PLAN
C-203 DETAIL OFF-SITE GRADING + DRAINAGE PLAN
C-204 DETAIL OFF-SITE GRADING + DRAINAGE PLAN
C-301 UTILITY PLAN
C-302 UTILITY PLAN
C-401 SITE DETAILS
C-402 SITE DETAILS
C-403 STORMWATER POND DETAILS
C-404 SITE DETAILS
C-405 SITE DETAILS
C-406 SITE DETAILS
C-407 ORANGE COUNTY UTILITY DETAILS
C-408 ORANGE COUNTY UTILITY DETAILS
C-409 ORANGE COUNTY UTILITY DETAILS
C-410 LIFT STATION DETAILS
C-501 ROADWAY + DEMOLITION PLAN – BISSEL STREET
C-502 ROADWAY PLAN – BISSEL STREET
C-503 ROADWAY PLAN / PROFILE – BISSEL STREET
C-504 SIGNAGE + PAVEMENT MARKING PLAN – BISSEL STREET
C-505 NEW UTILITY PLAN – BISSEL STREET
S-100 GENERAL NOTES
S-101 SCHEDULES
S-102 FOUNDATION PLAN
S-103 ROOF FRAMING PLAN
S-104 TYPICAL CONCRETE DETAILS
S-105 SECTIONS & DETAILS
S-106 SECTIONS & DETAILS
S-107 SECTIONS & DETAILS
A-001 ARCHITECTURAL INFORMATION
A-101 FLOOR PLAN, ROOF PLAN AND FINISH LEGEND
A-102 REFLECTED CEILING PLAN AND CEILING LEGEND
A-201 EXTERIOR ELEVATIONS
A-301 BUILDING SECTION
A-401 WALL SECTION
A-501 DETAILS
A-502 DETAILS
A-503 TOILET PARTITION DETAILS
A-504 DOOR SCHEDULE AND DETAILS
A-505 WINDOW SCHEDULE AND DETAILS
M-001 HVAC GENERAL NOTES SYMBOLS AND SCHEDULES
M-101 FLOOR PLAN - HVAC
M-501 HVAC DETAILS
P-001 PLUMBING GENERAL NOTES, SYMBOLS AND SCHEDULES
x
P-101 FLOOR PLAN PLUMBING – SANITARY
P-102 FLOOR PLAN PLUMBING – DOMESTIC WATER
P-301 PLUMBING RISER DIAGRAMS
P-501 PLUMBING DETAILS
ES-101 OVERALL SITE PLAN ELECTRICAL
ES-102 PARKING LOT AND ROADWAY PHOTOMETRICS
ES-103 BALLFIELD PHOTOMETRICS
ES-104 BALLFIELD PHOTOMETRICS
ES-105 BALLFIELD PHOTOMETRICS
ES-106 CONTROLS SUMMARY
ES-107 ELECTRICAL SITE DETAILS AND SCHEDULES
E-001 GENERAL NOTES, SYMBOL LIST AND LIGHTING FIXTURE
SCHEDULE
E-101 FLOOR PLAN LIGHTING
E-201 FLOOR PLAN POWER AND SYSTEMS
E-301 PANE SCHEDULE AND POWER RISER DIAGRAM
THIS PAGE INTENTIONALLY LEFT BLANK
ISSUED: January 10, 2022
NOTICE
INVITATION FOR BIDS NO. Y22-764-FH
PARKS DR. PHILLIPS/ORANGE COUNTY PUBLIC SCHOOLS (OCPS) FUTURE
MIDDLE SCHOOL JOINT BALLFIELD PARK
Sealed bid offers (Original Bid Form and one (1) complete copy) for furnishing the above will be accepted up to 4:00 PM, February 10, 2022 via the electronic submission portal at: https://secure.procurenow.com/portal/orangecountyfl, or in the Procurement Division; Internal Operations Centre II, 400 E. South Street; 2nd Floor, Orlando, FL 32801. Bids will be opened per the public meeting notice.
Bid Documents are available in the following formats:
1. Please visit the following link to access this Invitation for Bids, opportunities are listed by number and title.
https://secure.procurenow.com/portal/orangecountyfl
2. Complete bid documents may be obtained from the Procurement Division, Internal Operations Centre II, 400 E. South Street, 2nd floor, Orlando, FL 32801.
