Y22-7028-RC_Apopka_Security_Specifications.pdf

PDF 2 MB Posted

Attached to
Orange County Clerk of Courts Apopka And Ocoee Branch Security Upgrades
Solicitation number
Y22-7028-RC
Issued by
Orange County, Orlando City, Florida

About this file

This is a comprehensive construction and security upgrade project specification document for Orange County, Florida, specifically targeting the Apopka and Ocoee Branch locations of the Orange County Clerk of Courts. The project, designated as Y22-7028-RC, involves security upgrades with an estimated cost of $350,000.00 and was solicited through an electronic sealed bid process via the OpenGov e-Procurement Platform. Sealed offers were to be submitted by 4:00 pm EST on Tuesday, August 9, 2022, with strict requirements that respondents could only submit electronically through the designated platform.

The specification document provides detailed technical requirements for electrical, communications, and security systems installations, including comprehensive guidelines for data communications infrastructure, audio-video equipment, wiring devices, and lighting systems. The project encompasses extensive work including selective demolition, metal fabrications, rough carpentry, firestopping, and installation of various technological systems. Notably, the document emphasizes specific technical standards, installation procedures, warranty requirements, and compliance with national and local electrical and building codes, with particular attention to electronic security team standards for video management systems and communication infrastructure.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Re-Bid / Permit Issue Set 2

ARCHITECTURAL DESIGN COLLABORATIVE

PROJECT

MANUAL

FOR THE

Orange County Clerk of Courts Apopka Security Upgrades

PREPARED FOR

1111 Rock Springs Road Apopka, Florida 32712

November 11, 2019 Revised, May 04, 2022

Orange County Clerk of Courts Security Upgrades Orange County Florida

STATEMENT OF COMPLIANCE 00 0103-1

SECTION 00 0103

STATEMENT OF COMPLIANCE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. To the best of my knowledge the Plans and Specifications comply with the applicable minimum building codes and the applicable fire-safety standards as determined by the local authority in accordance with this Section and 633 Florida Statutes.

B. Reference Article 101.4 Applicability, Paragraph 101.4.2 Building of the FBC.

PART 2 - PRODUCTS – Not Used

PART 3 - EXECUTION – Not Used

END OF SECTION 00 0103

TABLE OF CONTENTS 00 0110-1

SECTION 00 0110

TABLE OF CONTENTS

DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS

00 0000 Cover 00 0103 Statement of Compliance 00 0110 Table of Contents

DIVISION 01 GENERAL REQUIREMENTS

01005 Administrative Provisions 01010 Summary of Work 01027 Application for Payment 01035 Modification Procedures 01040 Project Coordination 01045 Cutting and Patching 01095 Reference Standards and Definitions 01200 Project Meetings 01300 Submittals 01 3233 Pre-Construction Video Recordings 01380 Construction Photographs 01400 Quality Control Services 01410 Testing Laboratory Services 01600 Materials and Equipment 01631 Products Substitutions 01700 Project Close-Out 01740 Warranties and Bonds

DIVISION 02 EXISTING CONDITIONS

02 4113 Selective Demolition

DIVISION 03 CONCRETE

03 5414 Cement Based Underlayment Revised Feb. 25, 2020

DIVISION 04 MASONRY

Not Used

DIVISION 05 METALS

05 5000 Metal Fabrications

DIVISION 06 WOOD, PLASTICS, AND COMPOSITES

06 0500 Common Work Results for Wood, Plastics, and Composites 06 1000 Rough Carpentry

DIVISION 07 THERMAL AND MOISTURE PROTECTION

07 8400 Firestopping Systems 07 9000 Joint Protection Revised Feb. 25, 2020

DIVISION 08 OPENINGS

08 1100 Metal Doors and Frames 08 1416 Flush Wood Doors 08 4113 Aluminum Entrances and Storefronts Revised Jan. 22, 2021

TABLE OF CONTENTS 00 0110-2

08 7100 Finish Hardware 08 8000 Glazing 08 8700 Safety and Security Glazing Films

DIVISION 09 FINISHES

09 0162 Repair of Existing Flooring 09 2216 Non-Structural Metal Framing 09 2900 Gypsum Board 09 5100 Acoustical Ceilings 09 9000 Painting

DIVISION 10 SPECIALTIES

10 1400 Signage

DIVISIONS 11-25

Not Used

DIVISION 26 ELECTRICAL

26 0500 Common Work Results for Electrical 26 0501 Investigation of Existing Electrical Systems 26 0519 Low-Voltage Electrical Power Conductors and Cables 26 0526 Grounding and Bonding for Electrical Systems 26 0529 Hangers and Supports for Electrical Systems 26 0533 Raceway and Boxes for Electrical Systems Revised Feb. 25, 2020 26 0553 Identification for Electrical Systems 26 0923 Stand Alone Lighting Control Devices Revised Feb. 25, 2020 26 2726 Wiring Devices Revised Feb. 25, 2020 26 5100 Interior Lighting 26 5600 Exterior Lighting

DIVISION 27 COMMUNICATIONS

27 2626 Data Communications Integration Revised Apr. 29, 2020 27 4100 Audio and Video Equipment

DIVISIONS 28-49

Not Used

END OF SECTION 00 0110

ADMINISTRATIVE PROVISIONS 01005-1

SECTION 01005

ADMINISTRATIVE PROVISIONS

PART I GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

A. Work of this Contract comprises building, and related construction work to produce a complete and functional facility including but not limited to plumbing, mechanical, and electrical for the construction of renovations to office spaces.

1.2 CONTRACT METHOD

A. Construct the work under a single lump sum contract (or as otherwise defined in bid documents).

1.3 COORDINATION

A. Coordinate work of the various Sections of Specifications to assure efficient and or-derly sequence of installation of construction elements, with provisions for accom-modating items installed later.

B. Verify characteristics of elements of interrelated operating equipment are compatible;

coordinate work of various Sections having interdependent responsibilities for in-stalling, connecting to and placing in service, such equipment. Differences shall be brought to the Owner’s attention during bid process or remain the responsibility of the Contractor.

C. Coordinate space requirements and installation of items, such as, but not limited to, mechanical and electrical work which are indicated diagrammatically or otherwise on drawings. Follow routing shown for pipes, ducts and conduits, as closely as practi-cable; make runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance and for repairs.

D. In finished areas (except as otherwise shown), conceal pipes, ducts, and wiring in the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Execute cutting and patching to integrate elements of work, uncover ill timed, defec-tive and nonconforming work, provide openings for penetrations of existing surfaces and provide samples as specified in individual sections for testing. Seal penetrations of existing surfaces and provide samples as specified in individual sections for test-ing. Seal penetrations through floors, walls and ceilings, and fire safe where neces-sary as part of the lump sum price.

1.4 REFERENCE STANDARDS

A. For products specified by association or trade standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. The date of the standard is that in effect when a specified date is specified.

ADMINISTRATIVE PROVISIONS 01005-2

1.5 SUBMITTALS

A. Obtain copies of referenced standards listed in individual specification sections.

Maintain copy at job site during progress of the specific work.

END OF SECTION 01005

SUMMARY OF WORK 01010-1

SECTION 01010

SUMMARY OF WORK

PART 1 GENERAL

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

1.02 PROJECT DESCRIPTION

A. Performance of all tasks specified in the contract documents shall be the responsibil-ity of the contractor unless specified otherwise.

1.03 BUILDING/SITE SECURITY

A. The construction site, to the limits indicated on the site plan, shall be secured by means of a construction fence, located around the entire perimeter of the construc-tion site. This construction fence shall be required to be secure from unwarranted entry at the end of each day.

1.04 CONTRACTOR USE OF PREMISES

A. General: Limited use of the premises to construction activities in areas indicated within the limit of the premises. The Contractor may use any portion of the site for storage or work areas or any legal purpose.

1. Confine operations to areas within Contract limits indicated on the Drawings.

Portions of the site beyond areas in which construction operations are indi-cated are not to be disturbed.

2. Burial of Waste Materials: Do not dispose of organic and hazardous material on site, either by burial or by burning.

3. Comply with Owner’s requirements for ingress and egress procedures, pro-hibitions against firearms, procedures for transportation of workers, safety and fire prevention requirements, and all applicable pollution control re-quirements. Refer to the following reference documents:

a. Orange County Safety and Health Manual

b. Orange County Policy Manual (pg. 100 regarding firearms)

4. Require all employees and subcontractors to wear no-objectionable clothing;

prohibit revealing clothing and articles of clothing with offensive writing dis-played. Remove from premises all personnel until such clothing is changed.

5. All personnel shall abide by the Orange County Tobacco Free policy while on any Orange County property. Policy applies to buildings, parking lots, parks, break areas, and work sites. Tobacco products are defined as cigars, ciga-rettes, pipes, e-cigs, chewing tobacco and snuff. Failure to abide by the poli-

SUMMARY OF WORK 01010-2

cy may result in civil penalties levied under Chapter 386, Florida Statutes and Contract enforcement remedies.

1.05 DISTRIBUTION OF RELATED DOCUMENTS

A. The Contractor is solely responsible for the distribution of ALL related docu-ments/drawings to ALL appropriate vendors/subcontractors to ensure proper coordi-nation of all aspects of the project and its related parts during bidding and construc-tion.

1.06 CONSTRUCTION BULLETIN BOARD

A. The Contractor shall erect and maintain a weather protected bulletin board of suffi-cient size to display all permits, notices and other documents required to be posted for the Project. Said bulletin board shall be located per Owner’s direction.