Phone (407) 836-5635. The documents are available for a cost of $75 non-refundable.
3. A printed copy of the basic solicitation documents and a CD containing the construction plans and specifications are available for a cost of $10 per CD non-refundable.
A Non-Mandatory Virtual Pre-Bid Conference will be held on January 20, 2022, at 10:00 AM.
NON-MANDATORY PRE-PROPOSAL CONFERENCE MEETING LINK
https://ocfl.webex.com/ocfl/j.php?MTID=me491a558c6e31f62a23eaae02d9bcdf7
Meeting number: 2464 784 7820 Password: Go2Meeting
More ways to join:
Join by video system Dial 24647847820@ocfl.webex.com You can also dial 173.243.2.68 and enter your meeting number.
Join by phone 1-408-792-6300 Call-in number (US/Canada) Access code: 2464 784 7820
SCOPE OF WORK: Build four ballfields concessions/storage/restroom building/storm drainage and parking/entrance road on the proper site and six acres of developer provided land.
PROJECT LOCATION: 10496 Bissell Street, Orlando, FL 32836.
Carrie Mathes, MPA, CFCM, NIGP-CPP, CPPO, C.P.M., CPPB, A.P.P.
Manager, Procurement Division https://secure.procurenow.com/portal/orangecountyfl https://ocfl.webex.com/ocfl/j.php?MTID=me491a558c6e31f62a23eaae02d9bcdf7
C-1
PART C - INSTRUCTIONS TO BIDDERS
1. GENERAL:
The term County used herein refers to Orange County, Florida, or its duly authorized representative. The term Bidder used herein refers to the manufacturer, dealer or business organization submitting a bid to the County in response to this Invitation for Bids.
2. PREPARATION AND SUBMISSION OF BIDS:
a. Form of Proposal: Each Bidder shall submit the bid in four parts (original Bid Form, marked original, with attachments, one (1) copy and one (1) electronic copy on USB drive, of the Bid Form and all attachments) and indicate the base bid price and any alternative(s) that may be included in the proper space(s).
The estimated total base bid is the sum of all pay item totals and the
County reserves the right to correct errors in pay item totals arising from incorrect extensions. See "Bid Errors", Item 5.
b. All bids may be submitted via the electronic submission portal at:
https://secure.procurenow.com/portal/orangecountyfl, or in the Procurement Division; Internal Operations Centre II, 400 E. South Street;
2nd Floor, Orlando, FL 32801, prior to the submission timeline as specified in Part B. Bids will be opened per the public meeting notice.
Bids received after the date and time specified will be returned unopened.
The time/date stamp clock located in the Procurement Division shall serve as the official authority to determine lateness of any bids.
Respondents are cautioned that they are responsible for delivery to the specific location cited above. Therefore, if your bid, proposal or quotation is delivered by an express mail carrier or by any other means, it is your responsibility to ensure delivery to the above address. This office will not be responsible for deliveries made to any place other than the specified address.
The delivery of said bid to the Procurement Division prior to the time and date stated in Part A is solely and strictly the responsibility of the Bidder.
The County shall not be responsible for delays in delivery to the Procurement Division caused by the United States Postal Service or courier service, delivery to any other County Office or delays caused by any other occurrence. The bid delivery time will be scrupulously observed. Under no circumstances will bid proposals delivered after the delivery time specified be considered.
The decision to refuse to consider a bid or proposal that was received beyond the date/time established in the solicitation shall not be the basis for a protest pursuant to the Orange County Code (Procurement Ordinance).
C-2
Bidders should indicate on the sealed envelope the following:
1. Invitation for Bids Number
2. Due Date of Bid Submittals
3. Name of Bidder
4. Return Address of the Bidder
c. Bids will be publicly opened in accordance with this public notice.
d. All bid must be manually and duly signed by an authorized corporate officer, principal, or partner (as applicable) with his signature in full. When a firm is a Bidder, the bids shall be signed in the name of the firm by one or more of the partners. When a corporation is a Bidder, the officer signing shall set out the corporate name in full beneath which he shall sign his name, give title of his office and affix the corporate seal. Anyone signing the bid proposal as agent must file with it legal evidence of his authority to do so. Bidders who are nonresident corporations shall furnish to the County a duly certified copy of their permit to transact business in the State of Florida along with the Bid. Failure to promptly submit this evidence or qualification to do business in the State of Florida may be basis for rejection of the Bid.
e. The Bidder is solely responsible for reading and completely understanding the requirements and the specifications of the solicitation.
f. Bids may be withdrawn by written or telecopied requests dispatched by the Bidder and received by the Manager of the County Procurement Division before the time for receiving bids has expired. Negligence on the part of the Bidder in preparing a bid is not grounds for withdrawal or modification of a bid after such bid has been opened by the County. A Bidder may not withdraw or modify a bid after the appointed bid opening and such bid must be in force for one hundred twenty (120) days after the bid opening. Bidders may not assign or otherwise transfer their bids.
g. At the time and place fixed for the opening of bids, every bid properly delivered within the time fixed for receiving bids will be opened and publicly read aloud, irrespective of any irregularities found therein.
Bidders and other persons interested may be present, in person or by representative, or attend via telephone or virtually.
h. A Bid, Payment and Performance Bond are a requirement of the IFB when the bid/contract amount exceeds $100,000. Firms utilizing electronic submission shall attach an electronic copy of their bid bond for responsiveness. Submission of the bid bond, along with a certified and effectively dated copy of the power of attorney, shall be completed and signed by all required parties and submitted on the form provided in the solicitation. Submittal of a bid bond less than 10% of the total estimated Contract amount for the first Contract year, shall result in the bid being deemed non-responsive.
C-3
If Bid security is required by Paragraph h. of this Section, submission of an electronic Bid Bond completed and signed by all required parties and submitted on the form provided in Exhibit 1 to the Bid Proposal (Part D), or in the alternative, a Certified Check, or a Cashier's Check shall be required to accompany each bid proposal in a stated dollar amount of not less than ten (10%) percent of the sum of the computed total amount of the Bidder's Base Bid proposal. Submittal of a Bid Bond less than 10% of the bid sum shall result in rejection of the bid. Failure to submit the Bid Bond on the form provided in Exhibit 1 to the Bid Proposal (Part D) shall result in rejection of the bid.
In order to be acceptable to the County, the Surety company issuing the Bid Bond as called for in this Invitation for Bids, shall meet and comply with the minimum standards described in Part C, Section 19, “Qualifications of Surety Companies”. Failure to submit a Bid Bond from a Surety Company meeting these minimum standards shall result in rejection of the bid.
Certified checks or cashier's checks shall be drawn on a solvent bank or trust company to the order of the Board of County Commissioners, Orange County, Florida and shall have all necessary documentary revenue stamps attached, if required by law. Personal checks are not acceptable to the County. See Section 19, “Qualifications of Surety Companies” for additional requirement.
i. A Pre-Bid Conference will be held at the time and location shown in the
Notice, Part B of this Bid package.
j. No oral interpretation of the meaning of the plans, specifications, or other
Contract documents shall be considered binding. All questions or concerns regarding this Invitation for Bids shall be submitted by email to Rolando.Melo@ocfl.net, no later than 5:00 PM on January 26, 2022, referencing the IFB number.
Any and all such interpretations and any supplemental instructions will be in the form of a written addendum which, if issued, will be available for download. All addenda so issued shall become part of the Contract Documents and receipt shall be acknowledged on the Bid Form, Part D or by completion of the applicable information on the addendum and returning it not later than the date and time for receipt of the bid.
k. Before submitting bids, Bidders must carefully examine the site of the proposed work and make all necessary investigations to inform themselves thoroughly as to all difficulties involved in the completion of all work required pursuant to the mandates and requirements of this bid package.
mailto:Fabio.Henao@ocfl.net
C-4
No plea of ignorance of conditions or difficulties that may hereafter exist, or of conditions or difficulties that may be encountered in the execution of the work pursuant to this bid package as a result of failure to make the necessary examinations and investigations will be accepted as an excuse for any failure or omission on the part of the successful Bidder (Contractor) to fulfill, in every detail, all of the requirements of the Contract Documents, nor will they be accepted as a basis for any claims whatsoever for extra compensation or for an extension of time.
l. Firms and/or individuals that assisted in the development or drafting of the specifications, requirements, statements of work, or solicitation documents contained herein are excluded from competing for this solicitation.
This shall not be applicable to firms and/or individuals providing responses to a publicly posted Request for Information (RFI) associated with a solicitation.