1.07 SECURITY AND IDENTIFICATION

A. The building (construction area) shall be secured from unwanted entry at the end of each work day.

B. All costs for background investigations will be the Contractor’s responsibility. The

County shall have the right to request any additional investigative background infor-mation including, but not limited to, employment records, Right-to Know records, E-verify system records (If the contractor uses this service as a means to determine employee eligibility), training records, payroll records, position for which hired includ-ing site location of any personnel assigned to perform the services. Furnish, in writ-ing, all such information to the extent allowed by law, prior to commencement of ser-vices. The County reserves the right to conduct its own investigation of any employ-ee or subcontractor of the Contractor.

C. Background Checks for the Contractor’s staff must be approved by Orange County’s security team prior to working in any County facility. Obtain necessary forms for background checks for work at Orange County. All Contractor’s staff background checks will be sent to the Orange County project Manager for approval.

D. For security purposes and to maintain privacy, please submit a FDLE Background

Checks via email. The subject line of the email must contain the following

***EXEMPT***

E. Orange County will inform the Contractor of their Background Check results. Upon

Background Check approval, the contractor’s staff shall arrange an appointment with the Orange County staff to obtain an Orange County ID Badge. An Affidavit of Iden-tity form (Issued by Contractor) and a State of Florida ID or Driver’s License will be required.

F. Contractor’s employees will not be allowed in Orange county facilities without com-pleted and approved background investigations.

1.08 BUILDING/SITE SECURITY REQUIREMENTS

SUMMARY OF WORK 01010-3

A. Provide security for each and every day that work is being performed on Site. The security firm that will be used is:

G4S Security Systems (USA), Inc.

Contact: Jose Troche, MBA Phone: 407 207 3221 Jose.troche@usa.g4s.com

1.09 OWNER OCCUPANCY

A. The Owner will occupy the building and areas next to the Work area. Normal hours are 7:00 AM to 5:00 PM Monday thru Friday. Coordinate with the Owner’s repre-sentative for Work areas that can be performed on during normal work hours. Work can be performed after hours provided the area where Work is done is fully opera-tional and back in original condition prior to beginning the next business day. Such placing of equipment and partial occupancy shall not constitute acceptance of the to-tal Work.

1. A certificate of Substantial Completion will be executed for each specific por-tion of the Work to be occupied prior to Owner occupancy

2. Obtain a Certificate of Occupancy from the local building officials prior to Owner occupancy.

3. Prior to partial occupancy, mechanical and electrical systems shall be fully operational. Required inspections and tests shall have been successfully completed. Upon occupancy, the Owner will provide operation and mainte-nance of mechanical and electrical systems in occupied portions of the build-ing.

PART 2 PRODUCTS

2.01 ASBESTOS FREE MATERIAL

A. Contractor shall provide a written and notarized statement on company letterhead(s) to certify and warrant that ONLY ASBESTOS FREE MATERIALS AND PRODUCTS were provided as required by the Architect in Section 01400, QUALITY CONTROL.

Such statement shall be submitted with the final payment request. Final payment shall not be made until such statement is submitted. Contractor agrees that if mate-rials containing asbestos are subsequently discovered at any future time to have been included in the construction, the Contractor shall be liable for all costs related to the redesign or modification of the construction of the project so that materials containing asbestos are removed from the facility. If construction has begun or has been completed pursuant to a design that includes asbestos containing materials, the Contractor shall also be liable for all costs related to the abatement of such as-bestos.

PART 3 EXECUTION (Not applicable).

END OF SECTION 01010

mailto:Jose.troche@usa.g4s.com

APPLICATION FOR PAYMENT 01027-1

SECTION 01027

APPLICATION FOR PAYMENT

PART I GENERAL

1.02 SUMMARY

A. This Section specifies administrative and procedural requirements governing the Contractor’s Applications for Payment.

B. The Contractor’s Construction Schedule and Submittal Schedule are included in

Section 01300 – SUBMITTALS.

1.03 SCHEDULE OF VALUES

A. Coordinate preparation of the Schedule of Values with preparation of Contractor’s Construction Schedule.

1. Submit the Schedule of Values to the Owner at the earliest feasible date, but in no case later than Preconstruction Meeting.

2. Sub-Schedules: Where the Work is separated into phases that require separately phased payments, provide sub-schedules showing values correlated with each phase of payment.

B. Format and Content: Use the Project Manual Table of Contents as a guide to establish the format for the Schedule of Values.

1. Identification: Include the following project identification on the Schedule of

Values:

a. Project name and location.

b. Name of the Architect

c. Project Number

d. Contractor’s name and address

e. Date of submittal

2. Arrange the Schedule of Values in a tabular form with separate columns to indicate the following for each item listed:

a. Generic name

b. Related Specification Section

c. Change Orders (numbers) that have affected value

d. Dollar Value

e. Percentage of Contract Sum to the nearest one-hundredth percent, adjusted to total 100 percent

APPLICATION FOR PAYMENT 01027-2

3. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports.

Break principal subcontract amounts down into several line items:

a. A value will be given for at least every major specification section

(subsections can logically be grouped together).

b. A single material subcontractor (i.e. sod, window blinds) will not be required to be broken down into labor and material unless it is anticipated the materials will be stored and invoiced prior to installation.

c. All multiple item subcontracts or work items (i.e. concrete, roofing, painting, mechanical, electrical items, etc.) will be shown broken down at least in labor and material (all taxes, burden and overhead and profit included).

d. Mobilization (move-on, bond, insurance, temporary office and sanitary service installation) shall not exceed 2 1/2% of contract price.

e. For multi-story work all items broken down per floor.

f. Concrete broken down at least into foundation slab on grade, columns, beams and suspended slabs.

g. Masonry divided into C.M.U. brick, stem walls, exterior walls, interior walls and elevator shaft.

h. Plumbing broken down at least into underslab rough-in, vents and stacks supply piping, equipment items (each listed separately), fixtures and trim.

I. HVAC: Typically shown per specification section, labor and material, per floor.

j. Electrical: same as HVAC.

k. Fire protection broken down at least into underground, rough-in and trim. All per building and labor and material.

l. Logical grouping of specification subsections is permitted.

4. Round amounts off the nearest whole dollar, the total shall equal the Contract Sum.

5. For each part of the Work where an Application for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed, provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

6. Margins of Cost: Show line items for indirect costs, and margins on actual costs, only to the extent that such items will be listed individually in Applications for Payment. Each item in the Schedule of Values and Applications for Payment shall be complete including its total cost and proportionate share of general overhead and profit margin.

a. At the Contractors’ option, temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown as separate line items in the Schedule of Values or distributed as general overhead expense.

APPLICATION FOR PAYMENT 01027-3

7. Schedule Updating: Update and resubmit the Schedule of Values when Change Orders or Construction Change Directives result in a change in the contract sum.

1.04 APPLICATIONS FOR PAYMENT

A. Each Application for Payment shall be consistent with previous applications and payments as reviewed by the Owner representative and paid for by the Owner.

1. The initial Application for Payment, the Application for Payment at time of

Substantial Completion, and the Final Application for Payment involve additional requirements.

B. Payment Application Times: The period of construction work covered by each

Application of Payment is the period indicated in the Agreement.

C. Payment Application Forms: Use the County’s most updated form as the form for Application for Payment. Form given at the Preconstruction Conference.

D. Application Preparation: Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the Owner.

Incomplete applications will be returned without action.

1. Entries shall match data on the Schedule of Values and Contractors’

Construction Schedule. Use updated schedules if revisions have been made.

2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.

E. Transmittal: Submit five (5) original executed copies of each Application for

Payment to the Project Manager by means ensuring receipt within 24 hours; one copy shall be complete, including waivers of lien and similar attachments, when required.

1. Transmit each copy with a transmittal form listing attachments, and recording appropriate information related to the application in a manner acceptable to the Project Manager.

F. Payment will be processed once a month. Payment for item will be based on percentage completed as determined and approved by the County Project Manager or invoice for stored materials. Retainage (10%) will be held for all applications.

G. Application for Payment at Substantial Completion: Following issuance of the

Certificate of Substantial Completion, submit an Application for Payment; this application shall reflect any Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work. Application shall also include all items listed in Part H. above.

H. Final Payment Application: Administrative actions and submittals, which must

APPLICATION FOR PAYMENT 01027-4

precede or coincide with submittal of the final payment. Application for Payment includes the following:

1. Completion of Project Close-Out requirements

2. Completion of items specified for completion after Substantial

Completion (Punch List)

3. Contractor’s release of lien (on Owner’s form)

4. Subcontractor and material supplier release of lien (If applicable)

5. Consent of Surety

6. Power of attorney

7. Asbestos-free letter, notarized

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

END OF SECTION 01027

MODIFICATION PROCEDURES 01035-1

SECTION 01035

MODIFICATION PROCEDURES

Conditions and other Division 1 Specification Sections, apply to this section.

A. This section specifies administrative and procedural requirements for handling and processing Contract modifications.

1.03 MINOR CHANGES IN THE WORK

A. Supplemental instructions authorizing minor changes in the work, not involving an adjustment to the Contract Sum or Contract Time, will be issued by the Project Manager.

1.04 CHANGE ORDER PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Proposed changes in the work that will require adjustment to the Contract Sum or Contract Time will be issued by the Project Manager, with a detailed description of the proposed change and supplemental or revised Drawings and Specifications, if necessary.

1. Proposal requests issued by the Project Manager are for information only. Do not consider them instruction either to stop work in progress, or to execute the proposed change.

2. Unless otherwise indicated in the proposal request, within 7 days of receipt of the proposal request, submit to the Project Manager from the Owner's review, an estimate of cost necessary to execute the proposed change.

a. Include a list of quantities of products to be purchased and unit costs, along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include a statement indicating the effect the proposed change in the work will have on the Contract Time.

d. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amount.