3. MINORITY/WOMEN OWNED BUSINESS ENTERPRISES:
a. To provide for the participation of certified minority and women owned businesses (M/WBE’s) in the County’s procurement of construction services, Bidders submitting bids to the County are urged to comply with M/WBE subcontracting goals established by the County Minority/Women Business Enterprise Ordinance, No. 94-02 and amended by Ordinance No.2009-21. The overall goal for all bids (inclusive of all additive and deductive alternates) is 20% participation of the contract value for this contract for M/WBE subcontractors and suppliers. Upon Contract award the Contractor must meet the M/WBE expenditure required by the Contract. Each M/WBE utilized to meet the project goal must be listed as a subcontractor on Attachment C-2. If there are any pre-qualifications required by the firm, then this must be provided to the M/WBE when they are solicited for interest in the bid. This required information must be completed prior to bid submittal.
The Ordinance also addresses minority/women group employment levels setting goals to encourage each Bidder to maintain 18% minority and 6% women employees.
Note: Only 50% of material/supply dollars purchased from M/WBE distributors is applied toward the goals for minority and women business enterprise participation on construction projects. Contractor shall list the total amount of material/supply dollars to be purchased from each M/WBE distributor on the Subcontractor/Supplier Page (Attachment C-2).
The County will calculate the actual dollars applied toward the goals.
b. NOTICE: Goals for bids under $100,000
There are M/WBE goals for all bids including bids for IFB estimated to be less than $100,000 (inclusive of all additive and deductive alternates).
C-5
c. All participating M/WBE's must be certified by Orange County. The Business Development M/WBE Directory is available by e-mail or through the Orange County web site at Orangecountyfl.net.
Only firms having established offices in the Orlando MSA (Orange, Lake, Seminole and Osceola Counties) are eligible for Orange County certification.
All firms must be certified prior to bid opening and must be certified in the area(s) for which they will be used. If a firm claims to be certified, but is not listed in the Directory, Contractor should obtain a copy of their Certificate and/or contact the Business Development Division Liaison for verification of certification.
d. M/WBE Bidders competing as primes
If an M/WBE firm bidding as a prime certifies with his/her bid that it will self-perform 51% percent or more of the project, as evidenced by Attachment C-2, then that firm will not be required to comply with the M/WBE subcontracting goals.
Failure to include the percentage of work and the scope of work to be self-performed, and the dollar amount for the work an M/WBE Bidder competing as a prime intends to self-perform will result in the M/WBE Bidder receiving zero M/WBE participation for the bid.
However, if the M/WBE Bidder will not be self-performing at least 51% percent of the project, then he/she must comply with the M/WBE participation goal, and good faith effort documentation required from non-M/WBE Bidders to receive M/WBE compliance consideration.
e. Subcontracts/Purchase Orders
The successful Bidder shall provide a copy of all fully executed subcontracts and/or purchase orders issued to M/WBE’s listed on Attachment C-2 to the Business Development Division Liaison. Submittal of these subcontracts/purchase orders is a condition precedent to execution of the prime Contract by the County.
The Contractor must include in the subcontract agreement:
1.) Prompt Payment Clause to the M/WBE subcontractor.
2.) Payment schedule in all subcontracts and purchase orders (including those with non M/WBE's) stating that payment will be made to the Subcontractor/suppliers within 72 hours of receipt of payment from the County.
3.) The sub-contract agreement shall include: (a) the percentage of the overall contract value; and (b) the dollar amount based on the percentage of the contract value (if available at the time of the sub-contract agreement).
C-6
4.) The following statement: “It is the M/WBE responsibility to submit the required subcontractor’s Monthly M/WBE workforce reports to the prime, monthly payment verification and Final M/WBE payment verification form to Business Development Division.”
The M/WBE’s failure to submit the required documents could negatively impact their M/WBE re-certification.
5.) Notwithstanding any termination provisions in this Subcontract
Agreement, the Prime Contractor shall not terminate this Subcontract Agreement without prior written authorization of the Orange County Business Development Division Manager, nor shall the Prime Contractor amend this Subcontract Agreement, or reduce the Scope of Work or monetary value awarded under this Subcontract Agreement, without prior written authorization of the Orange County Business Development Manager.
6.) All sub-contract agreements shall be contingent upon the term
(whether terminated, renewed or extended) of the Prime’s contract with the County.
The awarded prime contractor’s responsibilities and requirement are as follows:
i. File copies of all executed subcontracts/agreements between the prime and all M/WBE subcontractors on the project to Orange County Business Division one time for the duration of the contract.
ii. The Contractor shall submit an updated Prime Monthly Contractor’s Workforce Report, Subcontractor’s Workforce Report and Monthly Prime Contractor’s Report for all construction contracts monthly, and any additional reports deemed by the County as necessary for M/WBE subcontractor utilization reporting purposes.
iii. The Contractor shall notify the Business Development Division of any additional awards to the M/WBE firm on the Contractor’s team and the addition of any new M/WBE firm to the Contractor’s team on the project.
iv. The Contractor shall expeditiously advise all M/WBE’s and the Business Development Division of all change orders, contract modifications, additions and deletions to any and all contracts issued to the M/WBE(s) on the team.
v. Furnish copies of subcontracts/purchase orders for the non-M/WBE’s listed on Attachment C-2. Also, provide a list of all non-M/WBE subcontractors and suppliers that have a prompt payment clause included in their subcontract agreement or purchase order.
vi. Notwithstanding any termination provisions in this Subcontract Agreement, the Prime Contractor shall not terminate this Subcontract Agreement without prior written authorization of the Orange County Business Development Division Manager, nor shall the Prime Contractor amend this Subcontract Agreement, or reduce the Scope of Work or monetary value awarded under this Subcontract
C-7
Agreement, without prior written authorization of the Orange County Business Development Manager.
Execution of the contract between Orange County and the bidder shall be contingent upon the filing of executed subcontract(s) between the bidder and the M/WBE subs listed on Form C-2 and included on Form C-3 with the Business Development Division.
The County may, at its discretion, require copies of subcontracts/purchase orders for the non-M/WBE's listed on Attachment C-2. However, if this option is not exercised, the awarded Contractor must provide a list of all non-M/WBE Subcontractors and suppliers certifying that a prompt payment clause has been included in that Contract or purchase order.
f. Good Faith Effort Documentation Requirements -
If the established goals (reference paragraph 3.a above) are not achieved, to maximize consideration for MWBE participation, Bidders must provide with the bid sufficient documentation to substantiate that ALL FIVE of the mandatory efforts listed below were undertaken. Bidders meeting or exceeding the goals need not provide good faith effort documentation. If the bidder does not achieve the M/WBE goal, Good Faith Effort documentation is required. If Good Faith Effort documentation is not submitted to address all five (5) requirements, the bid shall be deemed non-responsive.
i. If a bidder desires to meet the good faith effort documentation requirements he/she must provide written notice to certified M/WBEs, as it relates to the scopes of services in the bid documents, that the Bidder intends to subcontract. The notice shall be by e-mail or fax, no fewer than seven (7) calendar days prior to bid opening. All e-mails and faxes shall include the legal name of the M/WBE firm. The notice shall advise the M/WBE’s:
a. that their interest in the contract is being solicited;
b. of the specific work the Bidder intends to subcontract
c. how to obtain information about and review the contract plans and specifications;
d. about information on bonding, insurance and other pertinent requirements;
All requirements as it relates to the bonding, insurance and pre-qualifications must be given to the M/WBE’s at the time the notice is provided. This information must be received and decisions to utilize the M/WBE must be known and denoted on Attachment C-2 prior to the bid submittal.
e. the deadline for bid or proposal submissions to the Bidder and the bid due date to the County;
C-8
f. 24 hours notice of any addenda.
ii. If M/WBE goals were not achieved the bidder shall provide an explanation as to why the scope of services listed in the bid documents were not subcontracted on Attachment C-2.
iii. Bidders shall follow up initial submittals of interest by contacting
M/WBEs and documenting using a contact log, which shall include the firm's name address, contact information (e-mail, telephone and/or fax numbers), scope of work requested, the date, name of person making the effort, denote if M/WBEs will bid, time quote received and notes denoting if plans and specifications were sent.
Each bidder shall use the standardized contact log, Attachment C- 4.
iv. In instances where a non-minority/non-woman contractor is listed for work for which M/WBE availability exists, the Bidder shall submit ALL quotations received from M/WBE’s AND the listed non-M/WBE within twenty-four (24) hours, if it is determined that the bidder is one of the three (3) apparent low Bidders. The Bidder shall provide an explanation as to why the M/WBE’s quotations were not accepted.