B. Contractor-Initiated Change Order Proposal Requests: When latent or other unforeseen conditions in mutual accord with the Owner Representative∋s findings require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Architect.

MODIFICATION PROCEDURES 01035-2

1. Include a statement outlining the reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and Contract Time.

2. Include a list of quantities of products to be purchased and unit costs along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Comply with requirements in Section 01631 − Product Substitutions- if the proposed change in the work requires that substitution of one product or system for a product or system not specified.

5. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amounts.

1.05 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: When the Owner and Contractor are not in total agreement on the terms of a Change Order Proposal Request, the Project Manager may issue a Construction Change Directive instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. The Construction Change Directive will contain a complete description of the change in the Work and designate the method to be followed to determine change in the Contract Sum or Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of the change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

1.07 CHANGE ORDER PROCEDURES

A. Upon the Owner's approval of a Change Order Proposal Request, the Project

Manager will issue a Change Order for signatures of the Owner and Contractor on County's Change Order form, as provided in the Conditions of the Contract.

PART 3 EXECUTION (Not Applicable)

END OF SECTION 01035

PROJECT COORDINATION 01040-1

SECTION 01040

PROJECT COORDINATION

Conditions and other Division 1 Specification Sections, apply to this Section.

A. This Section specifies administrative and supervisory requirements necessary for project coordination including, but not necessarily limited to:

1. Coordination

2. Administrative and supervisory personnel

3. General installation provisions

4. Cleaning and protection

B. Progress meetings, coordination meetings And Pre-installation conferences are included in Section 01200 ‘Project Meetings’.

C. Requirements for the Contractor’s Construction Schedule are included in Section 01300 ‘Submittals’.

1.03 COORDINATION

A. Coordination: Coordinate construction activities included under various Sections of these Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included under different Sections of the Specification that are dependent upon each other for proper installation, connection, and operation.

1. Where installation of one part of the Work is dependent on installation of other components, either before or after its own installation, schedule construction activities in the sequence required to obtain the best results.

2. Where availability of space is limited, coordinate installation of different components to assure maximum accessibility for required maintenance, service and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Where necessary, prepare memoranda for distribution to each party involved outlining special procedures required for coordination. Include such items as required: notices, reports, and attendance at meetings.

1. Prepare similar memoranda for the Owner and separate Contractors where coordination of their Work is required.

PROJECT COORDINATION 01040-2

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Schedules

2. Installation and removal of temporary facilities

3. Delivery and processing of submittals

4. Progress meetings

5. Project close-out activities

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials.

1. Salvage materials and equipment (if any) involved in performance of, but not actually incorporated in, the Work.

E. Lack of coordination as specified in this and other sections of the contract documents are in grounds for assessment of back charges and/or termination in order to remediate the situation.

1.04 SUBMITTALS

A. Coordination Drawings: Prepare and submit coordination Drawings where close and careful coordination is required for installation of products and materials fabricated off-site by separate entities, and where limited space availability necessitates maximum utilization of space for efficient installation of different components.

1. Show the interrelationship of components shown on separate Shop

Drawings.

2. Indicate required installation sequences.

3. Comply with requirements contained in Section Submittals.

4. Refer to Facility Services documents for specific coordination Drawing requirements for mechanical and electrical installations.

B. Staff Names: At the Preconstruction Conference submit a list of the Contractor’s principal staff assignments, including the Superintendent and other personnel in attendance at the site; identify individuals, their duties and responsibilities; list their addresses and telephone numbers.

1. Post copies of the list in the project meeting room, the temporary field office, and each temporary telephone.

PART 3 EXECUTION

PROJECT COORDINATION 01040-3

3.01 GENERAL INSTALLATION PROVISIONS

A. Inspection of Conditions: Require the Installer of each major component to inspect both the substrate and conditions under which work is to be performed. Do not proceed until unsatisfactory conditions have been corrected in an acceptable manner.

B. Manufacturer’s Instructions: Comply with manufacturer’s installation instructions and recommendations, to the extent that those instructions and recommendations are more explicit or stringent than requirements contained in Contract Documents.

C. Inspect materials or equipment immediately upon delivery and again prior to installation. Reject damaged and defective items.

D. Provide attachment and connection devices and methods necessary for securing work. Secure work true to line and level. Allow for expansion and building movement.

E. Visual Effects: Provide uniform joint widths in exposed work. Arrange joints in exposed work to obtain the best visual effect. Refer questionable choices to Project Manager for final decision.

F. Recheck measurements and dimensions, before starting each installation.

G. Install each component during weather conditions and Project status that will ensure the best possible results. Isolate each part of the completed construction from incompatible material as necessary to prevent deterioration.

H. Coordinate temporary enclosures with required inspections and tests, to minimize the necessity of uncovering completed construction for that purpose.

I. Mounting Heights: Where mounting heights are not indicated, install individual components at standard mounting heights recognized within the industry for the particular application indicated. Refer questionable mounting height decisions to the Architect/Project Manager for final decision.

3.02 CLEANING AND PROTECTION

A. During handling and installation, clean and protect construction in progress and adjoining materials in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

B. Clean and maintain completed construction as directed by the Project Manager and as frequently as necessary to ensure its integrity and safety through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

C. Limiting Exposures: Supervise construction activities to ensure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period. Where the

PROJECT COORDINATION 01040-4

applicable, such exposures include, but are not limited to, the following:

1. Excessive static or dynamic loading

2. Excessively high or low temperatures

3. Excessively high or low humidity

4. Air contamination or pollution

5. Water

6. Solvents

7. Chemicals

8. Soiling, staining and corrosion

9. Rodent and insect infestation

10. Combustion

11. Destructive testing

12. Misalignment

13. Excessive weathering

14. Unprotected storage

15. Improper shipping or handling

16. Theft

17. Vandalism

END OF SECTION 01040

CUTTING AND PATCHING 01045-1

SECTION 01045

CUTTING AND PATCHING

A. This Section specifies administrative and procedural requirements for cutting and patching.

B. Refer to other Sections for specific requirements and limitations applicable to cutting and patching individual parts of the Work.

1. Requirements of this Section apply to mechanical and electrical installations.

Refer to Facility Services Sections for other requirements and limitations applicable to cutting and patching mechanical and electrical installations.

1.03 SUBMITTALS

A. Cutting and Patching Proposal: Where approval of procedures for cutting and patching is required before proceeding, submit a proposal describing procedures well in advance of the time cutting and patching will be performed and request approval to proceed. Include the following information, as applicable, in the proposal:

1. Describe the extent of cutting and patching required and how it is to be performed; indicate why it cannot be avoided.

2. Describe anticipated results in terms of changes to existing construction;

include changes to structural elements and operating components as well as changes in the building’s appearance and other significant visual elements.

3. List products to be used and firms or entities that will perform Work.

4. Indicate dates when cutting and patching is to be performed.

5. List utilities that will be disturbed or affected, including those that will be relocated and those that will be temporarily out-of-service. Indicate how long service will be disrupted.

6. Where cutting and patching involves addition of reinforcement to structural elements, submit details and engineering calculations to show how reinforcement is integrated with the original structure.

7. Approval by the Architect to proceed with cutting and patching does not waive the Architect’s right to later require complete removal and replacement

CUTTING AND PATCHING 01045-2

of a part of the Work found to be unsatisfactory.

1.04 QUALITY ASSURANCE

A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that would reduce their load carrying capacity or load-deflection ratio.

1. Obtain approval of the cutting and patching proposal before cutting and patching the following structural elements.

a. Foundation construction

b. Bearing and retaining walls

c. Structural concrete

d. Structural steel

e. Lintels

f. Timber and primary wood framing

g. Structural decking

h. Miscellaneous structural metals I. Stair systems

j. Exterior curtain wall construction

k. Equipment supports

l. Piping, ductwork, vessels and equipment

B. Operational and Safety Limitations: Do not cut and patch operating elements or safety related components in a manner that would result in reducing their capacity to perform as intended, or result in increased maintenance, or decreased operational life or safety.

1. Obtain approval of the cutting and patching proposal before cutting and patching the following operating elements or safety related systems.

a. Shoring, bracing and sheeting

b. Primary operational systems and equipment

c. Air or smoke barriers

d. Water, moisture, or vapor barriers

e. Membranes and flashings

f. Fire protection systems

g. Noise and vibration control elements and systems

h. Control systems I. Communication systems

j. Conveying systems

k. Electrical wiring systems

C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces, in a manner that would, in the Architect’s opinion, reduce the building’s aesthetic qualities, or result in visual evidence of cutting and patching.

Remove and replace work cut and patched in a visually unsatisfactory manner.

1. If possible retain the original installer or fabricator to cut and patch the following categories of exposed work, or if it is not possible to engage the original installer or fabricator, engage another recognized experienced and

CUTTING AND PATCHING 01045-3

specialized firm:

a. Processed concrete finishes

b. Preformed metal panels

c. Window wall system

d. Stucco and ornamental plaster

e. Acoustical ceilings

f. Carpeting

g. Wall covering

h. HVAC enclosures, cabinets or covers I. Roofing systems

2.01 MATERIALS

A. Use materials that are identical to existing materials. If identical materials are not available or cannot be used where exposed surfaces are involved, use materials that match existing adjacent surfaces to the fullest extent possible with regard to visual effect unless otherwise indicated by Architect/Owner. Use materials whose installed performance will equal or surpass that of existing materials.

3.01 INSPECTION

A. Before cutting existing surfaces, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. Take corrective action before proceeding, if unsafe or unsatisfactory conditions are encountered.