Receipt of a lower quotation from a non-M/WBE prior to bid opening will not in itself excuse a Bidder's failure to meet M/WBE participation goals. However, a Bidder's good faith effort obligation does not require a Bidder to accept a quotation from a M/WBE which is an unreasonable price. For the purpose of this subsection, "unreasonable price" means a price above (or below) competitive levels which cannot be attributed to the M/WBE’s attempt to cover costs inflated by the present effect of discrimination.
v. The Contractor shall contact the Business Development Division staff as a resource to obtain M/WBE participation.
If the Bidder fails to meet one of the first four good faith effort requirements listed above (i – iv), the substitution will only count towards one good faith effort requirement and all other good faith requirements must be met. The substitution is from the following:
(1) The Disney Entrepreneur Center (DEC) was used to host a workshop that informed M/WBE firms how to better prepare for sub-contracting opportunities;
(2) The Contractor has participated in Orange County Business Development
Division’s sponsored “How to do Business” workshop;
(3) The Contractor has sponsored a match-maker event with certified M/WBE firms. Enclose a copy of the certificate provided to your firm when the service was successfully completed.
C-9
If, after Contract award, Prime Contractors who have not achieved the M/WBE participation goals choose to subcontract work indicated as being self-performed without prior written approval of the Business Development Division (reference Part F, Article 21, paragraph D), the matter will be reported to the Procurement Division with an appropriate responsibility recommendation for consideration in the event the contractor competes for future County contracts.
g. Letters of Intent must match exactly the information provided on Attachment C- 2 of the Bid Forms and must be executed by the apparent low Bidder for all M/WBE Subcontractors and/or suppliers listed. The letter(s) of intent must be submitted to the Business Development Division office before 5:00 P.M. on the second business day after bid opening. The non-submission of the Letter of Interest by the deadline will result in the low bidder being found non-responsive for failure to meet the M/WBE subcontractor utilization goal. In the event the lowest bidder is not the recommended bidder, then letters of intent must be obtained from the recommended bidder two business days after being contacted.
h. Bidders shall not reject an M/WBE as unqualified without sound reasons based on a thorough and documented investigation of that M/WBE's capabilities.
i. Bidder's efforts will be evaluated considering the ability of other Bidders to meet the requirements relating to the use of M/WBE subcontractors.
j. Bidders should make whatever additional efforts are necessary to achieve the goals and it is recommended that these efforts be documented. However, this documentation shall not replace the required documentation if the goals are not met.
Bidders are encouraged to contact the Business Development Division through the Orange County Procurement Division for guidance and assistance. Additional efforts by Bidders may include but are not limited to the following:
i. Bidders should provide interested M/WBE's with assistance in reviewing the Contract plans and specifications.
ii Bidders should assist interested M/WBE's in obtaining required lines of credit, insurance or bonding.
iii. Bidders should solicit only types of work that match the capabilities of the M/WBE's and for which they are certified.
k. The County has a graduate program. Under this program, utilization of M/WBE firms designated as graduates shall count toward meeting M/WBE participation goals only on specified projects. All construction solicitations for which the County has determined the overall contract amount to be awarded to the prime in excess of $10,000,000 for vertical construction, $7,000,000 for horizontal construction and $7,000,000 for all other construction are eligible for graduate M/WBE participation.
C-10
Vertical construction is any construction of a structure or building which requires a general or building contractor’s license. Horizontal construction includes but is not limited to roadwork, site work, drainage or utilities work.
Other construction is any construction other than what is defined as vertical or horizontal construction.
The Bidder’s total base bid, which is used by the Procurement Division as the basis for determining Contract award value, will be used to determine if graduated M/WBE firms are eligible to participate. If the contract has option provisions, the total base Bid is the total of the Basic Contract Year plus all Option Years. Prime contractors will receive full M/WBE credit for the use of graduated M/WBE’s that meet all other requirements.
It is the Bidder’s responsibility to ensure that graduate M/WBE’s are not listed in bid to meet M/WBE participation requirements on projects in which they are not eligible to participate.
Intentional failure to attempt compliance and/or intentional failure to comply with the M/WBE subcontract goals pursuant to the Minority/Women Business Enterprise Ordinance, may result in the County invoking penalties under that ordinance and/or a finding by the County that a Bidder is "non-responsible", thus resulting in that bid being rejected and the Bidder facing possible suspension or debarment from future County IFB's.
4. BID PREFERENCE FOR REGISTERED SERVICE-DISABLED VETERANS (SDV)
PRIME
The Orange County Registered Service-Disabled Veteran Business Program
Ordinance sets vendor preferences for registered service-disabled veteran business enterprises registered with Orange County Business Development Division.
Also, in accordance with the County SDV Ordinance, preferences for registered service-disabled veteran business enterprises shall be applied on bid awards (sealed bids). The following bid preference scale shall apply to bids submitted by Prime registered service-disabled veteran business enterprises as long as the bid does not exceed the low bid by more than 8% on bid awards up to $100,000;
7% on bid awards from $100,000.01 to $500,000; 6% on bid awards from $500,00.01 to $750,000; 5% on bid awards from $750,000.01 to $2,000,000; 4% on contract awards from $2,000,000.01 to $5,000,000.00 and 3% on bid awards over $5,000,000.01.
Prime registered service-disabled veteran business enterprises may be awarded or recommended for award of contracts when their bids are within the above allowed percentage in comparison to the low responsive and responsible bid(s).
If a prime registered service-disabled veteran business enterprise, entitled to the vendor preference under this section, and one (1) or more other businesses also entitled to this preference, or another vendor preference provided by the Orange County Code, submit bids, proposals, or replies for procurement of commodities or contractual services which are otherwise equal with respect to all relevant considerations, including price, quality, and service, then the Procurement
C-11
Division Manager shall award the procurement or contract to the business having the smallest net worth.
5. BID ERRORS:
Where bid forms have erasures or corrections, each erasure or correction must be initialed in ink by the Bidder. In case of unit price bid items, if an error is committed in the extension of an item, the unit price as shown in the Official Bid Form will govern. Errors between any sum, computed by the Bidder, and the correct sum thereof will be resolved in favor of the correct sum. Any discrepancy between words and numbers will be resolved in favor of the written words.
6. DEVIATIONS:
Bidders are hereby advised that Orange County will only consider bid Proposals that meet the specifications and other requirements imposed upon them by this bid package. In instances where a deviation is stated in the bid form, said bid will be subject to rejection by the County in recognition of the fact that said bid Proposal does not meet the exact requirements imposed upon the Bidder by the Contract Documents.
7. SUBSTITUTE MATERIAL AND EQUIPMENT:
The Contract, if awarded, will be on the basis of material and equipment described in the Drawings or specified in the Specifications without consideration of possible substitute or "or-equal" items. Whenever materials or equipment or patented processes are specified or described in the Contract Documents by naming a trade name, manufacturer, supplier or proprietary item or catalog number, the naming of the item is intended to establish the type, function and quality required and to establish a basis for bidding.
Substitute materials or equipment may be considered after a Contract for the Work is executed if sufficient information is supplied by Contractor to allow Project Manager to evaluate the proposed substitution, unless the naming of the item is followed by words indicating that no substitution is permitted. The procedure for submittal of any such application by Contractor and consideration by Project Manager is set forth in the General Conditions.
In the event that substitute materials or equipment are used and are less costly than the originally specified material or equipment, then the difference in cost of the item shall benefit the County and Contractor in equal proportions.
Applications for substitute materials and equipment shall only be evaluated after the Contract is executed. The Base Bid and Alternates shall reflect the costs for the materials and equipment named or specified only.
8. REQUESTED INFORMATION AND DESCRIPTIVE LITERATURE:
Bidders must furnish all requested information in the spaces provided on the bid form or attachments thereto. Additionally, where required pursuant to the provisions of this bid package, Bidders must submit with their bid proposal cuts, C-12 sketches, descriptive literature and/or complete specifications relative to the items proposed and offered.
9. AWARD OF CONTRACT/REJECTION OF BIDS:
The Board of County Commissioners will award a Contract to the low, responsive and responsible Bidder, price and other factors considered. The County will award one Contract for this requirement. The Board of County Commissioners, in its sole discretion, reserves the right to reject any and all bids and to waive any informality concerning bid proposals whenever such rejection or waiver is in the best interest of the County. The ability of a Bidder to obtain a performance bond and a payment bond shall not be regarded as the sole test of such Bidder's competency or responsibility. Nothing contained herein shall place a duty upon the County to reject bids or award a Contract based upon anything other than its sole discretion as described herein.