1. Before proceeding, meet at the site with all parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.

3.02 PREPARATION

A. Temporary Support: Provide temporary support of work to be cut.

B. Protection: Protect existing construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.

C. Avoid interference with use of adjoining areas and interruption of free passage to adjoining areas.

D. Take all precautions necessary to avoid cutting existing pipe, conduit or ductwork serving the building, but scheduled to be removed or relocated until provisions have been made to bypass them.

3.03 PERFORMANCE

CUTTING AND PATCHING 01045-4

A. General: Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay.

1. Cut existing construction to provide for installation of other components or performance of other construction activities and the subsequent fitting and patching required to restore surfaces to their original condition.

B. Cutting: Cut existing construction using methods least likely to damage elements to be retained or adjoining construction. Where possible review proposed procedures with the original installer; comply with the original installer’s recommendations.

1. In general, where cutting is required use hand or small power tools designed for sawing or grinding, not hammering and chopping. Cut holes and slots neatly to size required with minimum disturbance of adjacent surfaces.

Temporarily cover openings when not in use.

2. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.

3. Cut through concrete and masonry using a cutting machine such as a Carborundum saw or diamond core drill.

4. By-pass utility services such as pipe or conduit, before cutting, where services are shown or required to be removed. Cap, valve or plug and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after by-passing and cutting.

C. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.

1. Where feasible, inspect and test patched areas to demonstrate integrity of the installation.

2. Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.

3. Where removal of walls or partitions extends one finished area into another, patch and repair floor and wall surfaces in the new space to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials if necessary to achieve uniform color and appearance.

a. Where patching occurs in smooth painted surfaces, extend final coat over entire unbroken surfaces containing the patch, after the patched area has received primer and second coat.

3.04 CLEANING

A. Thoroughly clean areas and spaces where cutting and patching is performed or used

CUTTING AND PATCHING 01045-5

as access. Remove completely paint, mortar, oils, putty and items of similar nature.

Thoroughly clean piping, conduit and similar features before painting or other finishing is applied. Restore damaged materials to their original condition.

END OF SECTION 01045

REFERENCE STANDARDS AND DEFINITIONS 01095-1

SECTION 01095

REFERENCE STANDARDS AND DEFINITIONS

1.02 DEFINITIONS

A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. Indicated: The term indicated refers to graphic representations, notes or schedules on the Drawings, or other Paragraphs or Schedules in the Specifications, and similar requirements in the Contract Documents. Where terms such as shown, noted, scheduled and specified are used, it is to help the reader locate the reference; no limitation on location is intended.

C. Directed: Terms such as directed, requested, authorized, selected, accepted, required, and permitted mean directed by the Project Manager, requested by the Architect/Project Manager and similar phrases.

D. Approved: This term approved means accepted, where used in conjunction with the

Architect's action on the Contractor's submittals, applications, and requests, is limited to the Architect's duties and responsibilities as stated in the Conditions of the Contract.

E. Regulations: The term Regulations includes laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, as well as rules, conventions, and agreements within the construction industry that control performance of the Work.

F. Furnish: The term furnish is used to mean supply and deliver to the Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

G. Install: The term install is used to describe operations at project site including the actual unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

H. Provide: The term provide means to furnish and install, complete and ready for the intended use.

I. Installer: An Installer is the Contractor or an entity engaged by the Contractor, either as an employee, subcontractor, or contractor of lower tier for performance of a particular construction activity, including installation, erection, application, and similar operations. Installers are required to be experienced in the operations they are engaged to perform.

1. The term experienced, when used with the term Installer, means having a minimum of five previous projects similar in size and scope to this Project, REFERENCE STANDARDS AND DEFINITIONS 01095-2 being familiar with the special requirements indicated, and having complied with requirements of the authority having jurisdiction.

2. Trades: Use of titles such as carpentry is not intended to imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as carpenter. It also does not imply that requirements specified apply exclusively to trades persons of the corresponding generic name.

J. Project Site is the space available to the Contractor for performance of construction activities, either exclusively or in conjunction with others performing other work as part of the Project. The extent of the Project Site is shown on the Drawings and may or may not be identical with the description of the land on which the Project is to be built.

K. Testing Laboratories: A testing laboratory is an independent entity engaged to perform specific inspections or tests, either at the Project sites or elsewhere, and to report on and, if required, to interpret results of those inspections or tests.

L. Florida Building Code (FBC): Where the term or acyronym is used it will mean the current edition of the Florida Building Code with all applicable revisions adopted by the authorities having jurisdictions at the location of the Project.

1.03 SPECIFICATION FORMAT AND CONTENT EXPLANATION

A. Specification Format: These Specifications are organized into Divisions and Sections based on the Construction Specifications Institute's MASTER FORMAT 1995 and 2014 numbering system.

B. Specification Content: This Specification uses certain conventions in the use of language and the intended meaning of certain terms, words, and phrases when used in particular situations or circumstances. These conventions are explained as follows:

1. Abbreviated Language: Language used in Specifications and other

Contract Documents is the abbreviated type. Words and meaning shall be interpreted as appropriate. Words that are implied, but not stated shall be interpolated as the sense required. Singular words will be interpreted as plural and plural words interpreted as singular where applicable and the context of the Contract Documents so indicates.

2. Imperative and streamlined language is used generally in the Specifications.

Requirements expressed in the imperative mood are to be performed by the Contractor. At certain locations in the text, for clarity, subjective language is used to describe responsibilities that must be fulfilled indirectly by the Contractor, or by others when so noted.

a. The words, shall be shall be included by inference wherever a colon

(:) is used within a sentence or phrase.

1.04 INDUSTRY STANDARDS

REFERENCE STANDARDS AND DEFINITIONS 01095-3

A. Applicability of Standards: Except where the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copies directly into the Contract Documents to the extend reference. Such standards are made part of the Contract Documents by reference.

B. Publication Dates: Comply with the standard in effect as of the date of the

Contract Documents.

C. Conflicting Requirements: Where compliances with two or more standards are specified, and the standards may establish different or conflicting requirements for minimum quantities or quality levels. Refer requirements that are different, but apparently equal, and uncertainties to the Architect for a decision before proceeding.

1. Minimum Quantity or Quality Levels: The quantity of quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. In complying with these requirements, indicated numeric values are minimum or maximum, as appropriate for the context of the requirements. Refer uncertainties to the Architect/Owner for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on the Project is required to be familiar with industry standards applicable to that entity's construction activity.

Copies of applicable standards are not bound with the Contract Documents.

1. Where copies of standards are needed for performance of a required construction activity. The Contractor shall obtain copies directly from the publication source or any other authorized source.

E. Abbreviations and Names: Trade association names and titles of general standards are frequently abbreviated. Where such acronyms or abbreviations are used in the Specifications or other Contract Documents, they mean the recognized name of the trade association, standards generating organization, authority having jurisdiction, or other entity applicable to the context of the text provision. See Trade Reference List at the end of this Section refer to the Encyclopedia of Associations, published by Gale Research Co., available in most libraries.

1.05 SUBMITTALS

A. Permits, Licenses, and Certificates: For the Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, and similar documents, correspondence, and records established in conjunction with compliance with standards and regulation bearing upon performance of the Work.

(Not Applicable)

REFERENCE STANDARDS AND DEFINITIONS 01095-4

END OF SECTION 01095

PROJECT MEETINGS 01200-1

SECTION 01200

PROJECT MEETINGS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.

A. This Section specifies administrative and procedural requirements for project meetings including but not limited to:

1. Pre-Construction Conference

2. Pre-Installation Conference

3. Coordination Meetings

4. Progress Meetings

B. Construction schedules are specified in Section 01300 Submittals.

1.03 PRE-CONSTRUCTION CONFERENCE

A. Schedule a pre-construction conference and organizational meeting at the project site or other convenient location no later than 20 days after execution of the agreement and prior to commencement of construction activities. Conduct the meeting to review responsibilities and personnel assignments.

B. Attendees: The OWNER’S Representative, Architect, the Contractor and its superintendent, major subcontractors, manufacturers, suppliers and other concerned parties shall each be represented at the conference by persons familiar with and authorized to conclude matters relating to the work.

C. Agenda: Discuss items of significance that could affect progress including such topics as:

1. Tentative construction schedule

2. Critical Work sequencing and/coordinating

3. Designation of responsible personnel

4. Procedures for processing field decisions and Change Orders

5. Procedures for processing Applications for Payment

6. Distribution of Contract Documents

7. Submittal of Shop Drawings, Product Data and Samples

8. Preparation of record documents

9. Use of the Premises

10. Office, Work and storage areas

11. Equipment deliveries and priorities

12. Safety procedures

13. First aid

PROJECT MEETINGS 01200-2

14. Security

15. Housekeeping

16. Working hours

D. Contractor must submit at the time of the meeting at least the following items:

1. Schedule of Values

2. Listing of key personnel including project superintendent and subcontractors with their addresses, telephone numbers, and emergency telephone numbers.

3. Preliminary Construction Schedule

4. Submittal Schedule

1.04 PRE-INSTALLATION CONFERENCE

A. Conduct a Pre-installation conference at the site before each construction activity that requires coordination with other construction. The Installer and representatives of manufacturers and fabricators involved in or affected by the installation, and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise at least 48 hours in advance the Project Manager of scheduled meeting dates.

1. Review the progress of other construction activities and preparations for the particular activity under consideration at each pre-installation conference, including requirements for:

a. Contract Documents

b. Options

c. Related Change Orders

d. Purchases

e. Deliveries

f. Shop Drawings, Product Data and…