When more than one method of work is prescribed in the solicitation with separate pricing allowed for each method, the County will select the method determined to be in its best interests, price and other factors considered.
Determination of the low Bidder when additive or deductive bid items are involved shall be as follows:
A. ADDITIVE/DEDUCTIVE BID ITEMS:
1. If it is deemed to be in the best interest of the County to accept the additive or deductive items, award will be made to the Bidder that offers the lowest aggregate amount for the base bid, plus or minus (in the order listed on the bid form), those additive or deductive bid items that provide the most features of the work.
2. All bids will be evaluated on the basis of the same additive or deductive bid items.
3. Failure of the Bidder to provide pricing for all unit priced items and/or the
Base Bid and ALL requested additive/deductive bid items, or alternate bids shall be cause for rejection of the bid as non-responsive.
B. RECIPROCAL LOCAL PREFERENCE:
In the event the lowest responsive and responsible bid submitted in response to any Invitation for Bids is by a bidder whose principal place of business is in a county other than Orange County, and such county grants a bid preference for purchases to a bidder whose principal place of business is in such county, then Orange County may award a preference to the (next) lowest responsive and responsible bidder having a principal place of business within Orange County, Florida. Such preference will be equal to the preference granted by the county in which the lowest responsive and responsible bidder has its principal place of business except as provided below.
C-13
1. Effective July 1, 2015 the reciprocal local preference will not apply to construction services in which 50 percent or more of the cost will be paid from state-appropriated funds which have been appropriated at the time of the competitive solicitation.
2. If the solicitation involves a federally funded project where the funding source requirements prohibit the use of state and/or local preferences, the reciprocal local preference will not be applied.
10. POSTING OF RECOMMENDED AWARD AND PROTESTS:
The recommended award will be posted for review by interested parties at the
Procurement Division and at http://apps.ocfl.net/OrangeBids/AwardsRec/default.asp prior to submission through the appropriate approval process and will remain posted for a period of five full business days.
Failure to file a protest to the Procurement Division Manager by 5:00 PM on the fifth full business day after the posting date shall constitute a waiver of bid/proposal protest proceedings.
Additional information relative to protests can be found at:
http://www.orangecountyfl.net/VendorServices/VendorProtestProcedures.aspx
A lobbying blackout period shall commence upon issuance of the solicitation until the Board selects the successful Bidder. For procurements that do not require Board approval, the blackout period commences upon solicitation issuance and concludes upon Contract award. Additional information relative to lobbying can be found at:
http://www.orangecountyfl.net/OpenGovernment/LobbingAtOrangeCounty.aspx
The Board of County Commissioners may void any Contract where the County
Mayor, one or more County Commissioners, or a County staff person has been lobbied in violation of the blackout period restrictions of Ordinance No. 2002-15.
11. CONTRACT DOCUMENTS:
The Contract Documents shall include the documents stated in the Contract (Titles, Subtitles, Headings, Running Headlines, Table of Contents and Indexes are used merely for convenience purposes).
12. MODIFICATION/ALTERATION OF SOLICITATION AND OR CONTRACT
DOCUMENTS:
Modification or alteration of the documents contained in this solicitation or the contract resulting from this solicitation shall only be made upon receipt of prior written consent of the County.
13 LAWS AND REGULATIONS:
The Bidder's attention is directed to the fact that all applicable Federal and State laws, municipal and County ordinances, and the rules and regulations of all http://apps.ocfl.net/OrangeBids/AwardsRec/default.asp http://www.orangecountyfl.net/VendorServices/VendorProtestProcedures.aspx http://www.orangecountyfl.net/OpenGovernment/LobbingAtOrangeCounty.aspx
C-14 authorities having jurisdiction over any part of the project shall apply to the solicitation and Contract throughout, and they will be deemed to be included in the solicitation/Contract the same as though herein written.
14. REQUIRED DISCLOSURE:
Bidder shall disclose with its bid submission all material facts pertaining to any felony indictments or convictions in the last ten (10) years, or any pending felony charges, anywhere in the United States against (i) Bidder, (ii) any business entity related to or affiliated with Bidder, or (iii) any present or former executive employee, senior management, key employee, officer, director, stockholder, partner or owner of Bidder or of any such related or affiliated entity, collectively referred to as “Bidder.” This disclosure shall not apply to any person or entity who is, or was, solely a stockholder, owning less than 5% of the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .